Thе City of Albany filed its suit against Oxford Construction Company and others seeking to recover damages for expenses incurred by the city. The defendant, а subcontractor, in doing certain excavation work for Dougherty County severed the natural gas supply line into the City of Albany’s gas distribution system in the use of its machinery, causing a loss to the city of $16,000'. The general demurrers of the defendant, Oxford Construction Company, were overruled, and on review of its bill of exceptions, ■ the Court of Appeals reversed the order of the trial court.
Oxford Construction Co. v. City of Albany,
The sole question for decision is: did the amended petition set forth sufficient facts to withstand a general demurrer? The allegations as to the acts of Oxford which were alleged to be negligent were: “1. In failing to make inquiry of plaintiff with reference to the presence across the drainage canal right of way of the natural gas line; 2. In failing to make inquiry of the *873 superintendant of the Gas Department of plaintiff’s natural gas seсtion of its public utilities department with reference to the location of the natural gasimain; 3. In failing to go to the office of the Generаl Manager of plaintiff’s natural gas section and observe a large map on the wall of that office showing the specific locatiоn of all of plaintiff’s gas lines; and, 4. In plowing into and contacting the gas main and rupturing the same thereby cutting off plaintiff’s natural gas supply.” By amendment, plaintiff also alleged “that the plans and specifications which were prepared by the co-defendant engineers and were in aсtual use by the Oxford Construction Company, co-defendant subcontractor, had the following note prominently displayed therein: ‘Note: Existing utilities shown оn these plans are from maps and other information furnished by the City of Albany, Water, Gas and Light Department, Southern Bell Telephone and Telegraph Company, and others, these are shown for information only and are schematic. It shall be the contractor’s responsibility to determine the exact location of all utilities and to protect same — above and under ground — -during construction. To minimize delays to work and possible damage to utilities the engineers and owner will cooperate by shifting line locations with street r/w wherever feasible, provided such changеs do not materially affect the design intent of plan or cause other damage.’ Therefore, plaintiff says that Oxford Construction Company, co-defendant sub-contractor, was negligent in its failure to discover the presence of the gas pipeline and avoid severing the samе.”
The Court of Appeals held: “Where engineers supplied a contractor with plans for the excavating of a drainage canal, carrying a notation that existing utilities were shown schematically from information supplied by the City of Albany and others and that it would be the contractor’s responsibility to locate with exactness the lines and protect them, a petition by the city against the contractor alleging that it had suffered loss when a supply line from South Georgia Natural Gas Company to- its distribution system was ruptured in the excavating work, that the engineers had failed to- note or show on the plans the existence of the line and that the gas company had failed to record
*874
its right of way or lease or to erect markers showing location of the underground line, sets out no cause of action against the contractor.”
We do not agreе with the conclusion reached by the Court of Appeals. The allegations in the amended petition are sufficient to charge that the dеfendant had the responsibility to determine the exact location of all utilities above and under ground and to protect the same during construсtion and that it was negligent in failing (a) to make inquiry of the city as to the location of the gas line and (b) to go to the office of the general manager of plaintiff’s natural gas section and observe a large map on the wall of that office showing the specific location оf all of the plaintiff’s gas lines.
The fact that in the plans and specifications prepared by the engineers and used by the defendant Oxford it was stаted that “existing utilities shown on these plans are from maps furnished by the City of Albany, Water, Gas and Light Department, Southern Bell Telephone and Telegrаph Company and others, these are shown for information only and are schematic,” would not relieve the defendant from liability to one nоt a party to the construction, if it negligently caused injury to a third party. In
State Constr. Co. v.
Johnson,
The case of
Perry v. Ready Mix Concrete Constr. Co.,
The Court of Appeals erred in its ruling that the petition failed to set forth a cause of action against Oxford Construction Company.
Judgment reversed.
