102 So. 178 | Miss. | 1924
delivered the opinion of the court.
On April 11,1923, the appellant M. E. Sandifer entered into a written contract with the appellee A. R. Netter-ville for the construction of a dwelling house on a lot described in the contract. By the terms of this contract the contractor agreed to furnish all the material and labor necessary for the completion of the building at and for the sum of three thousand dollars. The contractor applied to the appellant Citizens’ Lumber Company to purchase lumber for the construction of this dwelling, and thereupon the lumber company notified the owner, Sandifer, that he would be charged with all material furnished, and that bills therefor, would be mailed to him every two weeks, and a discount of two per cent, would be given for prompt payment. The contractor employed a number of workmen, and purchased brick and material from other parties on his own credit, and proceeded with the construction of the building. On the certificate of the architect as to the amount of work done the owner
At the time these notices were given there was a balance of nine hundred and forty-one dollars and twenty-six cents due on the original contract for the building, and after receipt of the notices the owner filed a bill of interpleader in the chancery court of Pike county, paying into court the amount due under the contract, making all parties holding claims including the Citizens’ Lumber Company and one H. M. Herrington, who- had not filed written notices of their claims, parties thereto, and praying that these claimants be required to propound their claims, and that the court adjudicate all matters in relation to said contract. Thereafter all the parties propounded their claims, and the contractor filed a petition in said cause, demanding of the appellant Sandifer the additional sum of six hundred ten dollars and sixty cents for extras, which he claimed were not covered by the contract, and which he had furnished.
At the final hearing proof was taken on all the claims and issues, and the court granted a decree awarding the contractor one hundred ninety-two dollars and forty cents for extra work done and not provided for in the plans and specifications, and held that the Citizens’ Lumber Company was a common, creditor of the contractor and entitled only to a pro rata share of the amount due by the owner to the contractor, and that this sum should be prorated among all the claimants, regardless of the date on which the written notices had been given, or of whether any written notice at all had been given.
The testimony upon this point appears to be undisputed, and it establishes beyond controversy that the material furnished by this company was sold upon the credit of the owner of the building, and that he had become obligated to pay therefor long before any notice was served on the owner by the appellees. Before any of this material was furnished he was notified in writing that it would be furnished on his credit only, and, while it is true that he did not reply to this letter, yet every two weeks he received a bill for the amount so furnished, showing that this lumber was'being charged to him. He accepted these bills without protest, and paid the sum of seven hundred seventy-one dollars and thirty cents thereon, and, aside from his positive testimony that
The court was also in error in holding that all the other claimants were entitled to share pro rata in the fund paid into court. The record discloses that the statutory notices were served on the owner on July 16, 1923, by A. R. Netterville, Jr., P. A. Deere, Clem Pluff, F. P. Netterville, M. D. Wilson, R. E. Dunn, and Fred Abraham, while the notice of G-. W. Netterville was served on July 17th, and PL M. Herrington filed no notice in writing. Pn the case of Enochs Lumber & Mfg. Co. v. Garber et al., 116 Miss. 229, 76 So. 730, it was held that “in legal contemplation the rights arising to materialmen and labors for material and labor rendered to a contractor, under section 3074 of the Code (section 2434, Hemingway’s Code), had only the effect of a garnishment, and the one first serving notice had rights prior to those serving subsequent notices,and further that, “the rights of each subcontractor or. laborer or materialman furnishing a contractor, only becomes effective from the date of the notice, and that the ones that served the first notices were satisfied in full before the ones serving a subsequent
Finally, on behalf of the appellant Sandifer, it is contended that the decree of the court below is erroneous in allowing a recovery against Sandifer of the sum of one hundred ninety-seven dollars and forty cents for extra work and material furnished by the contractor.
The contract contains two provisions in reference to extra work and changes in the plans of the building; the first being as follows:
“It is also further agreed that the said party of the second part (the owner) may make all alterations by adding, omitting or deviating from the aforesaid plans, drawings and specifications, or either of them, which he may deem proper and the architect shall advise, without impairing the validity of this contract, and in all cases the said architect shall value or appraise such alteration, .and add to or deduct from the amount herein agreed to he paid to the said first party the excess or deficiency occasioned by such alteration. ’ ’
The second provision in reference to alterations or changes in the plans is as follows:
‘£ Should any extra work -or changes of the plan be required whereby the cost may be increased or diminished, all such changes must be determined and agreed upon before the change is made, and the amount, whether an increase or decrease in cost, must be indorsed upon the back of the contract.”
If it can be held, on the testimony in this record, that the additional brick work done by the contractor, and for which allowance was made, was required on account of an alteration, change, or addition to the plans and
“The terms of a plain and unambiguous contract can-, not be varied by evidence of the acts of the parties thereto indicating a construction thereof by them at variance with its terms.”
We conclude, therefore, that the court erred in allowing a recovery by the contractor against the owner of the sum of one hundred ninety-seven dollars and forty cents for extra material and labor furnished by him.
The judgment of the court below will therefore be reversed, and judgment entered here in accordance with the directions of this opinion.
Reversed, and judgment here for appellants.