CITIZENS FOR HIGGINS LAKE LEGAL LEVELS, ERIC OSTERGREN, STEVE RICKETTS, GLENN R. FAUSZ, ROBERT OBRYAN, DRU OBRYAN, and THOMAS THOMSON, CAROL THOMSON, and JANICE JAMESON, Individually and as Trustees of the JANICE JAMESON TRUST v ROSCOMMON COUNTY BOARD OF COMMISSIONERS and DEPARTMENT OF ENVIRONMENT, GREAT LAKES, & ENERGY, ANNE MEEKS, RICHARD MEEKS, DON CORRELL, VALERIE SMITH, DEAN REUSSER, PHILIP WILL, KAREN WILL, JULIE SMITH, GARY SMITH, STAN GALEHOUSE, BARBARA GALEHOUSE, STEVE BURNS, and DIANE BURNS
No. 353969
STATE OF MICHIGAN COURT OF APPEALS
March 17, 2022
FOR PUBLICATION 9:05 a.m. Roscommon Circuit Court LC No. 19-724711-AW
If this opinion indicates that it is “FOR PUBLICATION,” it is subject to revision until final publication in the Michigan Appeals Reports.
Plaintiffs/Petitioners-Appellants,
v
Defendant/Respondent-Appellee,
and
Intervening Defendants-Appellees.
Before: CAVANAGH, P.J., and MARKEY and SERVITTO, JJ.
In this dispute involving the water levels of Higgins Lake, plaintiffs appeal by right an order granting summary disposition in favor of defendant Roscommon County Board of Commissioners (defendant), and denying plaintiffs’ motion to dismiss intervening defendant Department
I. FACTUAL BACKGROUND
Plaintiff Citizens for Higgins Lake Legal Levels “is a domestic nonprofit corporation whose purpose and existence are to promote and defend the legal lake levels on Higgins Lake.” The remaining plaintiffs are those who own, inhabit, use, or have access to land that abuts Higgins Lake. For ease of reference, we will refer to the entity and various individual plaintiffs collectively as “plaintiffs.” In 1982, the Roscommon Circuit Court established the legal lake levels for Higgins Lake to be 1,154.11 feet in the summer months and to be 1,153.61 feet during the winter months. The parties do not dispute this. The 1982 order also provided:
[I]n adjusting the lake levels as herein provided, the person or persons responsible for such operations shall make every reasonable effort to take into consideration stream flows into the lake and projected snow melt runoff within the water shed, as well as providing a minimum release during refill operations.
Plaintiffs alleged that, for several years, defendant failed to “employ known best practices and available technology” to maintain Higgins Lake at its court-mandated levels for “each and every day of the summer time period.” Plaintiffs pointed to data from the “United States Geological Survey” of Higgins Lake for support, which showed that lake levels in the summer months were below the court-ordered levels “two-thirds (2/3) of the time in 2016, over one quarter (1/4) of the time in 2017, and nearly ninety percent (90%) of the time in 2018.” Plaintiffs claimed that defendant was intentionally causing the reduced lake levels by not “utilizing all known reasonable practices and available technology.” Plaintiffs alleged that each of them had “suffered adverse, negative, and loss-causing effects,” which plaintiffs described as the inability “to enjoy the full extent of recreational and water-based activities” because of defendant‘s failure to maintain the proper lake levels.
Plaintiffs sought a writ of mandamus based on the claim that defendant “has the clear legal duty . . . to maintain or have its delegated authority maintain the lake level of Higgins Lake during the summer months at 1154.11 feet above mean sea level” and that defendant had breached this duty. As the basis for defendant‘s clear legal duty and violation of that duty, plaintiffs pointed to two statutory sections under the Natural Resources and Environmental Protection Act (NREPA),
Attached to plaintiffs’ complaint and petition was a “Higgins Lake Level Control Structure 2010 Engineering Report” from
A permit from the then-Department of Environmental Quality, now EGLE, was issued in 2007 for the LCS. The permit provided that it did “not eliminate managing Higgins Lake and the Cut River in accordance with the Court Ordered Lake Level. Minimum and maximum flows must be maintained in the Cut River as necessary to prevent harm to the aquatic ecosystem.”
The Spicer Group‘s overall conclusion was
that the Higgins Lake LCS has adequate hydraulic capacity during large runoff events. However, discharge from the lake is limited by the capacity of the Cut River. Additionally, this study has found that the level of Higgins Lake has averaged below the court established legal lake level during the summer months in typical years. Factors such as water loss due to evaporation, wave action and flow through an unregulated low flow channel contribute to the low summer levels. Losses due to evaporation have been calculated to be the most substantial factor followed by flow through the unregulated span and then by losses due to wave action.
The Spicer Group examined data on lake levels and found that, between “1986 to 2009, the lake level has averaged 0.1 feet above the legal level to 0.3 feet below the legal level during summer months.” The Spicer Group found that, in 2007, the LCS
was altered to include two additional tilting weir gates (also referred to as “flop gates“) totaling 33 feet in length and an unregulated low-flow channel measuring roughly 4.75 feet in width. Through comparison of historical data, the average lake level was found to have been lower in the period following these alterations than the period prior. This does not appear to be attributable to a drought as precipitation in the years immediately following the structure‘s alteration has been well above average. Therefore, if legal levels are to be maintained annually, water levels must exceed the legal level in the early summer months to conserve an adequate volume to maintain the legal level through the later summer months.
This process of raising water levels in the early summer months is apparently referred to as water banking. The Spicer Group examined data on lake levels and found that, after the 2007 modification of the LCS, “the average lake level has decreased by 0.1 to 0.4 feet relative with the periods prior to the modification.” The Spicer Group recommended that
[a]lterations are needed to improve LCS operation to enable lake levels to be maintained closer to the legal level. Specifically, a restrictor should be placed in the low flow channel to reduce the amount of flow to the Cut River in late summer. Also, scour protection should be added to the low flow channel, improvements should be made to the sheet piling portions and improvements should be made to the stop logs. Also, the staff gage should be replaced.
According to the Spicer Group, the LCS modification in 2007 caused “the amount of water leaving the LCS during summer months . . . to increase by roughly 30 percent over the losses due to evaporation and wave action alone.” Moreover, in the prior
Relevant to this appeal, plaintiffs requested that the trial court issue a writ of mandamus directing defendant “to meet its legal obligation to keep and maintain” Higgins Lake water levels in accordance with the 1982 order, and ordering defendant “to implement the Spicer Group‘s recommendations and/or establish guidance and operational practices for the devices used to control the lake level of Higgins Lake.”
A joint ecohydrological evaluation of Higgins Lake in the mid-2010s evaluated the effect that removing the LCS would have on the ecosystems of Higgins Lake and the Cut River. The evaluation concluded “that lake level management does not have significant effects on fishery habitat in Higgins Lake but does have significant effects on shoreline erosion. Lake-level manipulations have significant effects on fisheries habitat in the Cut River.” The evaluation provided that
[t]he probability of achieving the established summer lake level (1154.11 feet) is 15% under current operation and 0% for the unmanaged dam scenarios (Table 2). The probability of achieving an established summer lake level 100% of the time under current operation would occur at 1153.28 feet (SLL-10), and at lower levels (1152.92, SLL-14.3) for the unmanaged dam scenarios.
Additionally, the evaluation provided
that flows of 100-150 cfs are necessary to provide optimal habitat for fish in the Cut River (Figure 5). Flows of 50 cfs are a target flow rate to protect Cut River fisheries and cannot be achieved when all dam gates are closed (Figure 6). Flows of 50 cfs during summer have a much greater likelihood of occurring in the unmanaged dam scenarios (No dam and Gates 4-6 open, Table 2). A summer flow of 33 cfs is likely to be exceeded 95% of the time under natural conditions, 90% of the time with Gates 4-6 open, and 63% of the time under current operation. Note that with the 4.75 ft low flow opening in the dam, Cut River flows are lower than recommended under current operation. Presently, the low flow opening is not large enough to consistently provide even 33 cfs (the 95% natural flow).
Alisha Pastell had served as “Board Secretary for the Roscommon County Board of Commissioners and as the Accounts Payable Clerk for Roscommon County.” Part of her duties was to “compile and keep the records of a daily log of the Higgins Lake Level Control Structure.” These logs were attached to her affidavit, and their dates were from April to November in the years of 2016, 2017, 2018, and 2019. The logs showed either a “C” or “O” to represent that a gate was either “closed” or “opened,” respectively. These logs demonstrate that, for the vast majority of the time between April and November, the gates were closed.
A. EGLE‘S MOTION TO INTERVENE
EGLE moved to intervene, arguing that it had “a right to intervene ... because it is designated by statute as an interested party who must be given notice and an opportunity to intervene in any inland lake level proceedings under” the NREPA. Although EGLE conceded that plaintiffs’ action was not “a proceeding to establish a normal lake level,” it contended that its “statutory right to participate should apply” because plaintiffs’ action “is an action brought to enforce the order resulting from” a proceeding to establish a lake level. Alternatively, EGLE argued that “permissive intervention” was appropriate because it was the state agency “charged
At the motion hearing, plaintiffs argued against EGLE‘s intervention, reasoning that plaintiffs had no claim against EGLE; instead, plaintiffs’ claim was against defendant. The trial court granted EGLE‘s motion to intervene. The trial court reasoned that intervention was proper because EGLE had an interest in any lake level, and prior court orders establishing lake levels, that was not adequately represented by defendant. Although similar, the trial court stated that EGLE‘s interest was “a little bit different than Roscommon County‘s position,” especially “as it impacts on the Cut River Dam and the channel and banking of water.”
B. PLAINTIFFS’ MOTION TO DISMISS EGLE
Subsequently, plaintiffs filed a motion to dismiss EGLE for lack of subject-matter jurisdiction. Plaintiffs argued that EGLE was “mis-joined” and must be dismissed because plaintiffs’ claims were against defendant and not EGLE. Additionally, plaintiffs contended that the trial court lacked subject-matter jurisdiction with respect to EGLE because only the Court of Claims could exercise jurisdiction over a claim involving EGLE. The trial court denied the motion, holding that EGLE had an interest in this case and the Court of Claims Act was not applicable under the facts of this case.
C. DEFENDANT‘S MOTION FOR SUMMARY DISPOSITION
Relevant to this appeal, defendant filed a motion for summary disposition under
Defendant also argued that the Spicer Group‘s recommendations addressed discretionary maintenance practices and were not ministerial; therefore, the writ of mandamus was precluded. Further, defendant contended that it did not have to comply with a lake level order if that meant noncompliance with state permit requirements. Defendant believed that, if it “has any duty regarding the [LCS], it is to leave the low-flow channel undisturbed.” And, defendant argued, plaintiffs had alternative remedies available which further precluded the writ of mandamus. Moreover, plaintiffs’ request for water banking “effectively seeks a determination of a new higher seasonal level,” and the proper course of action for plaintiffs was to petition defendant for this new level. Finally, defendant contended that the logs showed that it had complied with the 1982 order and relevant Michigan law.
The trial court granted defendant‘s motion under both
The trial court stated that it needed to determine the scope of defendant‘s legal duty and whether plaintiffs had a clear legal right to performance of such duty. To this end, the trial court stated that it needed to examine defendant‘s actions regarding the “gate of the dam” and whether it was closed or opened; this could be examined via the logs. The trial court stated that these logs showed, “as an example, that all gates and boards at the dam had been closed as of June 4, 2018 and remained closed through October 31, 2018.” The trial court stated that, despite doing this, the lake levels during this period were below the legal limit. According to the trial court, plaintiffs had failed both in their complaint “or any of the other information the Court read in the documents to suggest [defendant] did anything to cause that as an intentional act.”
The trial court discussed the legal principles and stated:
The Act says that . . . they shall provide for and maintain that normal level, that they need to inspect the dam and make repairs as necessary. The Inland Lake Act does not define normal lake level to include a minimum or a maximum. Also, there is no legal authority to support the notion that any deviation from a normal lake level is illegal and a breach of duty per se. If that . . . is spelled out in the statute, I couldn‘t find it.
The trial court referenced caselaw in which this Court held that a “lake level order establishes a normal level subject to seasonal variation and precipitation” and that fluctuations were not a breach. The trial court rejected plaintiffs’ argument that defendant breached its clear legal duty whenever the lake‘s levels went below the legal level:
[A]s the reports the Court has studied as part of this action and as the studies themselves suggest, that is all but impossible task [sic] given the current . . . state of the dam and accounting for evaporation, precipitation, wave action . . . and water action on the shoreline. The 1982 lake level order does not require this heightened duty for daily compliance with that level. If it does, I . . .
didn‘t find it in the order and I don‘t find it in the Inland Lakes Act either.
The trial court summarized defendant‘s duty as maintaining the legal level “subject to the laws of nature and the limitations of the dam.” The legal level was “not a minimum or a maximum level nor is it a level that can be expected to be hit on exactly on a daily basis due to the laws of nature and the limitations and functioning of the current dam structure.” Moreover, the trial court stated that defendant had “a duty to maintain the dam and comply with the state permitting requirements.”
The trial court stated that neither the 1982 order nor applicable law required defendant to adopt “suggestions as to managerial approaches” or else be in breach of its duty. With no contrary authority presented, the trial court held that defendant had “no legal obligation to adopt the findings of the Spicer Report while ignoring the findings of the ... ecohydrological evaluation ....” Instead, the trial court concluded that both studies addressed “discretionary practices and not ministerial as mandamus actions require.” The trial court pointed to the 1982 order, which included no language requiring defendant to bank water or do anything else recommended by the Spicer Group. Given that these were discretionary actions, plaintiffs could not compel defendant with a writ of mandamus. Moreover, the trial court summarily mentioned that to force defendant to adopt the Spicer Group‘s recommendations would be “a clear violation of the separation of powers clause.”
Additionally, the trial court noted that banking water would raise lake levels above the legal level; accordingly, the trial court was concerned with “why is it the case that if the level of the lake is below the legal level, a breach automatically occurs” but, if banking water was above the legal level, no breach would occur. Moreover, restricting the LCS would lead “to a possible misdemeanor and fine.” The trial court noted that the 1982 order required defendant to maintain the water levels both above and below the legal level. The trial court further stated that plaintiffs’ alleged harm, if taken as true, was not “contemplated by the Inland Lake Act or the 1982 order” because it was merely recreational harm. The trial court stated that plaintiffs had other remedies available, such as petitioning for a change in the lake level. Therefore, the trial court ruled that plaintiffs had failed to state a claim under
Plaintiffs’ attorney asked for clarification because “you also utilized records that would be outside the pleadings as part of your fact recitation.” Plaintiffs’ attorney stated that, if the trial court “has a rationale under (C)(10) as well it sounds like it would be helpful.” The trial court agreed and stated, similar to its ruling under
II. ANALYSIS
A. DISMISSAL OF DEFENDANT
Plaintiffs argue that the trial court erred in granting defendant‘s motion for summary disposition under
A motion is properly granted under
Questions of law are reviewed de novo. Christenson v Secretary of State, ___ Mich App ___, ___; ___ NW2d ___ (2021) (Docket No. 354037); slip op at 3. Similarly, a decision “whether defendants have a clear legal duty to perform and whether plaintiff has a clear legal right to performance of any such duty” is reviewed de novo. Id. at ___; slip op at 3. In contrast, the trial court‘s decision whether to issue a writ of mandamus is reviewed for an abuse of discretion. Younkin v Zimmer, 497 Mich 7, 9; 857 NW2d 244 (2014); Berry v Garrett, 316 Mich App 37, 41; 890 NW2d 882 (2016). A court abuses its discretion when its decision “is outside the range of reasonable and principled outcomes.” Saffian v Simmons, 477 Mich 8, 12; 727 NW2d 132 (2007).
The arguments on appeal are relatively straightforward. Plaintiffs contend that defendant has a clear legal duty to maintain the lake levels during the summer months at the legally set level of 1,154.11 feet. According to plaintiffs, defendant cannot deviate from this level and must work to maintain it at that specific level. Given that defendant failed to do so for a number of years, it was in violation of its clear legal duty, which warranted the writ of mandamus. Summary disposition was, therefore, improper. On the other hand, defendant argues that it does not have a clear legal duty to strictly maintain the 1,154.11-foot level and that deviations are permissible. Accordingly, there was no clear legal duty or breach of that duty. Additionally, defendant argues that plaintiffs failed to show a ministerial duty because the method of maintaining the lake level is left to defendant‘s discretion. Therefore, the writ of mandamus failed, and summary disposition was proper. We agree with plaintiffs.
To obtain the extraordinary remedy of a writ of mandamus, the plaintiff must show that (1) the plaintiff has a clear, legal right to performance of the specific duty sought, (2) the defendant has a clear legal duty to perform, (3) the act is ministerial, and (4) no other adequate legal or equitable remedy exists that might achieve the same result. In relation to a request for mandamus, a clear, legal right is one clearly founded in, or granted by, law; a right which is inferable as a matter of law from uncontroverted facts regardless of the difficulty of the legal question to be decided. [Christenson, ___ Mich App at ___; slip op at 4, quoting Rental Props Owners Ass‘n of Kent Co v Kent Co Treasurer, 308 Mich App 498, 518; 866 NW2d 817 (2014).]
“A ministerial act is one in which the law prescribes and defines the duty to be performed with such precision and certainty as to leave nothing to the exercise of discretion or judgment.” Berry, 316 Mich App at 41 (quotation marks and citation omitted).
“Normal level” means the level or levels of the water of an inland lake that provide the most benefit to the public; that best protect the public health, safety, and welfare; that best preserve the natural resources of the state; and that best preserve and protect the value of property around the lake. A normal level shall be measured and described as an elevation based on national geodetic vertical datum.
Here, in 1982 the circuit court entered an order establishing the normal lake levels for Higgins Lake to be 1,154.11 feet in the summer months and to be 1,153.61 feet during the winter months. The parties do not dispute this. Specifically, the 1982 order stated, in relevant part:
This cause having come on to be heard on the Petition to Establish Water Level of Houghton Lake, Higgins Lake and Lake St. Helen, heretofore filed in this cause on behalf of the Roscommon County Board of Commissioners; it appearing that proper notice was given to interested parties; this having heard testimony of [sic] behalf of the Michigan Department of Natural Resources and interested persons appearing at the public hearing on said petition; it appearing that the following order will provide the most benefit to the public and best protect the natural resources of the state, and preserve and protect the values of property developed around said lakes; and the Court being fully advised in the premises:
IT IS HEREBY ORDERED AND ADJUDGED that the legal level of Higgins Lake, Roscommon County, Michigan, heretofore established at 1154.11 feet above mean sea level, be continued;
provided, however, that said level be lowered to a level not less than 1153.61 feet, commencing on or about November 1 of each year, and restored to its legal level, commencing on or about April 15, or ice-out, which ever shall first occur, in each year. *
*
*
IT IS FURTHER ORDERED AND ADJUDGED that, in adjusting the lake levels as herein provided, the person or persons responsible for such operations shall make every reasonable effort to take into consideration stream flows into the lake and projected snow melt runoff within the water shed, as well as providing a minimum release during refill operations.
Plaintiffs filed this case seeking enforcement of the normal lake levels already established by the circuit court and memorialized in a court order, and so, invoked the circuit court‘s continuing jurisdiction over the matter. See
The rules of statutory construction are well established. “When interpreting a statute, [this Court] must ascertain the Legislature‘s intent,” which is accomplished “by giving the words selected by the Legislature their plain and ordinary meanings, and by enforcing the statute as written.” Griffin v Griffin, 323 Mich App 110, 120; 916 NW2d 292 (2018) (quotation marks and citation omitted). If a statute is unambiguous, it must be applied as plainly written. McQueer v Perfect Fence Co, 502 Mich 276, 286; 917 NW2d 584 (2018). This Court may not read something into the statute “that is not within the manifest intent of the Legislature as derived from the words of the statute itself.” Id. (quotation marks and citation omitted). And it has long been understood that the use of the word “shall” means mandatory. Browder v Int‘l Fidelity Ins Co, 413 Mich 603, 612; 321 NW2d 668 (1982); State Hwy Comm v Vanderkloot, 392 Mich 159, 180; 220 NW2d 416 (1974).
We conclude, then, that the 1,154.11-foot level established in the 1982 court order was the lake level that defendant was required to maintain in the summer months. This, by extension, supports plaintiffs’ position that defendant has a clear legal duty to maintain the 1,154.11-foot level and that, by failing to do so for several years, it has violated that duty. If this level is impossible or no longer beneficial to the public, the proper course of action was for defendant to petition the circuit court for a departure from the 1,154.11-foot level. See Glen Lake-Crystal River Watershed Riparians, 264 Mich App at 537; Anson, 210 Mich App at 325-327. But deviations from the court-established level must be explicitly permitted by the court after proper proceedings.
We disagree with the trial court that the 1982 court order had “a discretionary component built . . . into” it. The order language that the trial court referenced was:
[I]n adjusting the lake levels as herein provided, the person or persons responsible for such operations shall make every reasonable effort to take into consideration stream flows into the lake and projected snow melt runoff within the water shed, as well as providing a minimum release during refill operations.
This language does not explicitly allow for deviations. The 1982 court order merely references stream flows and snow melt runoff and mandates that defendant take these into consideration. The 1982 court order sets the legal levels and no explicit deviation or fluctuation was permitted. The trial court summarized defendant‘s duty as maintaining the legal level “subject to the laws of nature and the limitations of the dam.” But this holding—and defendant‘s claim that it is not required to maintain the level at 1,154.11 feet in the summer—renders the 1982 court order meaningless and reads in language that is not present in that order. Caselaw, as well as the mandatory statutory language, does not support reading in these limitations. And plaintiffs did not claim that a single deviation occurred; rather, plaintiffs alleged, and the Spicer Group‘s report demonstrates, that the deviation has been perpetual and consistent across many years. The first two elements for a writ of mandamus are, therefore, met. See Christenson, ___ Mich App at ___; slip op at 4.
Defendant also contends that plaintiffs have failed to satisfy the third requirement for a writ of mandamus because there is no ministerial duty. Although
However, this does not, as defendant argues, defeat the writ of mandamus. Defendant and the trial court mistakenly confused what duty to examine. Plaintiffs asked the trial court to compel defendant to comply with its legal duty of maintaining the legal lake level at 1,154.11 feet. Accordingly, the applicable duty was not how defendant had chosen to maintain this level; rather, the applicable duty was the duty to maintain the lake at this level. The method of maintaining the lake level is discretionary, but defendant has a ministerial duty to maintain the lake level. To accept the position of defendant and the trial court would leave plaintiffs, and other similarly situated parties, without any way to obtain a writ of mandamus. A defendant could essentially always defeat petitions for such writs on the basis that the method is discretionary and not ministerial. This would have the effect of rendering
Finally, plaintiffs met the fourth element for a writ of mandamus: no other adequate legal remedy exists to achieve the same result. See Christenson, ___ Mich App at ___; slip op at 4. Defendant argues, and the trial court agreed, that the proper remedy and course of action was for plaintiffs to petition the trial court to change the lake level. We do not agree. A writ of mandamus to compel compliance with a previously established lake level is the proper course of action. Most importantly, plaintiffs are clearly not attempting to change the level; rather, they are attempting to compel defendant to maintain the level at 1,154.11 feet, which has been the court-ordered legal level since 1982.
Therefore, summary disposition under
For the same reasons, summary disposition was improper under
Accordingly, the trial court erred by granting summary disposition in favor of defendant under
B. DISMISSAL OF EGLE
Plaintiffs also argue that the trial court erred by refusing to dismiss EGLE for lack of subject-matter jurisdiction. We disagree.
“Whether a court has subject-matter jurisdiction presents a question of law that this Court reviews de novo.” Reynolds v Robert Hasbany MD PLLC, 323 Mich App 426, 431; 917 NW2d 715 (2018). Questions of statutory interpretation are reviewed de novo. Dextrom, 287 Mich App at 416.
“[T]he circuit court is presumed to have subject-matter jurisdiction over a civil action unless Michigan‘s Constitution or a statute expressly prohibits it from exercising jurisdiction or gives to another court exclusive jurisdiction over the subject matter of the suit.” O‘Connell v Dir of Elections, 316 Mich App 91, 101; 891 NW2d 240 (2016) (quotation marks and citation omitted). Relevant to this appeal, the Court of Claims has authority
[t]o hear and determine any claim or demand, statutory or constitutional, liquidated or unliquidated, ex contractu or ex delicto, or any demand for monetary, equitable, or declaratory relief or any demand for an extraordinary writ against the state or any of its departments or officers notwithstanding another law that confers jurisdiction of the case in the circuit court. [
MCL 600.6419(1)(a) .]
This authority includes writs of mandamus against the state and its departments or officers. O‘Connell, 316 Mich App at 103-104. The Court of Claims’ jurisdiction, given by statute, “is exclusive.”
Plaintiffs’ sole argument is based on
Regardless,
Affirmed in part, reversed in part, and remanded for further proceedings consistent with this opinion. We do not retain jurisdiction.
/s/ Mark J. Cavanagh
/s/ Jane E. Markey
/s/ Deborah A. Servitto