City of Binghamton v. Hawk Engineering P.C.City of Binghamton v. Hawk Engineering P.C.
In 2003, defendant, an engineering firm, entered into a contract to provide plaintiff with a design for the rehabilitation of a bridge. Defendant delivered the plans in September 2005 and submitted its final bill in November 2005. The bridge was completed in October 2007. In December 2007, the Department of Transportation (hereinafter DOT) inspected the bridge, discovered cracking in certain structures, and issued a “Red Flag report” recommending a check of the capbeam cantilеver design. Plaintiff engaged McFarland-Johnson, Inc. (hereinafter McFarland), another engineering firm, to perform a strength analysis of the pier cap cantilevers. In January 2008, the firm reported that the structures’ strength was inadequate. In March 2008, plaintiff reported these findings to defendant and requested that it review its design computations. Defendant engaged a third engineering firm, Modjeski and Mаsters (hereinafter M & M), to review its design. M & M identified certain design errors and recommended repairs. Plaintiff asked defendant to pay for these repairs in June 2008. Thereafter, DOT found increased cracking in the bridge structures and issued a second Red Flag report. Plaintiff again asked defendant to contract and pay for the repair, and defendant turned the matter over to its attorney and insurаnce carrier.
In April 2009, plaintiff commenced this action alleging breach of contract, negligence and professional malpractice. Defendant moved for summary judgment dismissing thе complaint, and plaintiff cross-moved for summary judgment on the issue of de
Initially, Supreme Court properly determined that plaintiff‘s claim is essentially one for professional malpractice and, thus, the three-year limitations period of
Plaintiff next contends that Supreme Court erred in determining that its malpractice claim accrued no later than November 2005, arguing that the cause of action did not accrue until construction of the bridge was complete. We disagree. Ordinarily, “a claim for professional malpractice against an engineer or architect accrues upon the completion of performance under the contract and the consequent termination of the parties’ professional relationship” (Town of Wawarsing v Camp, Dresser & McKee, Inc., 49 AD3d 1100, 1101-1102 [2008]). Plaintiff‘s argument regarding the termination date is based upon a contractual provision that required defendant to “provide design response to unanticipated or changed field conditions, analyze and partic
“[W]e look to the parties’ intent as embodied in their agreement to determine when their professional relationship ended” (Town of Wawarsing v Camp, Dresser & McKee, Inc., 49 AD3d at 1102). The termination “must be judicially interpreted in light of the given situation and the responsibilities of thе parties in carrying out their agreement” (Board of Educ. of Tri-Val. Cent. School Dist. at Grahamsville v Celotex Corp., 88 AD2d 713, 714 [1982], affd 58 NY2d 684 [1982]). Here, the parties’ agreement, read as a whole, embodies their intеnt for their professional relationship to terminate upon submission of defendant‘s final design or, at the latest, upon final payment for that design, except in the event of contingenciеs that did not occur. Accordingly, Supreme Court properly concluded that the malpractice cause of action accrued, at the latest, in November 2005, when defendant submittеd its final bill for preconstruction design services.
Plaintiff next contends that the statute of limitations was tolled by the doctrine of continuous representation, which “recognizes that a person seeking professional assistance has a right to repose confidence in the professional‘s ability and good faith, and realistically cannot be expected to question and assess the
Finally, plaintiff asserts that defendant is estopped from relying on the statute of limitations as it worked and corresponded with plaintiff after discovery of the design defect. “Equitable estoppel is an extraordinary remedy which applies where a party is prevented from filing an action within the aрplicable statute of limitations due to his or her reasonable reliance on deception, fraud or misrepresentations by the other” (Pulver v Dougherty, 58 AD3d 978, 979-980 [2009] [internal quotation marks, brackets and citations omitted]; see Dombroski v Samaritan Hosp., 47 AD3d 80, 82-83 [2007]). Plaintiff did not meet its burden to establish by clear and convincing evidence that defendant engaged in affirmative misconduct (see Cellupica v Bruce, 48 AD3d 1020, 1021 [2008]). Defendant‘s initial cooperation with рlaintiff‘s requests to review its design calculations and devise a solution to the problem did not constitute decep
Peters, J.P., Spain, McCarthy and Egan Jr., JJ., concur.
Ordered that the order is affirmed, without costs.