The City of Bismarck, North Dakota (City) appeals the district court’s 1 September 26, 1984 order staying the instant litigation pending resolution of the disputes in arbitration between the City and Minn-Kota Excavating, Inc. (Minn-Kota). The court had made an earlier finding in a declaratory action between the City and Minn-Kota that the disputes were referable to arbitration under the arbitration clause of the parties’ construction contract. Minn-Kota urges that the City should be collaterally estopped in this action because of the district court’s earlier finding. The City, in addition, argues Minn-Kota is not entitled to a stay of the litigation pursuant to the Federal Arbitration Act, 9 U.S.C. § 3 (1982), because it failed to give proper notice of its claims as required by the parties’ contract. We reject the City’s contentions and affirm the order of the district court.
Factual and Procedural Background
The City and Minn-Kota, a Minnesota corporation, entered into a construction contract on June 23, 1981 in which MinnKota agreed to construct a sanitary sewer addition to the City’s existing sewer system. After disputes arose between the parties, the City brought an action against Minn-Kota seeking a declaratory judgment that the disputes between them arising from the performance of the contract were not arbitrable. By a final order dated December 30, 1982, the district court held the parties had agreed to arbitrate such disputes and ordered the parties to proceed to arbitration. The City did not appeal the judgment entered.
In April 1984 the City commenced the instant action against Minn-Kota; Toltz, King, Duvall, Anderson and Associates, Inc. (TKDA); and St. Paul Fire and Marine Insurance Company (St. Paul) asserting its claims arising from the contract. MinnKota responded that the disputes between the City and Minn-Kota concerning the project are to be resolved by arbitration pursuant to the contract, and that the City’s lawsuit was barred by a prior decision of the court which was res judicata. Because it had previously ordered the City and Minn-Kota to proceed to arbitration, the district court ordered a stay of the proceedings pending such arbitration. The City appeals from this order.
Analysis
This court has jurisdiction over the district court’s order. In
Mellon Bank, N.A. v. Pritchard-Keang Nam Corp.,
Under the doctrine of res judicata, a final judgment on the merits of an action precludes the parties or their privies from relitigating issues that were or could have been raised in that action.
Federated Department Stores, Inc. v. Moitie,
The City contends, however, that controlling legal principles have changed since the district court’s earlier decision and special circumstances warrant a reconsideration of the arbitration issue in this action. Under
Montana,
the City’s assertions are properly considered in determining the appropriate application of collateral estoppel.
Id.
at 155,
While it is true the district court in its December 30, 1982 order construed the arbitration clause according to North Dakota law, the contract in this case is clearly governed by federal law. The district court’s order now on appeal granted the defendants’ motion to stay, which was brought pursuant to section 3 of the Arbitration Act. The district court granted the stay “pursuant to 9 U.S.C. § 3.” At oral argument, counsel for the City conceded the written arbitration provision is part of a “contract evidencing a transaction involving commerce” within the meaning of 9 U.S.C. § 2. Interpretation of an arbitration agreement affecting commerce is determined by federal law.
Mediterranean Enterprises, Inc. v. Ssangyong Corp.,
We next consider the City’s argument that Minn-Kota has forfeited its claims by failing to give proper notice as required by section 30.1 of the Additional Supplemental General Conditions of the contract. Although the district court apparently did not decide in the earlier declaratory action whether proper notice was given, it found in the instant case that “[tjhere has. been no showing that the applicants for the stay, Minn-Kota, and its liability carrier, St. Paul Fire and Marine, are in default in proceeding with such arbitration.” Section 3 of the Arbitration Act provides: 9 U.S.C. § 3 (1982) (emphasis added). The City has failed to prove the district court’s factual finding of no procedural default was clearly erroneous. We also refer to
Contracting Northwest, Inc. v. City of Fredericksburg, Iowa,
If any suit or proceeding be brought in any of the courts of the United States upon any issue referable to arbitration under an agreement in writing for such arbitration, the court in which such suit is pending, upon being satisfied that the issue involved in such suit or proceeding is referable to arbitration under such an agreement, shall on application of one of the parties stay the trial of the action until such arbitration has been had in accordance with the terms of the agreement, providing the applicant for the stay is not in default in proceeding with such arbitration.
Finally, we address the propriety of the district court’s grant of the stay pending arbitration. A trial court’s stay of an action will be overturned only for abuse of discretion.
See Mediterranean Enterprises,
While it is true that the arbitrator’s findings will not be binding as to those not parties to the arbitration, considerations of judicial economy and avoidance of confusion and possible inconsistent results nonetheless militate in favor of staying the entire action.
Moreover, in
Contracting Northwest,
Section 3 of the Arbitration Act, which permits a court to stay “any suit ... brought in any of the courts of the United States upon any issue referable to arbitration,” is broad enough to permit the stay of litigation between nonarbitrating parties as long as that lawsuit is based on issues referable to arbitration under an arbitration agreement governed *433 by the Arbitration Act. 9 U.S.C. § 3 (emphasis added). In any event, the district court had the inherent power to grant the stay in order to control its docket, conserve judicial resources, and provide for a just determination of the cases pending before it.
See also Mediterranean Enterprises,
Notes
. The Honorable Bruce M. Van Sickle, United States District Judge for the District of North Dakota.
.
If the arbitration agreement in
Wagner Bros.
had been one involving commerce and therefore governed by federal law, the North Dakota statute rendering arbitration agreements unenforceable no doubt would have been preempted by the Federal Arbitration Act under
Southland Corp. v. Keating,
