161 N.E. 80 | Ill. | 1928
The city of Belvidere, Illinois, by its proper officials passed an ordinance during May, 1926, providing for the paving and otherwise improving of South State street and Logan avenue under the Local Improvement act. It appears the improvement is a part of Grant highway, or Route 5 of the State hard road system. The estimated cost of the improvement was $100,000, one-half of which, it seems, was to be paid for by the city at large. An assessment roll was prepared, filed and confirmed and the improvement work was performed during the summer of 1927. The board of local improvements filed its certificate of cost and completion of the work, under section 84 of the Local Improvement act, in the county court of Boone county, showing the work to have been completed substantially according to the original improvement ordinance and at a cost slightly in excess of $88,500. Fifty-seven owners of property affected by the improvement assessment filed objections to the certificate and a hearing was had thereon. There was no objection as to whether or not the improvement was constructed substantially as required by the original ordinance. The objection was that the certificate of completion included in the total cost of the improvement various items, charges and extras, amounting to $20,000, which were entirely outside of the cost of the work and not provided for by the original improvement ordinance. The several items or extras were set out in detail in the objections filed. A bill of particulars was required of and was furnished by the city, wherein it was recited that "in compliance with order of court heretofore made for bill of particulars, presents the following items, all of which were necessary and proper in the estimation of said city of Belvidere and its officers for the proper completion and necessary to the using of said streets and said improvement and were fully ordered and authorized to be done as additional *33 or extra work not provided for in said contract, and all of which said extra or additional items of construction, at the prices charged herein, were and are reasonable and fair at the price and cost herein charged and set out." Then follows a statement of the contract price of the work, together with sixteen separate items designated as "extra work ordered by board of local improvements and necessary to the completion of said contract," which amount to almost $20,000. It was also admitted on the hearing by the city's engineer in charge, that some of the items set out in the bill of particulars were additional work not provided for in the ordinance but such as was needed to make a good improvement. The city's attorney also explained and admitted that one of the items designated as "replacing water service" was included within the cost of the work, and that such water connections for the respective properties were installed under authority of another city ordinance. The county court, among other things, found that the improvement conformed substantially to the requirements of the improvement ordinance. Three items, in amount of approximately $2170, as set out in the bill of particulars as "extras," were disallowed by the court, but the other items therein, which were in excess of $17,700, were approved as a part of the total cost of the work, which the court found to be $87,168.88. From the order there entered the objectors sought and were allowed an appeal. Thirty-eight of the objectors have accordingly prosecuted an appeal to this court.
The real controversy in this case was caused by a large amount of extras, or additional work, which it is claimed were not included within the contract or improvement ordinance, being made a part of the cost thereof by the board of local improvements; and it is contended by appellants that the county court having approved the major part of such extras as a part of the cost, has thereby exceeded its jurisdiction under section 84 of the Local Improvement act. *34
Section 84 (Smith's Stat. 1927, chap. 24, p. 503,) provides, in substance, that within thirty days after the final completion and acceptance of the work the board of local improvements shall cause the cost thereof, including engineering services, to be certified in writing to the court in which the assessment was confirmed, together with an amount estimated by the board to be required to pay the accruing interest on bonds or vouchers issued to anticipate collection; and in every case in which the assessment shall be divided into installments the board is also required to state in its certificate whether or not the improvement conforms substantially to the requirements of the original ordinance for the construction of the improvement and to make application to said court to consider and determine whether or not the facts stated in the certificate are true. The court, after legal notice given, is required to proceed to hear such application and any objections which may be properly filed thereto. The board's certificate shall be prima facie evidence that the things stated therein are true, but if any part thereof is controverted by objections filed, then the court shall hear and determine the same in a summary manner and "enter an order according to the fact." The section further provides that such order shall be conclusive upon all the parties and no appeal therefrom or writ of error thereto shall be allowed to review or reverse the same.
Appellee contends that as the objectors admitted the improvement conforms substantially to the ordinance and the court having had jurisdiction of the property and persons assessed for the improvement, the only question of fact presented to the court for determination was as to the total cost of the improvement, and the court having determined that fact, under section 84 there can be no review of the court's order. Appellee also contends no valid appeal has been perfected.
Section 95 of the Local Improvement act (Smith's Stat. 1927, p. 507,) provides that appeals from final judgments *35
or orders of any court made in proceedings under the act may be brought to this court by any of the owners or parties interested in lands taken, damaged or assessed, and the court may allow such appeal to be "taken jointly, and upon a joint bond, or severally, and upon several bonds, as may be specified in the order allowing the same." It appears from the abstract the objectors "pray an appeal jointly or any portion jointly, or any one of said objectors severally, to the Supreme Court of the State of Illinois, which appeal is allowed on condition that the objectors so appealing shall within thirty days file a proper bond according to law in the penal sum of $200 for each objector so appealing, provided that in case more than five objectors appeal the bond need not be more than $1000." In the instant case there were fifty-seven objectors, all represented by one attorney, and thirty-eight of those objectors by the same counsel have perfected this appeal. The appeal is in accordance with the order granting it and the order for the appeal was authorized by the statute. City ofMomence v. Kirby,
In support of the first contention of appellee, that the order of the county court as to the cost of the improvement is final and that no review may be had thereon, several cases are cited, among which are Village of Niles Center v. Schmitz,
It is not specifically provided for by statute as to how the board of local improvements shall make up its certificate of cost and completion. The facts necessary to be included therein are provided for, and it would seem that the filing of a certified copy of the engineer's final estimate of *37
the improvement work as a part of the board's certificate would assist in simplifying the report and hearing thereon and would be a substantial benefit to all parties concerned. The property owner has a legal right that the city shall keep an intelligible and accurate account showing the actual cost of the improvement and what moneys have been expended therefor within the power conferred upon it by law for the making of the improvement for which he has been assessed. The city is the instrumentality authorized by the law to collect and receive the money from the property owners and to disburse it for the particular purposes specified in the ordinance. It is not required that the original description of an improvement shall be so minute as to mention each and every detail. Those things which are fairly implied and necessarily included within the general terms used will be regarded as within the description. However, this applies only to work performed or materials furnished under an improvement ordinance which consist of minor details or changes found necessary in the execution of the work and which are within the general scope of the ordinance and necessary to render it effective. (People v. McWethy,
Unquestionably the power and authority given the court by section 84 of the statute are to be exercised in the furtherance of the particular improvement, and the necessary requirements pertaining thereto, as contemplated and included within the original improvement ordinance. The court has no jurisdiction to adjudicate matters of any nature which are without the purview of the ordinance as authorized by the Improvement act. The extras here involved, or at least the major portion of them, were not included within the contract or ordinance, and the court attempted to exercise its jurisdiction and also to find as a fact something which it was shown by the record, and which was undisputed, was not a fact. The extras or additional work disclosed by the record, as we understand it, amounted to $20,097.67 and are included in seventeen separate items. Three of those items in amount of $2169.55, and over which the county court assumed to exercise legal jurisdiction, were disallowed by that court. No objections are here made by appellants to four items in amount of $2672.50. The remaining ten items, in amount of $15,255.62, should not have been approved and allowed as a part of the cost of the improvement. *39
The order of the county court will be reversed and the cause remanded, with instructions to modify the order in accordance with the views expressed in this opinion.
Reversed and remanded, with directions.