History
  • No items yet
midpage
City of Beaumont v. Excavators & Constructors, Inc.
870 S.W.2d 123
Tex. App.
1994
Check Treatment

*1 123 N;” triаl “Betty court’s Wyatt Drilling v. we REVERSE ment interest. See Penrod (5th Co., Cir.1984); appellees 951, punitive damages to n. 3 of 735 F.2d 955 award Co., punitive appellees Barrios Louisiana Constr. Materials receive v. RENDER that (6th Cir.1972). Second, 1157, 465 F.2d 1168 trial court’s amend- damages; we declare ongoing calculating prejudgment interest judgment judgment and RENDER ed VOID jury. a is difficult for remainder judgment; on the first Sanford Vidrine, Boats, 958, Bros. Inc. v. 412 F.2d judgment is AFFIRMED. (5th Cir.1969); Airlines, n. Nat’l Inc. 973 13 (5th Stiles, 400, Cir.), v. F.2d cert. NYE not Former PAUL W. Chief Justice denied, 885, 157, 80 S.Ct. 4 L.Ed.2d 361 U.S. participating. (1959). However, justifications policy these inapplicable

are of a when beneficiaries bring

deceased seaman a Jones Act or DOH- wrongful claim. The

SA death Fifth Circuit prejudg

has indicated that the calculation of in wrongful

ment is easier death interest cases the loss occurs at time. because one Barrios, Stiles, 1168; at at 465 F.2d 268 F.2d CITY OF BEAUMONT Furthermore, 406 n. 6. the Fifth Circuit has Telephone Southwestern provision just held that DOHSA’s “fair and Appellants, Company, compensation pecuniary for the loss sus v. prejudgment tained” in mandates interest special the absence of circumstances. Stiles CONSTRUCTORS, EXCAVATORS & holding prejudgment at F.2d 406. INC., Appellee. interest recoverable under DOHSA percent where court awarded the district ten No. 09-92-029 CV. annum,

per per the court and where itself Texas, Appeals Court calculation, prejudgment formed interest Beaumont. the Fifth Circuit stated: We do not believe that rationale for 16, 1993. Dec. disallowing prejudgment in interest Jones Rehearing Feb. 1994. Overruled justifies brought Act at law cases disallow- ing brought that interest DOHSA cases Dissenting Opinion of wrongful at law. Most of Burgess Feb. 1994. Justice death case occur a moment. Calculation from prejudgment interest that moment relatively easy is a task.

Snyder, at 839 F.2d 1094. appellees

Accordingly, we hold recovery prejudgment

entitled in- Furthermore,

terest under DOHSA. be- wrongful action

cause this suit is death Act, personal

under and not a the Jones action,

injury distinguish this we case appellees were entitled to

Cano and hold recovery prejudgment interest under point Appellants’ Act. thirteenth Jones

of error is overruled. trial court’s REVERSE “Betty N” RENDER the F/V appellees nothing against the take F/V

126

Tyrone Cooper, City Atty., ry Asst. Bruce W. to Excavators’ contract. Bell had no con- Cobb, Beaumont, Deborah Heaton McElva- tractual relation with Excavators and the Dillard, Kovach, Houston, ney, McElvaney telephone company & was not advised that the Oleson, Beard, Cheryl Wells, Peyton, actually D. contract and exe- had been awarded Crawford, Beaumont, Greenberg, April Hunt & cuted until Bell received a notice (the appellants. preconstruction meeting precon- certain meeting). Query: struction Were the 220 Scott, Goforth, Lewis, Robert Scott & working days salutary available and Williams, Houstоn, Duesler, Thomas W. City? Query: Could not the look to the Adams, Duesler, L.L.P., Coffey & E.Wm. days scheduling City’s work? Heaner, Jr., Co., Gulf State Utilities Beau- wording think From the contract we mont, Lewis, Henry, Clint W. Lewis and *4 yes query. Nothing the answer is to each in Beaumont, appellee. for basic contract authorizes the Excavators project. the accelerate work the WALKER, C.J., Before BURGESS, BROOKSHIRE and JJ. The record reflects that Excavators com-

pleted project its contract on the within the OPINION days. allotted Excavators was assessed no penalty damages types or other for un- BROOKSHIRE, Justice. timely completion. clearly The evidence In March of Excavators & Construc- percent that a 16.7 shows Excavators made (Excavators) tors, Inc., against filed suit $168,000. project, being profit on the about City (City), of Beaumont Southwestern fin- Bell’s contentions are that Excavators (Bell), Telephone Company Gulf States Utili- contractually project ished the within the ties, (GSU), Shipman, Inc. Fittz & Inc. profit allotted time and made the that it (Fittz), Cable, (Cable), Liberty T.V. Inc. intended to make. It was demonstrated that inefficiency delay damages allegedly for opportunity perform no loss or to bid or performance suffered Excavators in the any other work on other contract existed. City. a contract it into had entered Excavators lost no other work. Excavators settled the enti- with several of prior ties to trial. Trial was had before a Excavators’ Position and Contentions

jury, jury and the found in favor of Excava- vis-a-vis Bell Judgment tors as and Bell. brought legal proceeding Excavators al- was entered in favor of Excavators and it delayed performance leging that was in the it pay ordered the Excavators’ improvement of its excavation and work indemnify partially and also ordered Bell to relocating telephone poles. delay Bell’s in its under Ordinance No. 85-50. From alleged it as a Excavators suffered appeal that this ensued. resequencing by result of the Bell. Excava- tors claimed it suffered inefficiencies due to The Basic Contract and its Provision for delays resequencing Bell’s in work. These Working Days Working and 240 caused because Excava- inefficiencies were Days Completion for Final tors contended it had to relocate and reas- City agreed to a Excavators sign equipment its own and its crews of 8, 1986, April nearly written contract on working claimed men. Excavators paid one million dollars to be and awarded equipment charges rental and labor costs. Excavators; provide Excavators was to very substantially generally costs These widening improvements to street and other after occurred within six months Avenue, Highland City. in a street preconstruction meeting. widening improvements and the were to be substantially working completed within 220 Question Enterprises The Thomason finally completed days and within work 21*0 8, 1986, ing days. costs April On Bell was not a Excavators contended-for increased signato- alleged with certain ineffi- party to the contract —it never was a were associated utilities. were case addition new When- ciencies which this well Excavators n own workmen and own working any existing presented utilities obstruc- ever (Exca- work, then contractor performing crews work Exca- tions to vators) notify engi- previously professional would vators had subcontracted out work). (Thomason necessary job. move Enterprises neer on When Thomason services, poles, guywires, pipelines or Relevant to this matter Excavators claimed obstructions, initial other Excavators forced because work, necessary arrangements necessary duty to make the its contract it was to have its operators employees perform the owners and utilities. own the Thomason work with language of the contract lay so that off We conclude Excavators would have to duty put this on notice employees thereby allegedly run a contractor changes have to employees risk that own hired that all of the involved would their would be Nevertheless, during progress contracting firm. be made work— another upon beginning the Excavators insisted affirmatively Excavators claimed that its own since Hence, immediately. perform previously crew did not work subcon- efficiently have known that there would be de- tracted work as as Thomason should lays. clearly, And the construction contract would have and that such inefficiencies dam- (City) aged alleged provides the owner will not be amount of *5 delays $102,785. damage for of to about The Thomason issue liable account due work by changes owner-operator resulted of from sole decision Excavators. made only progress of utility Not and involved which hindered did Excavators increase its cost be alleged damages, mitigate to its the work. Nor will owner liable it failed for Thus, damages. by the due to relo- costs and dam- costs incurred contractor Excavators services, aged cating poles, ap- utility Excavators. service and purtenances. coming superintendent Evidence from for Thomason showed that chose Excavators Damage Delay” “No The for Clause perform simply to the Thomason work be- high profit cause it was and work that Exca- “owner-operator” in The term or “owner” performed efficiently vators work as City, the contract means but the broad Furthermore, Thomason could have. this owner-operator language to of used as superintendent of- testified that Excavators poles evidently utility would refer to other performed profit- ten Hence, Thomason work when utility operators. certain owners and able to so. do importance paramount are in this issues of One, damage delay” appeal. for does “no City

The of Beaumont’s Point of implicated clause and viable under become Reply No. 1 Error Point Two, damage for record? does the “no of Excavators (or delay” rather preclude clause Excavators Excavators) recovery by any inef- for loss of City’s point The number one contends that ficiency delay damages? usually con- or As overruling City’s the trial court erred in strued, delay” damage for the so-called “no motion for non obstante veredicto essentially contractor the clause denies the clause, damage delay” con- as the “no for damages delays of right to for others recover tained in the basic construction contract be- performance of a construction con- in the Excavators, City precluded tween the See, Annotation, Brunner, T. tract. Maurice recovery delays inefficiency damages. for or Damage” Validity “No Construction Delay Building Respect Duty Clause Responsibility Excavators Contract, 187, A.L.R.3rd Inspect Construction the Work Site (1976). 197-200 provided itself The construction contract Texas, provisions in construction inspect In similar that the contractor would the route given by the been effect during bidding period contracts have the construction Ball City v. R.F. and a courts. See Houston and check thаt location utilities for (Tex.Civ. Co., Inc., problems as 570 S.W.2d possibility Const. conflicts App. by operators [14th Dist.] writ ref'd owners or of utilities. Excava- — Houston n.r.e.). wording of the clause makes by tors this and arguing refutes counters purpose obvious its and intent which is to damages that the for apply do not exculpate liability damages for damages allegedly by that were sustained (1) any delay due to “changes from: made Excavators in this case. owner-operator utility hin (1) argues damage that: the no (2) work”, progress der the “incurred in simply apply clause does to Excavators services, relocating utility services, poles, applies only here because this un- clause appurtenances.” (2) construction; derground work and disputed It is not the contract provides the contract for work between Excavators and contains a valid delayed or hindered if the Exca- fact, damage no In put clause. vators suffered actual and if the entirety that contract in its into evidence. contractee, is, City, responsible question The crucial is whether the clause delays. for the cost caused applies in such a manner as to defeat Exca recovery delay efficiency vators’ or loss of Bell’s Point of Error No. 1 and damages. practical pragmatic There is a Legal Duty the No Defense reason delay” for “no clauses to adamant, uncompro Bell takes the incorporated be in such construction con (Bell) mising position that it owed and owes record, tracts. this ease and under this legal duty to Excavators. Bell maintains parties actually knowledge and fore total, that it and Excavators were and are possibilities delays. language saw the legal strangers. duty Bell claims that no of the contract itself stated: “It is contem whatsoever existed that was owed Bell plated existing that the removal of utilities Excavators. record is clear that there is accomplished the construction area will be *6 any a total absence of contract between Bell during the work of this contract.” It is Hence, and Excavators. there can be no parties obvious that the to the contract and duty arising ordinary out of a contract. Bell especially actually contemplated argues duty that no common-law exists and delays under the contract sinсe the work was duty imposed upon no common-law is it. existing to be done under the ‍‌‌​​‌‌‌‌​‌​​​​‌​​​​​‌‌‌​‌‌​‌​​​‌​‌​‌​​​‌​‌‌‌​​​‌‍circumstances. Furthermore, argues question Bell that the Again, Excavators elected to start work at duty strictly question of a of law for the once, thereby breaching scope a of the work appellate trial court or the court to decide. provision. The record reflects that Excava compare County and See Fort Bend Drain plenty ample opportuni tors had of and time Sbrusch, (Tex.1991); age D. v. 818 S.W.2d 392 (at time) ty bidding go to the area on Transp. Phillips, Greater Houston Co. v. 801 Highland inspect perform Avenue to and a (Tex.1990). S.W.2d 523 proposed job full reconnoiter of the area. In fact, required the contract Excavators to in determining in Bell maintains that the le- spect the route and area of construction dur gal question duty necessary of it becomes ing bidding period the and to check the that the court and this intermediate trial utilities; possibilities any location of the of Court discern and define some definite rela- conflicts, problems, and In obstructions. tionship parties between the which is of such deed, by certain utilities had been relocated quality policy a character and that social City during previous the the work on a con justifies imposition duty. the of a The deter- job prior performed by tract and a that was policy justifies mination of a social which Excavators at a different site. duty easy creation of a is not an exercise. compare Kilgarlin and See William W. & Reply point City’s number one and the Sterba-Boatwright, Sandra The Recent Evo- point argue challenge number one and this Texas, Duty lution 241 S.Tex.L.Rev. delay.” issue of “no for (1986). City very language contends that simply the contract analysis disallows Bell insists that in an of social policy duty, or for inefficiencies caused and the related a court must i.e., interrelated, special relationships, intermin- its customers consider a number of against singular gled, interdependent public, balanced factors. These fac- involved, Accordingly, stranger. this foreseeability, tors interests of a include risk must correct the probability injury Court] or or Ninth [the the likelihood dam- court perpetrated the trial ages. egregious wrong weighed All of these are to be decisis, conduct, court, concept stare utility the social of the aсtor’s embrace Bell, as a magnitude guarding against that Southwestern of the burden of and render law, duty legal no to Exca- injury, consequences placing matter of owed theirs) vators, legal stranger, (emphasis a an burden actor-defendant. See Transp. compare Greater Houston Co. v. sum, legal argues Bell that it owed a Phillips, supra, 801 S.W.2d at 525. cus- duty solely public, and alone to the its tomers, No and to the of Beaumont. Foreseeability has been characterized as (as duty It is correct is con- other existed. the foremost and dominant consideration— Bell) privity there no tended that was Corp. principle factor. El See Chico v. direct, (Tex.1987). relationship Poole, contract or no contractual 732 S.W.2d Bell The formal between Bell and Excavators. argues persuasively it somewhat had no litigation this contract made the basis of special relationship contract and no with Ex existed between Excavators and cavators; hence, duty no to relocate party. governed no That contract other road-widening project utilities in the within a street-widening project. Bell concedes predetermined timing sequencing sched relationship have a with did ule orchestrated the convenience argues or that there were contract terms places important Excavators. Bell reli provisions obligations other duties or County Drainage ance on D. v. Fort Bend Sbrusch, whereby agreed to its facilities Bell relocate supra, wherein Bell contends that sequence the time frame and Supreme presented the Texas Court was agree. orchestrated Excavators. closely awith similar fact situation and sce black-letter, Bell axiomatic rule High refers a nario and wherein Court declined parties contract other cannot impose duty. analyzes a between the Fort Bend obligation duty on a County Drainage create an non-con- case one which the tracting party, non-contracting party district an had entered into easement con basic, stranger underlying con- tract bridge. owner of a certain *7 v. injury struction contract. See Bemarct-Johnson bridge collapsed causing later to a Constructors, S.W.2d 365 Continental party. compare third See and Southwestern n.r.e.). Texas, (Tex.App. writ refd Bell v. Carlo John 843 S.W.2d 470 —Austin (Tex.1992). argues no Bell thаt since there was duty, must and contractual courts invent Question Policy Creating of and conjure up type other of discover some Duty Imposing a on Bell legal duty that force Bell to relocate would gaunt- Southwestern Bell throws down its height its for the facilities convenience let to us in this fashion: potential despite of Excavators a profits ened If to Bell in this court affirms the trial court’s detriment or real detriment Judgment, legal telephone it will act hav- turn Bell’s Bell ar condone a to customers. wit, law, ing gues to ordain a new no basis in the to will our Court would have duty. compare artificially carve out of this factual scenario and novel See El Chico essence, Bell, any Corp., in duty, unique supra. a Bell and denies to Southwestern any foreseeability of risk of companies, other to insure such reasonable utilities agree third-party strang- harm. that Bell could not all unforeseen harm We reasonably a risk harm at the ers. other has chosen to so foreseen No court disrupt “iffy” predic or future cavalierly balancing time of the utterances delicate meeting. preconstruction at overriding factors: social and made critical tions representative, needs those whom South- We not think that Bell’s economic with do Dillard, spoke negligent a deceit- western Bell has a contractual a Scott and/or fol or misleading It, fraudulent or manner at the pipes. constructions water and sewer preconstruction meeting part, site, this issue preparation relevant includes —more below. negligently misrepre- excavation, Dillard did not clearing, grubbing, street surface removal, sent future events. boring, tunneling, dewatering, lay- ing joining pipe, bedding, back-filling, addition, argues, that it could not manholes, fittings installation of testing anticipate that rely upon Excavators would and cleaning up of the site and other work. timing sequencing utterances (but This Item 600 is not to be mistaken with made preconstruction Bell at the meeting. to) specific dealing makes reference Item 121 agree. These utterances dealt with fu- underground pipe construction which ture contingent actions which were on weath- speci- also deals with the street construction er, rain, performance and the of several third City. part fications of another parties. quite hurry inwas basic contract there is a section entitled get job out get started. The section, “General Conditions”. Under this record reflects that Excavators un- stated lands, availability Article sets out the equivocally that it could have started the physical points. conditions and reference work a prior preconstruction month Article 4 mandates that the shall furnish meeting. up argument Bell sums along its the lands work is to be these lines: that for this intermediate court performed, rights-of-way and easements for impose duty where there is no contractu- access thereto and other lands which are relationship al theory and no common-law designated contractor, being for the use of statutory and no foundation and no familial Thus, duty Excavators. there exists such relationship, duty then such would create an on Bell. undue, oppressive unreasonable and burden mandating requiring Bell to focus all of Query: damage” If “no clause did not energies road-widening on a contractor’s apply project why to this it in the basic project profit so that it could make its bid contract; why plaintiff did the introduce more, simultaneously and much depriv- while entire contract into evidence and how are the ing telephone public Bell’s customers and the underground various references to construc- legal rights. Admittedly, their argu- explained? words, tion In other if the work ments and rationales advanced Bell are strictly done nothing appealing pertaining legal duty”. to “no construction, underground why do with City makes the notable contention that the put was this clause into the basic contract delay” complete “no clause is a agreed which was Excavators and the defense to Excavators’ suit. City? important part Such an of the con- tract, is, clause, damage” the “no Applicability

The Record and the obviously contemplation within the Damage Thereunder of the “No parties logically and there were intentions on Delay” Clause *8 part parties recognize the of the to an as integral part of the basic contract. parties, Both the and Excavators cite the clause contained in Item 600.07 Important work done Excavators was the contract. This has clause been and will underground language construction. The continue to be referred to ás the “no dam spelled out in Item 600.01 defined under- age” clause. Excavators insists that this “no grоund construction. We think various damage” applies only underground clause to clauses, phrases, provisions, paragraphs underground construction and work. This ambiguous; of the contract are if not says clause it not in is involved this case. ambiguous, they are inconsistent with each disagree. proves The otherwise. record other. But the record the reflects that under heading “Governing Specifi- damage”

Under the contract the “no clause stated that Provisions”, Special cations and (City) there is an the owner will not be liable dam- for “Specifications Item 600 entitled for ages delays changes Under- on account due to ground owner-operator (City). Construction of Water and made the Sewer This construction, Pipes.” underground applies underground Item 600.01 describes clause to nec- that when fails to observe exclusively underground construc- not services, guylines, any poles, underground essary Importantly, con- to move tion. struction, record, obstructions, delays in under this caused the contrac- pipelines, other Damagewise, delays necessary these surface work. make obligated to tor was intermingled. The de- were intertwined and owner-operator of the arrangements with the lays by underground construction of the con- general conditions utilities. The delays. separable from other were not provide that the contractor specifically tract damages Certainly, expert on Excavators’ means, solely responsible for the be shall Thus, separate did them. the “no dam- not methods, proce- techniques, sequences, and applies age” in case. clause construction, including notice to of the dures problems. additional, The contractor independent utilities of

There is an clause adequate planning and providing duty in the contract this: “nor will to make basic had excavations started. [City] [sic] be liable cost before preparation OWNER relocating poles, “Sequence incurred utilities of Work” so Item 600.02 entitled service indepen- appurtenances.” This services mandates.

dent clause absolves owner of utilities liability occurring costs Schwartzkopf, Testimony of William relocating poles. utilities and service Expert, on Excavators’ Moreover, Item is and is 600.01 harmonious Damages 600.07, doubly making to be read with Item applicable damage” the “no clause. Excavators, plaintiff, offered an The He expert, Schwartzkopf. testi one William position that “no

Excavators takes the damages amounted fied that Excavators total damage” simply clause of the basic contract $230,721. This exact amount was awarded but, apply does not to it this clause does not from all jury. This total sum resulted make such limitation. Excavators further delays partici all inefficiencies all argues damage” appli- that the “no clause is job. Schwartzkopf only pants parties underground cable construction and underground freely road work not con- cross examination that admitted But, point jury struction. give that Excavators he could not a total number of if underground misses is construction days delayed. had been that Excavators inefficiencies, delays, defined causes or hin- expert also that he admitted work, ders the surface then the owner or study. He no gave opin done a causation operator simply of utilities liable delay, any, as to to what ion causation as if damages. such Excavators has failed to damage. gave opinion He caused what prove separation resulting of the confluent party caused what as what defendant damages. damage. study He conducted no as to an allocation of the between performance an contract had overall gave Bell. of the dam He no allocation $973,701.50. bond in the There amount parties. ages the numerous between record, perfor- were two bonds in the one for payment, one for both of which mance and prov plaintiff had the burden scope amounts. The identical (and ing that and hindrances clearly work includes storm sewers and wa- therewith) connected that were sued events scope improvements. ter line plaintiffs money upon actually caused the improvements. sewer work refers storm *9 damages. That burden is an essential ele extending in- improvements of These consist of and the ment of Excavators cause action building new let leads and inlets even resulting damages of must be shown. amount system. new storm sewer construction aof as of The causal nexus as well the amount underground construction. Storm sewers are by compe damages must be demonstrated improvements line of The water consisted Compugraphic six-inch, Morgan v. tent evidence. replacing a cast iron water line with 729, (Tex.1984), the Corp., larger, eight-inch, 675 S.W.2d asbestos cement water eight-inch underground. line held: line. This Court involved, upon Whether the event sued tractor that there was a caused causal any injuries plaintiff delay is another relationship mat- such and the ne- between entirely. ter The causal nexus cessity between of additional actu- reasonableness the event upon plaintiffs sued and the Company al cost. Construction J.D. Hedin injuries strictly damages is referable States, v. United 347 F.2d 171 Ct.Cl. 70 portion plaintiffs of the cause of action. (1965), held: liability Even if the defendant’s has been government It that the is is well settled established, proof this causal of nexus is faulty liability irrespective relieved necessary to ascertain the amount of dam- specifications, delays the actual where ages plaintiff to which is entitled.... by were occasioned factors outside the Proving upon that the event sued caused government’s control. plaintiffs injuries alleged part is parcel proving damages the amount of delays It is well settled where are plaintiff to which entitled. The caus- beyond occasioned factors the control of al upon nexus between the event sued government, contractor or a con- plaintiffs injuries must be shown damages tractor cannot recover from the competent evidence. government delays, nor can for Furthermore, in plaintiff alleged an government properly liquidated assess breach of a contract construction must show damages against the contractor. the nature and delays extent various holding uniquely rationale and its are damages are claimed. Plaintiff applicable appeal. to this must show and connect these Schwartzkopf We must stress the hindrances to some act omission or com fact admitted that he could an mission or breach on the individual formulated defen causation; opinion as to and he could have part. damages, any, dant’s if opinion allocating an proved. each be must See Wun formed defendant y against each individual He un- Contracting Compan derlich v. United defendant. equivocally States, stated that he had not been (1965). asked 351 F.2d 173 Ct.Cl. 180 necessary make the calculations. Excava- leniency Yet this to the actual mechan- necessary tors had not this authorized work computation ics of does not relieve the study. contractor of his burden essential of estab- lishing liability, the fundamental facts of Schwartzkopf had been contacted causation, injury, and resultant [citations year engaged about a trial to become before plaintiffs’ obligation It omitted] litigation Excavators. He stated ease prove at bar to with reasonable cer- opinion analyzing that his revolved around tainty delay the extent of unreasonable the actual performance. cost of As an ex which resulted from defendant’s actions pert, jobsite. he had visited This visit provide making and to basis a reason- was after complet the construction had been ably approximation correct of the damages completed ed. The had been construction therefrom, which arose [citations omitted] years Schwartzkopf more than three when generalities Broad and inferences to the inspection made his first visual of the site. effect that defendants must have caused opinion, In his Excavators had been faced delay some because the con- inefficiency problems delay with both days longer complete tract took problems from other factors and entities not sufficient, (em- anticipated than are attributable to the or Bell. This witness theirs) phasis analysis prepared summary an of his Id. 351 F.2d at 968. Excavators failed to opinion January prove approximations. necessary such trial, year being 1991. One the first

The burden rests the contractor elements or items of additional cost was what by competent to establish evidence the dura was described as flatwork. “Flatwork” was *10 delay, delay, tion of the fact of such the driveways the and term for the concrete and that greater pavements. originally there was no fault of the con- had been This work Thomason, you’ve up with a final num- Q. later And come was subcontracted to at by delay itself an additional in this disruption damages done ber $102,785. expert The cost to Excavators of how much? case of very that at first this like stated sounded $230,721. A. decision, to poor business but this was done keep together. Query: Was the work crew The trial was entered City against an element of the City the in the against favor of Excavators Bell? not. and We think $230,721. exact of the amount (in appellee’s position point on this inefficiency dam delay all the and amount of determining directly perform previously to by Schwartzkopf ages as testified to work) being subcontracted was that it was very cent. This was very and dollar to telephone company working told that jury’s finding. also way getting poles out of the and city pre-judg- additional Against was an clearing other the area entities $125,494.57. expert ahead of Excavators. The stated that ment interest award of prudent Excavators had made a business Additionally, concedes that expert then another decision. The described delays from experienced certain excavation being equipment item as additional cost of alleged other than those in the law causes $65,374. expert then a third included lay- missing engineering suit. It referred to item, payment an Thomason. additional to shutdowns, rain, hurricane, outs, under- perceive record that this that the reflects alia, gas ground including, utilities inter payment to Thomason was an sum additional underground con- lines and certain water money con- of over and above Thomason’s duits. price compensate attempt tract to Thoma- Query: charged son. this to be Was firmly abundantly is clear’ estab- It and Bell? The next item of addi- Schwartzkopfs estimate of dam- lished amounted tional indirect cost excess ages truly represented the total amount of all $31,800. expert’s based on the This was all actors and entities on factors testimony project that the could have been job. jury precisely answered the esti- September finished but was mate and amount testified Schwartz- Therefore, job

finished until if the had later. hence, jury kopf; answer levels completed by September been the end of Bell, ’86, had against the some which the Excavators could moved on have Cable, projects correctly to other these indirect so-called attributable to to have been charged Entex, costs could have been to the other GSU, other subcontractors However, new, projects. no other available engineers. project professional well as projects were shown Excavators.1 Hence, $230,721 figure obviously could confluent, correct; syn- it includes testimony not be expert’s The climacteric of this damages. сhronous the record is: fact, telling you’re Q. During project the course of this the record As matter 1. you those Jury had shut down on any that utilities other reflects that Excavators did not recall days? may them to work been available for I’ve never claimed utilities has us shut A. perform. Seemingly, contract for and Excava- for the excavation. down other than actually down tors concedes that it never shut go stop Q. do oth- You would excavation and alleged delays performed but rather other due items of work? er Cooper, required by the Earl work contract. correct, A. That’s ma’am. superintendent, Excavators’ testified: Q. work of work were items of Other items days you Q. When about the couldn't we talk by you pursuant required performed to be Highland Project, Beaumont; excavate out on the Avenue your contract with telling gentlemen you're not ladies correct. Yes, ma’am, Jury days you they excavate on those couldn’t were. A. sure any during didn’t do other work? them at some time You to do time, no, project? at A. I’ve never said that right. That’s ma’am. *11 Sehwartzkopf damages. testified: on the law error is Reversible of. Well, proved. Q. just finally let’s move to— delay portion. your figure And is —are Sehwartzkopf through July testified that your figures represent intended to the to- trial, charges 31st of the his total as an tal delay inefficiency damages by caused — $12,580.34. expert witness would be excavation, any delay including delays provision the absence of a contractual Cable, by Liberty GSU, Entex, TCI or or contrary, a contractor situated such as anybody else out there? may be entitled to recover dam- They’re represent A. intended to the to- ages city, from a contractee home rule for delay by tal other than normal causes. I delay, inefficiency losses hin- due to mean, basis, clearly day-to-day you on a if work; drance of the but the contractor must rainstorm, get a delay; that’s a but that’s (1) prove: delayed work or hin- was expected job delay. an and estimated in the (2) dered; damages that it suffered because delay The parties, from what I call third hindrance; delay very impor- mentioned, people you that’s the— (S) tantly, responsi- that the contractee was Q. figure’s damages Yeah. Your not for ble the act or which omission caused delays alleged charged caused delay, inefficiency, or the hindrance. particularly of Beaumont over This Excavators has failed to do. The water meters? responsible delays would not be A. To delays the extent those are normal subcontractors, parties, third or other and I—that’s correct. operators, utilities owners or or acts of na- ture, God; or acts of nor would Bell. Q. rep- This calculation is not intended to damages you resent consider attrib- Issue Causation presence utable to the of Southwestern undergird opinion To and buttress our we poles? note that the record shows from Excavators’ Well, significant part delay, A. of this expert: my reading from I didn’t do a causa- —and Q. Okay. personally give You can’t us a analysis. significant part tion But a itof days total amount that Excavators & appear does to be attributable South- delayed project? Constructors was on this poles. western Bell part A. I wasn’t that as asked to do Q. But have not done a causation so, no, my analysis; I can’t do that. study and no allocation? Q. give any A. I opin- have not done an allocation. That’s You weren’t asked to just reading jobsite diary ions on causation in this case at all? —not diary, daily They reports. appear added) (Emphasis A. No. cause, significant poles being to be a those Thus, Sehwartzkopf unequivocally stated that there. opinion damages his was not based or saying You’re that’s true of GSU origi- allocated on causation as to the various poles; isn’t that correct? certainly nal defendants not as to the say I’d have to I can’t differentiate City perceive and Bell. Excavators had ‍‌‌​​‌‌‌‌​‌​​​​‌​​​​​‌‌‌​‌‌​‌​​​‌​‌​‌​​​‌​‌‌‌​​​‌‍poles they between whose were. It was settled with several other defendants before poles generally. settling parties trial. The defendants are Thus, Sehwartzkopf delays by appeal. expert included this testified definitely overlapping GSU and caused GSU as well as there was some $230,721 Again, damage figure delay inefficiency others. claims and the claims. No encompasses study disruptions productivity all the had been done this case, “anybody expert claims and to do a attributable to nor had this been asked analysis ... out analysis. scheduling there”. This award was schedule confiseatorily adjudged against been and distributed furnished unfair; Excavators; pro- Bell. It is due Excavators failed to do emasculates cess; orchideetomy performed Importantly, expert an asked: has been so. *12 analysis delays that have I was to assume that here is asked —what delays analysis a damage the and do assumption on an that all of these were based added) utilities; accordingly. (Emphasis delays by were caused is correct? Hence, expert not the the could answers of inadvertent; they repeated been have No, entirely A. that’s not correct. It’s several times. assumption all based the job Sehwartzkopf agreed had Mr. that the by persons are caused other than years four he been finished for about before Excavators & Constructors. the had first had a chance even view Q. Okay. segregated You haven’t these Further, interpret the project as we site. delay sundry among various and claims damage record included estimates there were various out the companies the involved on by back concerning made the work taken project? Thomason, a Excavators subcontractor. from that, requested A. I have not been do by Excava- Extra labor costs were incurred added) (Emphasis I nor have done that. work, In Excava- usurping tors. Thomason’s itself; mitigate tors it failed to wounded “[D]elays by persons are caused other than damages. definitely Excavators & in- Constructors” defendants, cludes entities and other factors It must that there is evidence be noted City judgment than the Bell. But the Exca- probative evaluation that considerable provides City pay that the and Bell all dam- vators took the Thomason work because over total, concurrent, ages highly profitable intermingled, the same to Exca- would be —the vators; damages. requiring coeval error Thomason had bid the work at This is re- cheaper versal. amount. jury damage the issue at answered point testimony At another in his the damage precisely figure given total the same expert, Sehwartzkopf, unequivocally testified $280,721. Hence, expert, namely, the this figures damages represented that his judgment figure brought forward delay inefficiency damages total the total against necessarily and Bell. It is delay damages by any delay caused incorrect, requires reversal egregious, excavation, by Cable, including delays judgment. jury’s neces- answer of sarily Entex, GSU, anybody job. or out on else damages or had to include some double included, damage figures definitely His in the damages overlapping elements of amount, damages delay total wrongfully against assessed a number of entities other than proves City and The record that the Bell. City and Bell. underground with the construction interfered expert Again, the reiterated he did Hence, surface work. excavation analysis not make a causation and he damages and that were was awarded monies study as

made a to the allocation dam- disallowed the basic contract. ages. His “I answer was: done an important para- We note that an decretal just reading job- That’s allocation. from graph judgment awards Excavators diary diary, daily reports.” site the—not Beaumont, $230,721.00 against plus April that sum from interest on important testimony was reiterated 18, 1991, through October date again. again in the rec- time We find judgment, total amount of interest ord, question: “Again, you’ve study done $125,494.57. Thus, amounting inter- this Answer: “That’s causation this case?” ” important Then est award is incorrect. this correct. paragraph portion orders decretal The record reflects: against City, together judgment Well, delay I causation in- pre-judgment post-judgment don’t do a with all terest, analysis quite joint at all. shall I’m not sure what be a several mean, Thus, joint against your question I do—I also Bell. and several is but didn’t contaminated, delay. judgment against asked causation Bell is erro- I wasn’t to do a neous, addition, $173,040.75 responsible and harmful. costs for which the was ordered to be received totalling to Excavators on this third Bell, plus pre-judgment $222,337.50; certain element post-judgment interest leveled Bell. *13 (4) appellate attorneys’ fees 75% of all the harmful, er- Since we found reversible City responsible for which the becomes $230,721, joint in the ror initial amount of the appeal in the event of an to Excavators liability against and several Bell must neces- case; in this sarily be reversed. (5) costs for which 75% of all taxable court paramount para- In a later and decretal City responsible; the is graph, judgment the that the total decreed (6) post-judgment interest which accrues judgment amount of the trial in favor of all set out above. the sums $777,497.23 against City the to be City not We conclude the is indemnified plus figure taxable court costs which exclud- fees, fees, attorney’s professional Bell for ed, course, post-judgment ap- of interest and Again, necessarily, errone- exhibit costs. pellate attorneys’ figure But this of fees. ous, $230,721 is the of all the invalid basis $777,497.23 figure included the erroneous of large other awards and for that reason $230,721. paragraph contained an order judgment against Bell must be reversed. recovery theory of was based on the promissory estoppel. Excavators recovered Promissory Estoppel $537,161.67 $537,161.67 against Bell and this jointly severally record, amount was awarded determine Under this we City Bell. The erroneous promissory estoppel is not the basis for $230,721 pollutes amount of vitiates and leading an of action to a affirmative cause subsequent mathematical calculations. recovery presented under the facts this case. Restatement (Second) CONTRACTS of paragraph, Then in a later decretal (1981) generally § the doc 90 has dealt with judgment pleadings recites that based on the promissory estoppel being trine of based trial, parties, of the the evidence adduced at type promise promisor on that which the of verdict; jury’s and the the court had deter- reasonably expect to induce action or should (pursuant mined to the terms of the franchise part promisee or a forbearance on the agreement City Bell between the person such third and which does induce evidence) City into is was admitted Promissory estoppel action or forbearance. partial indemnity entitled to from Bell for a if, if, only injustice applicable becomes part judgment City to owed only by can be avoided the enforcement judgment Then recites that Excavators. promise. promise made. But a must be have and recover a made; promise we We conclude that no indemnity against paid Bell for all amounts rely conclude Excavators did not on Dillard’s pursuant judgment up to Excavators utterances; and we so hold as a matter of to: Promissory estoppel in its re law. basic (1) $226,106.58 delay 75% of the or loss (2) (1) promise, quirements demands: fore efficiency damages by Ex- suffered seeability promi- thereon reliance responsi- is cavators for which the (3) sor, prom- substantial reliance ble, $169,579.93; totalling [the 75%] Fischer, English isee to his detriment. v. $230,721 the harmful some [Note: —less 521, (Tex.1983); Traco, 660 524 Inc. S.W.2d reducing given small credits Co., Inc., 814 v. Arrow Glass S.W.2d $230,721 $226,106.58 the basis —is denied). (Te x.App.—San Antonio writ 190 erroneous calculation] has failed in each of these re (2) pre-judgment 75% of the interest quirements. $122,984.68 amounting on that sum $92,238.51; precedent establishes Decisional wrong] [This amount of interest requirement separate element or fourth and (3) estop- $296,450.00 engage promissory attorneys’ the doctrine 75% of the

fees, is a pel. separate fourth and element professional fees and trial exhibit That

137 misrepresenta- negligent so-called injustice avoided finding that can be definite tion, any, Bell. if made only by promise. See enforcement of Bank, Etc., Nat. Fretz Co. v. Southern Const. clearly shown meeting it was At this same (Tex.Civ.App. [1st S.W.2d to do good deal of work —Houston still had a that GSU 1980), rev’d and remanded on other Dist.] representative of in the future and (Tex.1982). grounds, More 626 S.W.2d attendees notified the clearly warned over, prove failed to the cor Excavators has work as to start its be able that Bell would promissory under rect measure completed project. as GSU soon estoppel. merely Furthermore, representative Bell’s four looking probably at Bell was stated that *14 manner, perceive, the guarded In a we starting date part; no Bell’s weeks on refraining Supreme Texas Court has none could Bell. At that time given for was approval overtly affirmatively condoning wait on other given Bell had to be because promissory estoppel in situations such as Elec- including and Gold Crest parties, Cable has Supreme us. The Court the one before among factors. The Company, other tric estoppel and stated that written on this issue fact, In the owner one factor. weather was operates pre in nature and to is defensive (depending on explained that of Excavators existing right. vent the loss an It does put many people Excavators decided to how liability operate to create where it does drag our job): don’t intend to “We Bank otherwise exist. Hruska v. First State in a feet that’s for sure.” Excavators (Tex.1988). Deanville, 747 S.W.2d 783 reliance Exca- big hurry. There was no phone company’s utterances. vators on the alleged promises sought to that were Bell, we deter- be made actionable Furthermore, repre- phone company’s mine, preconstruction at the meet- occurred to clearly explained that GSU had sentative ing April record reflects 1986. The had to complete its work and then Cable 17, 1986, рarties April met on that when the lines) everything (including all of its transfer already signed a contract had been between phone com- complete its work before City. Excavators and the Excavators had simply There pany could start. prior, to a solemn contract committed itself promise legal promise of a the sense days performing project working in 220 rely upon. represen- Bell’s Excavators could finalizing working days the same going there were to explained tative alleged promise or Bell’s to do with without Entex. definitely problems some with be anything. express hope to Excavators did acknowl- representative of Excavators complete project within six months. work edged it would do storm sewer construction, underground involved precon- during made Comments were delay” implicating “no clause. meeting struction to the effect that Excava- fact, preconstruction In Excavators at the on-going, binding tors had an commitment meeting was noticed warned complete project commitment to system underground phone company had an that it needed the contract. Excavators said involved, demon- that a manhole was away very day right a work order on that construction and work strating underground ready even to start a month and that was play the “no brought again into and this meeting. prior preconstruction Exca- delay” This clause cer- damage for clause. employees had as- explained that its vators owner-operator tainly applied out and it could be sembled their barricades underground phone utility as to work. working by following project area Furthermore, meeting Exca- at the same day. planning it was Excavators announced specifically warned and noticed days In of vators was five or six a week. view to work as well as statements, the effect that Bell and Cable impossible it is to conceive these prob- going to run into reasonably Ex- other utilities were foreseen how Bell could possi- of the school and lems at the location alleged reliance on utterances cavators’ and also with some promissory bly property owners the doctrine of of Bell or on Hence, knew prehistoric have relied oaks. estoppel or how Excavators could promissory estoppel is dеfen- possibilities proba- The doctrine of that there were even fact, delays. parties bilities of all the sive in nature. We conclude that the doc- concerning property were warned owners promissory estoppel not available trine of concerning prehistoric oaks. Inter- that Excavators to Excavators. We hold very particular about ested citizens were profits anticipated or cannot recover lost large, oaks. These citizens these ancient profits profits or increased under the doc- completely protect desired to these beautiful promissory estoppel trine of under the rec- adjoining nostalgic high trees school. ord before us. alleged We conclude that the so-called merely

promises were utterances or some Negligent The Doctrine of speculative ideas as to future events. No Misrepresentation negligent misrepresentation Dur- occurred. ing point April 17th discussion at a By reasoning, theory like —but response any question not as a or answer negligent misrepresentation not entitle does query posed by repre- Excavators —Bell’s damages. profits See Excavators to lost sentative, Dillard, Scott stated that Bell was § 552B ToRts, (Seoond) Restatement “looking probably at four weeks on our *15 (1977). provision that mandates part” “probably” operative is the word. — damages theory or recoverable under meeting, Cooper,

Later in the same Earl negligent misrepre cause of action known as superintendent representative of Ex- only damages sentation are those cavators, posed question a to the different compensate necessarily to would be awarded utility representatives. question gen- in pecuniary plaintiff-litigant actual for was, long eral “how would Excavators be upon losses he has and because of suffered looking everybody getting pole at off the so upon misrepresenta his actual reliance they response could be moved.” here there is no reliance —nor tions —but question there was no definite or set negligent misrepresentation. gave response time frame. Bell no and made negligent misrepre- this Under doctrine promise response query. no a as sentation, supply must known speculative the dеfendant maintains that it was as to the timing instigation completion of Bank v. of Bell’s false information. Federal Land (Tex.1991). Sloane, the relocation work. We find 825 S.W.2d 439 supply that Bell did not Moreover, false information although Bell maintains that under Dillard’s utterances were this record. making promise response after Earl no or future, happenings; guesses as to unknown Cooper’s statement that Excavators wanted did not they were not information. Dillard months, complete project about six Again, knowingly lie about the future. under drawing Bell later went back to its board and theory, that Excavators we fail to see provide completely plan redrafted its a proba- mostly demonstrated reliance evidence aerial relocation of its lines. Such provides quicker. aerial relocation would be Bell had tive value. The Restatement underground construc- originally planned for damages for this tort do not include the Bell contends it accommodated Exca- tion. plaintiffs with the contract benefit of readily reasonably as vator’s schedule as however, again, Here there was defendant. Excavators never solicited a as could be. privity or of contract between contract sequence time and commitment from Bell. Excavators and Bell. See Restatement Excavators did not contact Bell while Exca- (1977). § also (Second) 552B See of ToRts entering preparing its bid or into vators was 552, § (Seoond) Restatement of Torts City. with the the contract negli- a. this doctrine Comment Under gent misrepresentation Supreme Court Excava- hold that the burden was on Bank, at 825 S.W.2d wrote Federal Land prove it to act and tors to that was induced damages beyond 443: “We decline extend alleged promises act in reliance did provided in Restatement section Ex- those limits Excavators failed its burden. Bell. disproved reliance. 552B.” cavators’ actions

139 Contracting Company v. The utterances had to do with future Wunderlich United States, (1965); complicated problems 173 180 events. There were 351 F.2d Ct.Cl. hin- compare with the future events. There were J.D. Hedin Construction see States, inherent in the future F.2d 171 Company drances v. United (1965). dependent upon proof pro- events. Bell’s actions were No causation Ct.Cl. third, fourth, parties. Proving fifth the to- presented. actions bative value confluent, damages synchronous, tal of coeval above, From what has been discussed wholly inadequate. appears justice that the element of must be truly in order to the doc- established invoke Damages Apportionment of negligent misrepresentation negli- trine of injustice gent representation. thinkWe Furthermore, apportionment there was no in this Excavators has been shown remaining damages between the two negligent record. We find no evidence of established rules of dam defendants. Under misrepresentation. Excavators made a Texas, ages applied in when certain dam profit project. handsome ages injuries result from two or more causes and one defendant is liable Indeed, different very reading we decide a careful of the causes of the some meeting transcript preconstruction all; proper then order that there be replete warnings demonstrates it was damages, award of it becomes incumbent and admonishments Bell to Excavators of portion of the plaintiff to establish which having Bell’s uncertainties of to wait on the from the causes for which others, resulted completion of the work of of no defi- is liable. 28 TexJur. particular date, defendant beginning ending nite and no definite (1980); 3d, § Damages, see and com perceive date. We that an essential element *16 Matthews, pare, v. 119 Tucker Oil Co. S.W.2d negligent of the cause of action based on 1938, (Tex.Civ.App. Worth misrepresentation negligent is that the mis- —Fort writ); compare see also and Panhandle & representation had to contain the element of Wiggins, Ry. v. 161 S.W.2d 501 negligence S.F. Co. at the time it was uttered. There 1942, (Tex.Civ.App. writ ref'd representative is no evidence that what Bell’s — Amarillo w.o.m.). negligent uttered was done a manner. He clairvoyant; was not he was not a seer of the fact, very In reading Pleadings

future. a careful The of Excavators analysis transcrip- of the notes and verbatim against causes of action Bell Excavators’ preconstruction tion meeting would negligent misrepre- encompassed negligence, speaker rather that the show uttered state- promissory estoppel. sentation and Excava- full ments that were of caution. alleged representa- tors of certain breaches allegedly by Bell. promises tions or made Burden of Proof on Damages— pleаded Additionally, Excavators for attor- Whose Burden? City ney’s fees and interest and sued the damages The amount of needs to be expert also for its trial exhibits. its fees and proven reasonably certainty with to each 1991, April City part In the latter of filed plaintiffs defendant. This is the burden. against a cross-action Bell for indemnities The causation or causal connection between allegedly City pursuant City’s due the to the inju plaintiffs the event sued and the Receipts Gross Ordinance No. 85-50—the damages by must be ries or demonstrated particular franchise. This cross-action was of‘probative evidence value. and com See separately by the to be tried as announced Corp., pare Morgan Compugraphic v. Bench. trial (Tex.1984). dealing S.W.2d 729 When with construction, plaintiff jury responded questions contract of has the part pertinent, relevant that burden to show the nature and extent of found comply obligations its alleged delays damages and the had failed to various by delays the utilities and that Bell caused which are connected or caused to relocate delay damages. part. compare on each defendant’s See Indemnity damages of and amounts Bell’s Position on These elements alleged Under Franchise to Bell’s were restricted nonperformance City’s alleged or the failure entry Bell contended before the to relocate certain meters and water coordi- level, judgment final at trial utility nate certain other relocations. against solely to recover Bell under elected theory promissory estoppel, being only expert gave testimony that Excavator’s his recovery by affording attorney’s fees figure conclusion line ultimate and bottom plaintiff. We determine cannot delays was based on total number of fees, attorney’s fees, experts’ recover inefficiency damages that were caused Furthermore, against cost exhibit Bell. actions of numerous entities and natural complained that in to be a what it contended that, than Bell and forces other (and surprise ruling any notice or without furthermore, suffered Exca- evidence), present any opportunity to multiple included vators factors utilities a judgment trial court entered in favor of the poles. than water other meters and City against Bell the indemnificatiоn under (by Sehwartzkopf): record reflects theory. part The indemnification Q. been you In this case have not re- entitled to ruled analysis, quested to do a schedule partial for the amount it certain indemnities you? required pay to Excavators. A. That’s correct. Later, to a pursuant December of Q. And a schedule anal- haven’t done Bell, the find- request of court rendered trial ysis? dealing ings law of fact and conclusions of I have one. A. And not done City’s with the indemnification claim analysis you have here is January supplemen- Bell. certain assumption an that all of these based on findings law tal of fact conclusions of utilities; were caused However, objec- rendered. Bell's later correct? requests tions and for either additional findings amended and conclusions of No, fact entirely that’s correct. It’s judge. denied law were the trial assumption that all based *17 delays by persons other than are caused contesting the presents points Bell of error Excavators & Constructors. Bell, in favor of to the adverse Q. Okay. segregated You these haven’t based on indemnification under Ordinance among delay sundry claims the prior to the trial various 85-50. ‍‌‌​​‌‌‌‌​‌​​​​‌​​​​​‌‌‌​‌‌​‌​​​‌​‌​‌​​​‌​‌‌‌​​​‌‍Bell contends that pro- claims, companies out on various involved trial court deter- of Excavators’ ject? mined to hear the cross-ac- indemnification later, separate time. against Bell at a

tion that, do requested A. I have been only Ex- Accordingly, proceeded the trial I nor have done that. Bell, remaining cavators’ theories you it’s custom- Q. And understand Inc. Fittz & City, Shipman, and Fittz & for utili- business ary in the construction Shipman close of the was dismissed at the aboveground ties, having specifically those by the trial court. evidence pole every- until their poles, not move typical? Isn’t that pole? off of that one’s Two, Three, of Bell’s Points Error said, you nor- To restate what I think A. Challenging the and Four — pole won’t move mally owner of the Damages Awarded are off of the pole until all the wires of only clearly that the The record reflects belong to. they pole, no matter who damages thereof of and the amount measure in the indus- Q. practice that’s the And loss its so-called proffered Excavators was try? efficiency delay damages result- of industry. practice A. That’s also multiple and resulted ed from factors including multiple parties, actors and you saying delay hours? party. Are not a A. who was one subcontractor No, job. Q. layouts. other actors and entities on the Nor did Schwartzkopf reach a conclu- determine and I’m I A. not —I can’t reference that —how concerning portion alleged sion what use that term. of nature such as resulted from acts Well, Q. engineer has some relocation But, spite a hurricane. hard rains and layouts prepare. evidence offered Schwartz- Oh, you engineering A. mean the draw- $230,721 kopf the full that the amount ings? entities; damages from numerous factors and Q. Sure. nevertheless, jury question answered A. To extent those weren’t 'normal number ten in that exact amount. delays, they would he in that. I calculated City simply amount of did not cause that say analysis say have to I’ve done no damages. attributable, any, how much should be if Also, clearly jury’s award is erroneous engineer getting drawing mathematically wrong, because the changes promptly. just out I don’t know. matters of un- amount includes Q. point many is that items are derground compare construction. See and your included or can be included in calcu- Co., Hurst v. Sears Roebuck & 647 S.W.2d lations here which are attrib- (Tex.1983). presence utable to causes other than the poles presence Southwestern Bell or the Jerry Testimony Braxton’s on Proftts Utility poles? States Gulf case, Upon Jerry the trial of the Mr. causations; A. There could be other Braxton was a witness. He was the 100 that’s correct. I’ve not done nor have I percent owner of Excavators. He stated any I’ve done causation testified analysis. industry profits that the usual be and would percent

should be 15 and 20 on this between job. This record reveals that on another days theOf 89 downtime that are occasion, given testimony he had sworn original claimed in the Excavators & Con- profit might range per from 20 to 25 claim, structors’ did determine if cent —but not more. Excavators had made a days? rain However, profit percent. of 16.7 $230,721, Yes, percent award of the additional eight days sir. There were rain age profit percent. rise to would about included in the claim. profit additionally large margin defeats Q. Hurricane Bonnie included recovery promissory a basis based on es- claim? toppel because Excavators did not and can A. Yes. injustice that an not demonstrate was done *18 propеr Is it a contractor Exca- like basis, Upon to it. this additional Excavators delay vators & Constructors to claim dam- as a matter law is entitled to recover ages against utility company a or attorney’s litigation its fees and other fees anyone workday else on downtime expenses against In Bell. accordance prevents when the weather it? with the above discussion we therefore sus No, sir, proper. that’s not two, three, points tain Bell’s of error added) (emphasis four. Schwartzkopf affirmatively admitted and Five, Six, Seven, Bell’s of Error Points conceded that he had conducted no causation Eight Refuting Promissory Estoppel, — study any specificity to determine with what Fault, Attacking Allocation of And portions any alleged damages resulted Rulings Trial Court’s on Certain Mo- conduct; portion from Bell’s nor what tions alleged damages City’s resulted from the conduct; portion alleged explicitly nor what The record demonstrates that that Excavators resulted from GSU’s conduct and Bell could not have foreseen any parties rely upon the conduct of other to. the suit and would utterances made employee fact, Bell who made the utter- employee. In Excavators did not Bell’s spoke ambiguous un- interpret- ances them in an rely. utterances not be could way as to the time or times involved. certain promise upon as a which Excavators ed any The utterances did not induce action rely person should or could nor which part from of Exca- forbearance action utterance or should making the could have vators. (Seoond) any reasonably expected induce detri- would Restatement of CON- § 90 mandates that for a further part mental action or forbearance on TRACTS binding to be and to be promise actionable Excavators. (Second) Restatement of CON- promisor injustice must in- upon the an be 90(1). promisor § A Bell was —and TRACTS promise binding only and the is volved certainly a maker of an promisor not a if —and only injustice by en- if, an can be avoided under utterance cannot be held liable this injustice forcing promise. that No to Exca- promisor only A made record. can be liable its vators is shown. Excavators recovered prom- meaningful reliance his or her Thus, profit. anticipated we sustain Bell’s he or she foresee or should ise where does seven, five, six, eight. points of error reasonably foresee reliance. reverse the below. See and We negates any record is that But this one Sloane, compare Land Bank v. Federal $973,- Excavators not cancel its reliance. did at 442. S.W.2d City in it 701.50 contract with the had record, this Excavators did Under profit. never in- percent a 16.7 Excavators it in what manner that would have show contemplated actually it formed Bell that away from this lucrative contract walked binding walking away signed, from this con- contemplated walking away it even fact, City. In Excavators’ tract with Again, profitable this deal. Excavators corporate disprove any such pragmatic acts it scope of the work when violated “walking away”. simply perceive We do not duty by starting its its breached contractual any position was in to “walk that Excavators to find in when it did. fail this work away” from this lucrative contract. Excava- lengthy record that established that evidence away” it could “walked tors contends differently than Excavators would have acted contract. it did not “walk from the Since uncertain, if the conditional utter it did act proves away”, argues Excavators spoken. Certainly had not no ances been record, disagree. this reliance. We Under shown; produc nor is causal connection was impunity could not “walk cause; proximate nor cause demon ing is away.” Excavators no such intentions. had Consultants, Larson, v. Cook Inc. strated. Clearly, of a causal there was evidence (Tex.App 700 S.W.2d . —Dallas connection between Bell’s utterances n.r.e.). Again, ref'd we sustain Bell’s writ fact, precon- In at the alleged reliances. Excavators, eight. error we deter point meeting, that Ex- announced struction mine, way alleged nothing by take can already the basic con- executed cavators misrepresentation. Nor can it re negligent street-widening for this tract with try the same unless a remand ordered Query: practicality, how project. could Supreme Court. away” “walk from this lucrative record, additionally we Under entire street-widening contract? overwhelming great conclude *19 meeting preconstruction an autho- At the preponderance of the evidence is weight and representative of Excavators made contrary jury’s finding question rized on alleged order neg- such as: need a work dealing statements “We nine Bell’s number with month, ready a today.... were to start on ligence. We reach the same conclusion ago.... negli- jury’s findings and a half Our barricade Excavators’ month the as to as jury’s negligence. The an- people gence be out there tomorrow.... We and GSU’s will main dam- drainage question that end.... ten —the our swer to number can start the days evidence working age five or six issue —is incorrect because planning We are the exactness of as to greatly hours.” was literal- insufficient eight Excavators week amount. ly begin the work. chomping at the bit to Appeals delayed excavating Our Court of can unfind Gulf States or Excava- affirmatively. project? facts. We cannot find facts tors on this But, (of point negli note that on this Bell’s delayed. A. I believe was I gence) overwhelming preponderance have can’t make no—I a statement as the evidence shows Bell had hired an extra most, who did the who did the least. perform underground contractor to work and Q. Okay. immediately pro Bell’s crews returned to the my dealings A. I know in with South- ject following spite Hurricane Bonnie in Bell, up western if I called and asked them the fact that Bell had extensive hurricane something, they I do felt like repair and needed to much of its pretty responsive. phone system regular for its customers all surrounding over Beaumont and territory. meetings Did have on-the-site brought Work crews from other states were employees with Southwestern Bell about help in to emergency situation. One utility conference? witness, Fittz, Richard Faust of and also the Yes, sir, along I all believe with Richardson, Inspector Gary both testi I Liberty utilities had some with GSU always fied that Bell responsive to re Cable, and I believe we had some with quests for delay relocations and did not Ex Entex. Statten, cavators. superintendent David subcontractors, for one of Excavators’ testi testimony given by The above Richard delay fied that Bell progress did not of Faust, employee Shipman, an for Fittz & project. We find and hold that there was consulting engineers project. Faust pervasive underground work and buried professional engineer. awas

work that had to be done in connection with above, As noted Excavators breached the certain belonged utilities —some of which definitely basic contract in that it and affir- proves Bell. The record in connection with matively started its construction and its work preservation old, historic oak trees prior telephone, to the time the relocation of go that Bell underground decided to completed. electrical and water utilities was portion being designated of the work that, proffered addition to Otherwise, the center section. Bell would witness Faust. This witness vouched heavy, have received defeating flack from the owner, being fact that the of Beau- Society Historical of Beaumont and other Bell, mont —not should have furnished the powerful groups of citizens. upon lands per- work was to be Furthermore, perma- formed. easements for Bell had contracted independent with an changes existing nent structures or facili- contracting company Rody known as Con- ties paid would be obtained and underground struction to do certain con- City. provisions place in the contract struction and buried Highland work on the obligations upon these relevant duties and project. Avenue This was done Bell to Bell. But we held —not expedite matters and to accommodate Exca- duty was owed Bell to Excavators. clearly vators. record also reflects that negligence The issue of the of Bell is to be realistically anything, before Bell could do only Supreme retried if ordered GSU, Cable, complete and others had to Court. their work. The record shows Cable did preconstruction meeting. not attend the Ex- Bell’s Point of Error Number Twelve— apparently cavators never called or notified Limiting Instruction Cable; nor did Excavators first contact Ca- preconstruction ble after the close of the point Bell’s of error number twelve meeting. charges that the trial court erred in submit ting jury questions, being certain six and

Noteworthy is this evidence: seven, they in the form submitted because you any Do have requested criticism or com- failed to include Bell's limited in plaint about think argues Gulf States? Do struction. Bell that 277 Tex.R.Civ.P.

144 process agree. due was not denial of Bell’s constitutional heeded. We We conclude day merits jury questions rights having incom of in court on the six and seven were its Scott, having type proceeding plete. See Lone Star v. 759 and notice Steel Co. 1988, against conclude (Tex.App. which it must defend. We S.W.2d 144 writ — Texarkana denied); Hall, 424, given day Bell full that should have been its Rеeves v. 428 S.W.2d writ). Ques in (Tex.Civ.App. court. no — Austin proper tions six seven failed include a and to given a that Bell was not We conclude or concept rule as set out in Stowers v. to be and to opportunity reasonable heard Harper, (Tex.Civ.App. Tyler S.W.2d — in A orderly defend an manner. valuable n.r.e.). must be shown writ ref'd It right right that Bell not was the afforded representation promisor that the be present and to evidence cross-examine estopped in party caused the other to act against claims it. witnesses defense of different, way way affirmative from the that points our sustain Bell’s view of rationale we promisee action acted. This different fifteen, thirteen, fourteen, of error number promisee’s prejudice. must be to the If pro- points urge lack of and sixteen. These exist, estoppel not no these elements do then misconstruing process, cedural due error requested arises. Id. The instruction was City to the the intent of Bell and as substantially correct. We held that clause, indemnity and and the no evidence promissory estoppel applicable is not to this factually points involved. insufficient evidence case. We not retreat therefrom. This do governing, section 15 of Ordi- A relevant implicated only upon a paragraph is remand employs following part nance 85-50 in Supreme Court. wording: Company, assigns, its successors and Indemnity The Issue and harmless indemnify, shall save hold argues strongly injuries that the court any Bell and all claims for City’s cross action personal property announced that occa- damage separately against arising be considered Bell would out the construc- sioned maintenance, tion, reconstruction, attempt opera- tried. was no either to There up indemnity companies clause or to prove properly repair commu- tion or said added) against during (emphasis week trial. defend the three system.... nication this; despite the Bell maintains trial money damages de- sought prior try the indemni court’s commitment Highland Av- lays. widening project manner; never ty separate in a clause issue enue, perceive, resulted in betterments we theless, judg proceeded to render the court think there was improvements. We against half a million ment Bell for about City’s person- to the no or detriment says prior that it no notice dollars. Bell contemplated by the franchise property al pres absolutely prior opportunity to pro- completion this street ordinance. After indemnity ent evidence defense of opine that yielded results. ject beneficial claim. indemnity gravamen and thrust Bell, timely encompass fails betterments not clause City, The did contends in- Clearly, not improvements. did judgment regarding any proposed submit actions, negli- its own urging demnify against itself indemnity objected, Bell claims. indemnity The does gences, or indemnity for a later defalcations. court to leave the issue necessary reloca- purposeful envision request was Later time. Bell’s refused. placed itself pro- has entry tions. objections to certain Bell indemnity clause. con- evidence within the judgment lodged. posed final exercising privileges; it was proceeded here was not court to enter sua tends of about discharging to the tune in- its burdens untried sponte award poles $375,000. City used some of Bell amount- demnification fights control. $484,155. traffic and vehicular Bell claims ing large sum to recover City did not its entitlement day in Bell claims show it did not have its court. 85-50 10 of Ordinance apparent patent in view section such is an an act *21 lines, involving lights the use of eight-inch, traffic or other asbestos cement water these systems, being responsible any being placed underground. ample Bell not There is party originally planned whatsoever reason of construction evidence that Bell had or maintenance designed major underground of traffic and other un- wires cables and belonging City. derground along Nor has the relocation of its facilities discharged proof Highland certainly burden of under section Avenue. This was under- 3 of dealing ground Ordinance 85-50 with reimburse- work. Evidence also exists that Bell (that indemnity ments to Bell. speed up These clause is- later decided in order to facilities) given sues are evidentiary to be full place court relocations of its it would hearings if Supreme aerially. Court orders a re- some of these facilities The aerial mand. plans quickly could executed be more to ac- preconstruc- commodate Excavators. The

Underground byWork anticipated underground tion conference work such as storm sewers. The under- Cooper Earl representa- was Excavators’ ground intermingled construction so job tive on the superintеn- acted as the with the other work so as to invoke the “no job. dent for the He was Excavators’ ace delay” clause. witness. We testimony conclude that his acknowledges underground there was performed. construction scope to be Question Damages proved underground work construc- Against Awarded tion performed. be As well as under- In the expert record before us the ground work, a prepared. sub-base had to be Excavators, Schwartzkopf, failed to make Cooper Earl testified: any damages. allocation of He failed to limit Q. thing on, One I quite wasn’t clear damages to water meter and above you get when you’re down here talking ground utilities. opinion, Above we (4) steps about the you have four is figure have set out that the overall testified underground (5), excavate, work and five to, $230,721, being types delay included all (6) prepare six is sub-base and on and on. alleged inefficiency damages suffered You meaning are not you to tell us have to Excavators from all sources. These factors (4) (5) step finish four step before five included factors other than water meters and (5) you’ve got to finish five to do of six Thus, ground above utilities. Excavators’ (6), (7), (8) (9)? eight seven or nine position is unhorsed. The word- No, you to, A. ma’am. Some do have ing question nothing. ten cures The an- not all. ($230,721) grossly swer to ten excessive as Q. got You’ve paving excavate before to water ground meters and above utilities. the street? allegata probata et and the verdict are A. That’s correct. at expert war. The also testified that he Q. But, thing. That’s one could be study conducted no causation to determine doing excavation underground work portion what alleged damages driveway and some sidewalk and work at Bell. time; the same is that correct? oft-repeated damage award was Yes, A. ma’am. by overwhelming shown evidence to have fact, As a matter taking that was garnered been compilation from a of informa- place project. on this provided by tion employees certain Yes, ma’am. agents plaintiff. This information was

Considerable, important prepared compiled storm sewer im- years about two after provements accomplished were to be includ- the law suit had been initiated. The basic ing the building extension of inlet leads and compilation information used for the was not new inlets to the storm accuracy sewers. Water line verified for its or reasonable cer- improvements performed by tainty by were to be Schwartzkopf. re- The amount of six-inch, placing cast iron water lines simply awarded did not *22 lays beginning causal connection or the dam- con- correlation to at Alabama Street and learned, ages against City tinuing scholarly, set the and and Bell. forward. The Bench a conscientious trial instructed verdict Important Miscellanea respect favor of Fittz. and defer- With ruling, conclude, clearly ence this was we trial Bench determined that Ar error. In view of record relevant to .the ticle entitled “Contract Documents” Fittz, delays delays by and caused those contract, ambiguous basic was also in and against and cannot taxed costs be complete because numerous blanks Bell. had form not been filled in—nor it exclu was relevancy. in its and sive thrust The trial Query: Why pay Bell for Fittz’ should scope that Bench concluded of the work actions or inactions whether it included con- part agree. professional a proper engi- was basic contract. than We duct less The trial Bench stated neering that basic contract conduct not? In this record this or ambiguous meaning duty was that the that much to Fittz. is clear. Bell owed no going to contract was be submitted to the Bell had no contract with Fittz. Bell wasn’t However, jury fact-finding a doing any as function. as work or construction that affected analyze charge special questions, slightest degree, we even to the Fittz. There- fore, not this was done. Parol on numer evidence or inactions actions caused points freely delays ous was admitted before the simply committed Fittz could not jury. The trial Bench tended to conclude Fittz be visited Bell. Whether conduct- that said was read in harmony profession- Article 8 to be ed its in a manner to affairs reach delay” not, with the engineering “no for clause and al standards and criteria thereby applicable general, be to the overall a to as would not be defense available Fittz example, construction. Bell. As Bell should not an delays pay to caused Gold Cooper acknowledged Earl Excava- an Company Crest Electric which was ordi- tors’ work had been shut down on certain nary not electrical subcоntractor was acknowledged days because of rain. He also doing professional engineering If work. poles operated by that traffic owned or contractor, simply Fittz had been another City signals control traffic and vehicle charged to Fittz’ could not be Bell. holding up devices were the work. This was point this out at trial the test We because alleged delay City part an on the employed used to instruct a standard Cooper to made was attributable Bell. verdict in favor of Fittz was that evidence of special appeal City expedite to the to - professional engineering stan- violations delayed pro- moving of all obstacles that lacking. dards This was an irrelevant was ject. He referred water meters rights respectfully Bell. test poles owned utilities —more one. than He to Bell differ. The instructed verdict as was acknowledged underground construction error. delayed. had and work and sewer work been concerned vis-á-vis Clearly, delay” pro- the “no Fittz’ clause was delays. Cooper’s applied position engineering to these fessional conduct or standards. delayed major be- perceive was that the had matters But we that the thrust and Cooper's necessity keeping gravamen Earl testi- cause of the traffic the severe mony lights working and traffic control devices in that the was to blame for the motoring regu- delays. public had to be most number of order. accidents, protected per- lated and avoid daily reports From notations in the injuries, including death. Bell had no sonal daily Cooper, diaries of Earl it was dem- any entity duty regard to the traffic underground utilities un- onstrated that

lights. derground construction were involved. record; daily Cooper daily diary personal de- Earl testified that there were lays Shipman. reports caused Fittz & His testi- were the records of Excavators. length inter- Cooper Earl testified at some mony probative was of value issue an gas preting utilities de- the basic contract. He was not that the and electric attorney. clearly He testified the relocation of these utilities had been duty responsibility completed and had the [sic]? *23 to it that see the utilities were out of Excava- A. That’s correct. way. definitely tors’ He felt like it was definitely We determine that there had to be City’s duty obligation provide Excava- typographical question. a error in the It tors awith clear area in which to work. must have been that the relocation of these Cooper scope testified that he considered completed utilities had not been word —the important of the work to be an part of the “not” omitted. contract. He described it as a brief sum- Q. Why you go job on take the if did mary project of the entire and it contained you they completed knew hadn’t the relo- requirements project. of the they cation as indicated? scope provided of the work in rele- During preconstruction meeting vant, controlling part: they they get indicated to us that would project join recently will two con- way way out of our and be out of our for roadway improvement projects. structed the construction. Irving Extension, These are the Street paramount importance ques- Of are these widening Highland Avenue from Cooper “they tions and answers. Earl said U.S. 96 & 287 to Florida Avenue. This promises. indicated”. Indications are not street, project will consist of storm sewer certainly legal promises Indications are improvements, along water line legal reliance can be based. Earl driveways. new sidewalks and The reloca- Cooper overthrew Excavators. telephone, tion electrical and water util- part This crucial of the record makes required ities prior will be to the start of construction, glaringly Cooper, clear that Mr. Earl a stel- added) (emphasis Excavators, lar superin- witness for and the Excavators did not provision; heed this all of and, job, acknowledged tendent on the in- alleged delays resulted from Excavators deed, scope insisted that the of the work was begin immediately. insistence to its work part a of the basic contract and was consid- Cooper acknowledged scope that the of the making ered in Excavators’ bid. His testi- part work was a the contract documents. mony only can be taken to be an admission Cooper insisted that when he and Excavators scope that the un- work dictated and prepared and submitted the bid to the equivocally required telephone, that all the important that one of the documents was the electrical and water utilities had to be com- “Scope document called of Work”. Excava- pletely removed and relocated and that these scope tors ‍‌‌​​‌‌‌‌​‌​​​​‌​​​​​‌‌‌​‌‌​‌​​​‌​‌​‌​​​‌​‌‌‌​​​‌‍had violated the unques- of work completed place prior relocations had to take tionably. to the start of work Excavators. His Then, surprisingly, Cooper Mr. was asked testimony prove and this record that Excava- by his own counsel: prerequisite. tors breached this contractual Q. got questions you I’ve some about Nevertheless, Cooper knew the actual situa- page the first scope of the work jobsite tion at and made allowances provision. get if I Let’s see can to it here. therefor in the bid. paragraph, The third says, last sentence here, Necessarily, digress, we in a telephone, “The relocation of electrical and manner, important point most out we required prior water utilities will be during great stretches of this record that start construction.” Correct? apparently lengthy there were numerous A. That’s correct. concerning conferences at the bench trial inquiry Then comes another basic and evi- evidence, objections procedures including dence of a fundamental breach of the basic exhibits, objections objec- and numerous contract: tions from various counsel. For the most And, April you part, large majority on at when of these conferences preconstruction you conference knew that at the bench were not recorded. We do not only place. knew that the —that know what took the — Cooper espe-

The record that Mr. Earl We conclude that evidence-wise and reflects cially plaintiff Exca- gave days from the evidence of the deposition that lasted to ten nine judgment vators that under the he was stand as live wrongfully cast an adverse have been jury for to four witness before the three Cable, GSU, delays days. him We commend for his candor and Entex, Fittz, and other contractors and sub- patience. sanguinely his conclude that project. Highland Avenue contractors truthfully he testified to a number breach- A few were occasioned es of the basic contract were committed *24 itself. Excavators its own crew to moved by Cooper’s Excavators. We conclude that city Highland another to do work while the testimony along entirety with the the rec- of progress. this project was in We stress that ord, although separate apart and from prof- from crucial evidence comes witnesses Schwartzkopfs testimony, demon- expert very A by important fered Excavators. money jury’s against that the strates award by Sep- phase Cooper’s of is that evidence the and Bell In was erroneous. the 1, 1986, stopped tember Excavators had alternative, money we that the hold award working Highland on the west side of Avenue against great weight preponder- the was and the of and thereafter moved over to east side ance of the evidence to extent that was Highland. Cooper acknowledged after that unjust manifestly clearly wrong. and This 1st, excavating September ruling in of alternative is made the case a Highland. side of the east east On by Supreme ordered remand Court. Highland poles side of were located the of poles GSU. Bell’s were on west side. one, only perceive that there was or equivocation He testified without that there two, perhaps telephone poles standing left single pole belonged was but a to Bell 10th, certainly after October or after October very early part that was in of relocated 20th, Counting period 1986. six-month December 1986. 20th, 1986, April after 18th or had virtu- Bell ally completed poles its relocation of pecuniary Bell interest in the con- had of period anticipated end the six-month and project. certainly tract or in the Bell could completion for the of desired profit. clearly make no record estab- event, expended its work. the one or two Bell the approximate lishes that telephone poles remaining $375,000 after 10th October of its facilities and sum relocate pecuniary or 20th utilities. This lack of interest ex- October could have plodes theory negligent representation of jury in the amount awarded misrepresentation. negligent Bell neces- against Bell. It correct that Excavators sarily expend complete had to monies to necessary prior started to do some work underground of its facilities be- construction However, mid-May in 1986. the substantial location and the of cause of the densities began May efforts on or about of Excavators in area of certain business establishments 22nd, May Counting 20th or 1986. from the High South Park School because May dates, period the six-month wоuld have planted ancient These oaks. oaks been ended about 20th or Novem- on or November high in front which had at one school ber 22nd of 1986. After November date beginnings time of Uni- housed Lamar cogently eompellingly reflects record versity. If aerial had been cables lines only telephone that there was one and one used, very require lines a these would standing. entirety of pole left In view the large cutting trimming amount opinion lengthy it is admit —we —but place. to take these oaks would have justifications length in there are —and changed appearance would have their view calculations con- mathematical beauty reduced their and aesthetic value. $230,721 sequelae cerning the award and its Cooper’s Braxton, review Earl testimo- after a Mr. owner of the stock sole ny, complied Excavators, we conclude that we there under- testified that Co., being per- ground Pool v. Ford S.W.2d 629 work Motor construction and (Tex.1986) through and its formed subcontrac- dicta. agreed delay tors. Braxton that in certain instanc- We must stress that some of the go es Bell days could forward with its work some of the downtime resulted waiting complete because it was original Cable Hurricane Bonnie. This was in the its relocation work. Braxton had claim conceded of Excavators. Hurricane Bonnie was deposition major in his and had stated that storm. We find the record: margin profit project on a like this one Q. Hurricane Bonnie included run percent. would from 20 to 25 We find claim? the record: A. Yes. Q. Okay. As a matter of fact —and when proper Is it for a contractor like Exca- you percent, told us 20 to 25 you said it delay vators & to claim Constructors dam- run high everything could if worked ages against utility company So, properly. pretty that means under a anyone workday else for a on downtime perfect much set of circumstances prevents when the weather it? might anticipate making as much as 20 to No, sir, proper. that’s not percent. right? Is that *25 glaringly This record demonstrates that Yes,

A. ma’am. Excavators knew that it would encounter Q. Okay. perfect And less than circum- delays inevitable and unavoidable since Exca- stances, your which is project, normal prior vators commenced its work to the relo- percent? would be 15 to 20 cation of the utilities and the water meters Yes, A. ma’am. Excavators, and the other facilities. at their project, But on Schwartzkopf this testified to option, necessarily own chose encounter jury and the awarded which would these plan under their of work. increase the amount profit addition, to 40 prepare failed to percent. failed to distribute a schedule of work until August early late or September of 1986. expert A thusly: defendant’s testified contractually Such schedule of work was Q. Now, Okay. this, if I understand Ex- prepared by preconstruc- be the time of the cavators & Constructors’ claim is essential- meeting certainly by May tion of 1986.

ly they could money have made more agree appraisal We do not with the they than bid? testimony relating Jerry of one witness Yes, A. sir. Braxton. The record reflects: Q. they Could money made more Q. they With this schedule that had in they than bid? any mind was there on the side friction They A. money did make they more than Jery between [sic] and Richard Earl bid. they Faust toas this schedule that had Q. they they answer is could and mind? did? no, Jerry A. Ias know Braxton Not — Yes, A. sir. Cooper, and Earl no. Q. they Could have made as much more Q. quote I don’t understand [sic] what money they as want? you you explain? mean. Would they A. I don’t think could have. Braxton, Jerry heart, A. his bless would complain Q. Okay. coming up about the sun in the you What would the —have cal- morning from the east. I don’t mean to be profit culated what the would be—what the that, just Jerry smart about profit percentage but this is would for be Braxton, complain any- and he will about they paid & Constructors if were what thing. I’m they want, probably And sure he request what —the last he— —the complained about me I when wasn’t there. quantifications last —the last of their [sic] claim? certainly approached And we have not Yes, They A. making sir. would be a 46 appeal any review of the record in this percent profit job. on this such idea. of, according to concerning funding lost to the extent one

Another witness testified $17,000,000. Fortunately, report, at a over complaints of Braxton: date, recouped most much later Well, Jerry complain on the Q. when did this The statement of facts loss. Highland project what did he com- Avenue documentary vividly demonstrate evidence plain about? ground utili- relocation of the above utility complained A. He about locations. through the com- ties were to be coordinated complained He He about weather. City and of Fittz bined efforts complained a lоt of— about indemnity hearing a full reason Q. stop me I (Interrupting) Let there. question necessary made inasmuch why be want to sure that does we— additional and different onerous complain about the weather? contractor duty obligations Bell had no duties and while much, They they? don’t do like progress of obligation to coordinate the No, A. sir. engineer, professional A Richard work. talking Q. you’re Is that what about? Faust, gave evidence employed Fittz Yes, sir. Scott, Mr. counsel Ex- when solicited Q. Anything else? cavators: just during pro- the course of the A. He — going to be Gulf there weren’t So that, ject things up are that come there way going up the side States in the west know, obstacles, just, you underground least half of the street or at the first know, things. things, general project, there? *26 defense, damage delay” it the “no for Under A. true. That’s noteworthy president of Excava- that any have criticism or com- Do underground complained tors about obsta- you think plaint about Gulf States? Do question posed by A Excavators’ coun- cles. delayed excavating Gulf or Excava- States posi- Excavators took the sel revealed that project? tors on that six was a reasonable time tion months delayed. A. I I believe Excavators was complete have for Bell to its work. As we as to have no—I can’t make a statement above, virtually pointed out Bell accom- most, least. who did the who did exception very plished this with of a few Q. Okay. presence explained. poles, the of which was record, fact, place at a in the Excavators my dealings I know in with South- work; complete its desired six months to Bell, up if I and asked them western called place it another Excavators stated could at [sic], something they like to I felt do so in 11 to 12 completed its work weeks. pretty responsive. nothing in the basic contract that We see professional engineer swore that: same right complete gives the Excavators eleven, just I general as note “[b]ut under in 11 weeks. Nor does the con- excavations read, have taken that he should [Excavators] require City comply or Bell to tract any problems into in his bid that account cost weeks estimate. a result relocation of came about as however, Bell argued, The record on utilities.” demonstrates in August of have started its work should pole to last Octobеr next record, but, 1985; High- as we read the Underground pulled con- was and removed. put project been on hold land Avenue had opera- underground struction and work money by City. great because of loss tions, involved improvements, and obstacles duty obligation there We decide was integral changes being an numerous —all its nine months before the Bell to start work part These factors of the basic contract. meeting. very preconstruction first delay” implicated the “no clause. that it position the definite was shows that there Braxton took Significantly, the record it that the underground duty utili- to see to involving were obstacles implement removed delay in utilities were ties and that obstacles caused these timely properly. their relocations surface work. the excavation resulting and the damages, part testimony developed confluent of Birchfleld’s any, if we conclude that were related to the by counsel for Excavators. Cable owned no construction, were, turn, underground in so utility poles; poles it rented from GSU or closely intermingled intertwined and with the Bell. Birchfield was not invited to attend surface work that the “no damage delay” preconstruction and did not attend the meet- clause is infused into the contract and the ing; dogmatically he no notice. received He Highland project. Avenue specific As a ex- charged any that Fittz failed to do coordinat- ample clearly evidence, set forth ing relationship of the work in to the Cable underground should be noted construc- company. tion large had to be extended because of a plans Scheduling engineering plans underground sanitary pipe storm or sewer were needed. These matters needed to be made out of concrete that was encountered carefully prepared and furnished to so Cable unexpectedly by Excavators. The same had starting have a Cable could date and not been plat. shown on This obstruc- finishing plans date. These would inform tion was not discovered until it was encoun- Cable as to what and when it should order tered; but it had to be removed order to equipment in materials and order to do its do other work. part of the work. The did not furnish

Charley plans; professional Testimony engineers nor did the Adams’ plans; furnish the nor did Excavators. Ca- Mr. Adams’ sworn statements in the rec- simply proрerly perform ble could not ord are unequivocal. clear and He stated the tasks and duties without these essential ma- City crews had to work on repairs certain concerning splic- terials. Problems arose moving well as the meters and that Excava- ing reconnecting of cables and lines. tors itself had made engaged mistakes and Splicing reconnecting caused the loss of wrong procedures; hence, many signal which in turn DBS loss improperly attempting profit from its picture quality and reduced the retail negligences own wrongful and its own acts. witness, Birchfield, television viewers. This important testimony Adams’ could be dis- further testified that there was no reason *27 further, length cussed but the opinion of this why anybody from Bell should call to Cable prohibits testimony same. His was to the give update Cable an of the status or the underground effect that construction had to progress of the work. put in reasphalting be and installed before work could commence. We conclude that the Undoubtedly, Excavators wanted to make underground construction was so related to $230,000 profit job. an additional on this the other work that the concurrent expert opinion One delivered the that if Ex- resulting therefrom were in- intertwined and $300,000 cavators had bid an additional termixed, triggering the “no for de- job and still had been able to obtain the lay” clause. attempt Excavators made no to contract; then, only then and could Excava- distinguish separate or the tors have made the additional amount of damage. elements of $230,000 asking jury. it was from the expert, Roy, ques- a Mr. was asked this Michael K. Birchfíeld’s Evidence tion: superinten- Birchfield was a construction Q. say Is it a fair statement to make or to dent or foreman. He also acted'as a con- you that if don’t have a schedule that tells supervisor. employee struction He was the City City’s engineer or tells the when main thrust of of Cable. The his evidence you’re going working to be and where on a was that Fittz had never furnished him or his day given time and it be difficult at —would any company plans pro- and that these the relocation of the best to coordinate engineers coordinate fessional had failed to engineer’s utilities to conform to the ex- job. cogent testimony the work on the His pected schedule? certainly Fittz had' raised the issue that I think it could be done. A. don’t Nevertheless, delay damages. Fittz Q. you say impossible? it’s an instructed verdict. And this Would obtained A. Yes. BY MS. OLESEN: Q. City suing Southwestern Jerry

President Braxton and timely failure to Bell in this lawsuit for Absolve they, telephone poles, sir? remove their are Q. Okay. you let me ask this. I And Honor, MR. SCOTT: Your that’s y’all supposedly understand that had the question. action same There’s cross April, schedule back this bar chart. The They’ve pending. sued Southwestern you you give contract told had to Bell. Shipman and Fittz & a schedule. You not for failure OLESEN: It’s MS. precon- asked for schedule at the poles, Your timely telephone remove you meeting give struction it but didn’t Honor. anyone you you any think had didn’t indemnity, It’s for THE COURT: obligation right? to do Is that. objection. I think I’ll still sustain A. It would have been no use. that’s There is a cross action related Q. you any You didn’t think had obli- that. gation to do that? right. All MS. OLESEN: say just I A. I didn’t that. said would BY MS. OLESEN: have been no use. any Q. obligation They didn’t have [Bell] Q. obligation you think Did you, they, did sir? to coordinate relocation of utilities on this ma’am, No, they A. didn’t. [Bell] project? Q. them You didn’t have contract with job. A. That was not our [Bell]? Q. any obligation to You didn’t have do right. A. That’s that? Q. pay to remove [Bell] You didn’t them supposed A. That was to have been done poles? those prior to. No, go

Q. any obligation to A. ma’am. You didn’t have or South- out and talk to folks GSU expense? it at own They do their supposed else Bell. Someone western Yes, A. ma’am. you’re Is that what you. that for do telling us? Jerry Braxton Exonerates taken supposed to have been It was Department superinten- Water of, ma’am. care *28 complaint made dent testified you Q. yet Southwestern And think moving relationship to City against Con- obligation Excavators & to had an Braxton, in the meters. Mr. of the water go do their work and structors out record, swore: your with schedule? accordance complain you didn’t Q. he indicated And A. Not— moving meters his not to him about Q. their cost? And at moving them not enough or his crews fast ma’am, not City, obligation to A. An correct? enough. Is that fast to me. right. A. That’s suing Well, City’s Q. right. All complain? Q. You didn’t are, you? aren’t You them here. [City] didn’t department A. The water Honor, object I Your SCOTT: MR. meters they to move the know that suing is That’s not true. that. they out there. until true, absolutely not here. That’s them you not you or did Q. My point was: Did straight- to be needs I think that and him? complain to out. ened I com- him. complain to I A. did There’s a Sustained. THE COURT: somebody else. plained to action. cross Q. [City superintendent] negligent representation negligent He was there and every day. misrepresentation unless allowed the Su- course, preme Supreme if the Court. Of helped every day, A. And him we too. Court, argument, either with or without di- Q. guy complain And he was the there to the remand be fashioned in a rects meters, to relative to the he? wasn’t mode, Supreme different then the Court or- right. A. That’s course, will, prevail. ders of this interest- fact, your prior As a matter of testi- we, enticing appeal, ing challenging and mony depart- indicated water earnestness, Supreme great invite the prompt in ment was the relocation of their opinion. Court’s of our review meters; isn’t correct? retry only can breach of contract issues right. A. That’s against City provided Supreme Court Q. They they stay tried as best could orders a remand. do not. get ahead those meters out of maybe have and We could should your way? important discussed other matters and the did, They helped sure and we them. evidence of°other docu- witnesses other opinion admittedly long long. is —too evidentiary ments. We feel that these other criticizing person Before the throws the first rightness opinion matters infuse into our stone, let him or her read this record com- judgment. prised heavy of 17 volumes of statement of judgment judg- We reverse the and render facts, transcripts, five volumes and a le- nothing ment that Excavators take gion opinion justified, of exhibits. The is that Excavators take however, in order to dispositive address the from —and nothing Bell. points of error. points Some of these overlapping repeti- error were and somewhat AND RENDERED. REVERSED Also, tious. since we have set aside certain jury findings, necessary it became for us to BURGESS, J., dissents. Co., heed Pool supra. v. Ford Motor Pool BURGESS, Justice, requires detailing dissenting. the evidence.

The district court makes I respectfully dissent. The author of the finding and recites that the defendants Gulf majority opinion correctly High stated in Utilities, Inc., Cable, Liberty States T.V. Youngblood, lands Ins. Co. v. 820 S.W.2d previously Inc. had plaintiff settled with the (Tex.App. de writ —Beaumont Thus, judgment. before the date of that nied): obligated uphold “[W]e are $230,721 figure includes some double dam- jury’s if there verdict evidence of ages. same,” probative yet support value to jury. overturns the unanimous verdict of this language We realize that some of the disagree majority many I with the issues ambigu- franchise ordinance is loose and and, course, disposition. I their ultimate jury finding ous. We also find the crucial will, however, limit this dissent to the more $230,721 be, as an finding, alternative poiiits. salient great weight preponderance *29 clearly wrong evidence so as to be Day Completion The Clause manifestly unjust. 220/240 doing applied In so we accepted the appellate standards of review. day completion period The 220 substantial Supreme If the day completion period Court under their Rules or the 240 final was a merely judgment provision designed 170 and 180 reverses our protect contract the hearing argument simply without re- of Beaumont. It maximum was the court, imposi- mands the case to the district it is our time allowed Excavators the before opinion liquidated damages. majority and our that Excavators tion of Yet the proceed against only can type Bell on the issue of treats it as some of insulation from negligence being damages by delay. and none other. Excavators can- liable for Furthermore, retry promissory estoppel majority nothing not its theories of the states 154 Dil- mony representative, Bell’s to accel- from Scott

the contract authorizes Excavators lard, This is illustrative: project. erate is view- the work wrong ing perspective. the clause you representa- make some Did also nothing prevent contract to There is April meeting concerning at the 17 tions accelerating the work. The work, Excavators from how phases Southwestern’s company penalize a for effi- majority would sequenced? it advantage ciency taking of favor- and even did, yes, I believe I sir. majority The even “Ex- *30 expert amount meeting,” in Excavators’ testified preconstruction Bell at other words, jury was what reasonably damages. asked could not foresee evidence, City of amount of or risk of harm. reliance ‍‌‌​​‌‌‌‌​‌​​​​‌​​​​​‌‌‌​‌‌​‌​​​‌​‌​‌​​​‌​‌‌‌​​​‌‍an- Bell and my majori- and Southwestern judgment, support does Beaumont majority question. Yet the disre- portion testi- swered the ty’s position. following majori- gards jury’s answer because

ty apparently portion Excava- believes parties.

tors’ were caused other jury

That was for the to decide. Their deci- supported

sion is and should evidence Assuming jury’s

stand. answer is incor-

rect, insufficiency factual this is and would remand, only in

result not a rendition. repeat,

To I legal find both a basis for

recovery and sufficient evidence in the record support jury’s findings and the trial judgment.

court’s I would affirm in all re-

spects. FORD, Appellant, Randall

Warren

v. Texas, Appellee.

The STATE of

No. 04-93-00006-CR. Texas, Appeals

Court of

San Antonio. 29,

Dec. 1993.

Rehearing Denied Jan. 1994.

Discretionary Review Refused

May 1994. able weather. notes In facts are identical a case where the almost penalty no or other cavators was assessed ease, Telephone Southwestern untimely typеs damages completion.” for Co., Company v. 574 Meader Construction early “untimely completion” comple- The 839, (Tex.Civ.App. Paso 842-843 S.W.2d —El tion. 1978, n.r.e.), legal duty was writ ref'd jury all the recognized. Here the answered Damages Delay The No for Clause necessary requirements impose fact unambig clear and sup the absence some duty upon Bell. Those answers are provision contrary, uous to the a ported by contractual the evidence. is recover contractor entitled to Promissory Estoppel delay from a for due to contractee losses estoppel is Clearly promissory available if proves hindrance of work work was hindered, Engineering, See Inc. Excavators. Westech delayed damages be or it suffered Constructors, Inc., v. 835 S.W.2d delay Clearwater cause of the or hindrance and writ). 1992, 190, (Tex.App 204 no responsible for the or contractee was acts . —Austin majority acknowledges the Restate delay hin The omissions which caused the or (1981), § of CONTRACTS 90 v. R.F. (Second) drance. Houston Ball Const. ment Co., directly estoppel. Inc., 75, promissory (Tex.Civ.App.— deals with 570 S.W.2d 77 n.r.e.); 1978, of the Restatement has been This section Dist.] Houston writ ref'd [14th Inc., Shintech, Constructors, See State adopted Texas courts. First Group v. Inc. Co., 687 144, Bank in Archer v. Schwarz (Tex.App. 688 148 S.W.2d —Houston 453, 1985, writ). 1985, (Tex.App. writ majority The S.W.2d no [14th Dist.] — Dallas n.r.e.), Traco, Inc. v. Arrow Glass delay” ref'd holds “no clause Co., Inc., (Tex.App.— 814 S.W.2d applied this contract to the entire contract denied). majori San Antonio writ The just underground construction law, finds, ty no clause, as matter of there were provisions. as noted promises representations made South majority, is item 600.07 of the contract. This finding is in con western Bell. This direct begins is a of item subset findings. again, jury’s to the Once tradiction specifications underground construction. support jury’s find any delay there is evidence to did not nor dam claim ings and this court should substitute ages underground con connected jury. judgment for that of the Excavators’ claims involved struction. roadway. This excavating paving Negligent Misrepresentation inapplicable controversy. clause Obviously falls this cause of action rises or Duty Bell’s Southwestern misrepresentations by upon issue found; jury so Southwestern Bell. majority represen- holds Bell made majority disregards. tations and could not antici- to Excavators rely pate “the would Damages timing utterances made sequencing

Case Details

Case Name: City of Beaumont v. Excavators & Constructors, Inc.
Court Name: Court of Appeals of Texas
Date Published: Feb 10, 1994
Citation: 870 S.W.2d 123
Docket Number: 09-92-029 CV
Court Abbreviation: Tex. App.
AI-generated responses must be verified and are not legal advice.