Opinion
Defendant and respondent State Lands Commission (Lands Commission) approved a 30-year lease allowing real party in interest and respondent Chevron U.S.A. Inc. (Chevron) to continue operating a marine
I. Background
The Long Wharf marine terminal and nearby Richmond refinery have been in existence since 1902. Standard Oil, Chevron’s predecessor, bought the refinery and began operating it and the terminal in 1905.
The marine terminal is a T-shaped, concrete docking structure approximately 3,440 feet long. Ships can dock at four deep-water outer berths and several inner berths. Ships off-load crude oil at the terminal for processing at the refinery and take on refined products which they transport to national and international markets. The marine terminal has been modified over the years. In 1946, the original wooden structure gave way to the present concrete one. Alterations in 1974 allowed for larger vessels. Since then, Chevron has added new platforms, breasting dolphins, and a vapor control system. In 2000 and 2004, the company completed a major seismic upgrade and electrical system revamp.
While Chevron’s refinery sits on private land beyond tidal reach, the marine terminal sits in the San Francisco Bay on submerged land owned by the state and subject to a public trust servitude and the control of the Lands Commission. The refinery and terminal are linked by a pipeline system that transfers oil and petroleum products between the two facilities. Leaving the terminal, the pipelines first cross a 4,200-foot causeway that largely stands atop submerged state land. The final 750 feet of the causeway, however, cross private land, which is submerged or partially submerged and therefore is also subject to a public trust servitude.
In August 1947, the Lands Commission granted Standard Oil a 50-year lease for the marine terminal. Chevron assumed the lease in 1976, and the
Before the Lands Commission approved the lease renewal, it considered what actions it needed to take to comply with CEQA. The 1902 terminal predates CEQA by nearly 70 years. Thus, no CEQA study examined its construction or ensuing operation. The Lands Commission concluded future oil spills constituted a potentially significant environmental impact, requiring analysis in an environmental impact report (EIR).
In 1999, at the beginning of the review process, the Lands Commission determined the EIR should assess environmental impacts of the lease renewal against a baseline that assumed no terminal operations but the terminal structure remaining physically intact. Over the years, the Lands Commission changed its view as to the appropriate baseline. Accordingly, the draft and final EIR’s defined the lease renewal project as allowing Chevron to “continue its existing Long Wharf operations” and used the existing, actual condition of the marine terminal, which included off-loading and on-loading operations, as the baseline by which to assess potential environmental impacts. Using this baseline, the EIR’s concluded the lease renewal could result in significant environmental impacts due to potential oil spills.
The Lands Commission held public hearings on December 3, 2008, and January 29, 2009, at which it discussed and ultimately approved the final EIR. Plaintiffs appeared at the hearings and challenged the sufficiency of the EIR, claiming it omitted consideration of other significant impacts of the terminal’s operation, especially in conjunction with the refinery, causeway, and pipelines. In approving the final EIR on January 29, 2009, the Lands
During the review process there was also discussion about how lease renewal would affect recreational activities on not only the submerged and tidal lands over which the terminal and the causeway sit, but also on the “upland” area where plaintiffs want a portion of the Bay Trail (a hiking and biking trail that will encircle San Francisco Bay) constructed. Chevron met with proponents of the trail and officials of the City of Richmond and entered into a community benefits agreement with the city. This agreement, dated July 31, 2008, obligated Chevron to pay money and provide other consideration to the city if it issues permits for certain projects at the refinery. Chevron’s commitment included specific resources for the Bay Trail, including an easement through its “upland” property and $2 million for any security measures necessary to keep trail users out of sensitive refinery areas.
Although prepared to vote on the lease renewal at the December 3, 2008, hearing, the Lands Commission postponed the vote until January 29, 2009, to provide Chevron and interested government agencies a further opportunity to discuss additional resources for the Bay Trail and make progress on several other issues of public concern. By the January 29 meeting, Chevron agreed to provide a second mile-long easement on its “upland” property for the trail, and also agreed to a plan to reduce nighttime glare from terminal lighting and to report on ship air emissions, which may be subject to future regulation
On March 5, 2009, plaintiffs filed a combined petition for writ of mandate (under Code Civ. Proc., §§ 1085 and 1094.5 and Pub. Resources Code, §§ 21168 and 21168.5) and complaint for declaratory relief. They filed an amended petition and complaint on March 27, alleging two causes of action against the Lands Commission: one for violation of CEQA and one for violation of the public trust doctrine. Plaintiffs sought a writ directing the Lands Commission to decertify the EIR and vacate its approval of the lease renewal, and a declaration the commission had violated CEQA and the public trust doctrine. The trial court denied plaintiffs’ writ petition and dismissed their complaint for associated declaratory relief on July 19, 2010, and entered judgment in favor of the Lands Commission on September 8, 2010.
A. CEQA
1. Standard of Review
On appeal from a writ of administrative mandate in a CEQA case, this court, just as the trial court, reviews the administrative record for “a prejudicial abuse of discretion.” (Pub. Resources Code, § 21168.5;
2. The Baseline
CEQA “requires a public agency to prepare an [EIR] only on projects that may have significant environmental effects.” (Communities for a Better Environment v. South Coast Air Quality Management Dist. (2010)
As we have discussed, the Lands Commission initially indicated the appropriate baseline should exclude current operations at the marine terminal
a. The Baseline Is Not Contrary to Law
The Supreme Court addressed the selection of CEQA baselines at length in Communities, supra,
“By comparing the proposed project to what could happen, rather than to what was actually happening, the District set the baseline not according to ‘established levels of a particular use,’ but by ‘merely hypothetical conditions allowable’ under the permits.” (Communities, supra,
The Supreme Court observed the “CEQA Guidelines” (Cal. Code Regs., tit. 14, § 15000 et seq.) provide: “ ‘An EIR must include a description of the
The court further observed a “long line of Court of Appeal decisions holds, in similar terms [to the Guidelines], that the impacts of a proposed project are ordinarily to be compared to the actual environmental conditions existing at the time of CEQA analysis, rather than to allowable conditions defined by a plan or regulatory framework.” (Communities, supra,
For example, in Riverwatch v. County of San Diego (1999)
Accordingly, in Communities, the Supreme Court affirmed the Court of Appeal’s directive that writ relief be granted and the matter be sent back to the air quality district to identify an appropriate baseline and reassess the environmental impacts of the proposed low-sulfur fuel project. (Communities, supra, 48 Cal.4th at pp. 327-329.)
As Communities requires, the baseline used by the Lands Commission here reflected “what was actually happening” at the site of the proposed project (Communities, supra,
Despite the foregoing authorities, plaintiffs assert the baseline for a renewal project must exclude current conditions because the approving agency can eliminate them by refusing the renewal. Thus, plaintiffs maintain the baseline here should exclude, at a minimum, use of the marine terminal and, possibly, the physical structure, itself.
However, neither the statute, nor any CEQA case, supports plaintiffs’ revisionist approach to the baseline. To the contrary, the CEQA Guidelines require a “description of the physical environmental conditions in the vicinity of the project, as they exist at the time the notice of preparation [of an EIR] is published!’ and specify “[t]his environmental setting will normally constitute the baseline . . . .” (CEQA Guidelines, § 15125, subd. (a), italics added.) The cases further make clear the baseline must include existing conditions, even when those conditions have never been reviewed and are unlawful. (See Fat, supra, 97 Cal.App.4th at pp. 1280-1281; Riverwatch, supra, 76 Cal.App.4th at pp. 1452-1453; see also Communities, supra,
To state the converse of what the court observed in Bloom, the rule that the baseline should normally reflect “the environment as it exists when a project is approved,” is consistent with the categorical exemption in CEQA for “existing facilities,” meaning “a facility as it exists at the time of the agency’s determination,” not at the time (now several decades ago) when CEQA was enacted. (Bloom, supra,
Ultimately, plaintiffs rely principally on League to Save Lake Tahoe v. Tahoe Regional Planning Agency (E.D.Cal. 2010)
However, as the federal district court, itself, explained in denying a motion for reconsideration based on the California Supreme Court’s then newly issued decision in Communities, it was concerned with the environmental provisions of the Tahoe Regional Planning Compact, an agreement between California and Nevada, and not with CEQA. (League to Save Lake Tahoe v. Tahoe Regional Planning Agency (E.D.Cal. 2010)
b. The Baseline Is Supported by Substantial Evidence
In Communities, the Supreme Court did not attempt to spell out the particulars of the baseline the air quality district was required to adopt on remand, observing the district and ConocoPhillips had emphasized refinery operations are highly complex and current NOx emissions varied greatly depending on a variety of circumstances. (Communities, supra,
Plaintiffs do not dispute that the baseline ultimately utilized by the Lands Commission reflected the then current conditions at the Long Wharf terminal. Indeed, the record shows the Lands Commission selected the baseline looking solely at, and accurately describing, the “physical environmental conditions in
Rather, pointing to the Lands Commission’s initial statement made in 1999 that the baseline should exclude operational use of the terminal and reflect only its structural presence, plaintiffs claim there is no support in the record for the commission’s decision to modify the baseline to reflect the actual conditions at the terminal. Plaintiffs claim the fact the Lands Commission initially selected a baseline that excluded use of the terminal established that a “no-lease” baseline was “more appropriate.”
To begin with, plaintiffs cite no authority supporting the implied premise of their argument—that the Lands Commission could not revisit the baseline during the environmental review process and modify it as the commission deemed appropriate or necessary.
The record also reveals a sound basis for the Lands Commission’s adjustment of the baseline. Chevron presented the commission with information about other baseline determinations being made for proposed San Francisco Bay Area projects, and urged it to take the same approach so there would be uniformity in the environmental review process. In addition, the case law in the area was being developed through decisions such as Fat, supra, 97 Cal.App.4th at pages 1277-1281, which endorsed and followed Riverwatch, supra,
In sum, the Lands Commission did not abuse its discretion in defining the baseline used to assess environmental impacts of the proposed marine terminal lease renewal. The baseline was not contrary to the law, and it was based on substantial evidence.
a. Buried Pipeline Alternative
A compliant EIR considers a “range of reasonable alternatives” to a proposed project to “foster informed decisionmaking and public participation.” (CEQA Guidelines, § 15126.6, subd. (a).) Plaintiffs assert the final EIR failed to consider a particular alternative—the removal of the causeway and burying the pipelines running between the terminal and the refinery. Plaintiffs claim this alternative would have reduced the environmental impact of the proposed marine terminal project by opening up new recreational uses on the bay underneath the causeway and on the beach near the currently exposed pipelines.
“An EIR need not consider every conceivable alternative to a project.” (CEQA Guidelines, § 15126.6, subd. (a).) Moreover, “alternatives shall be limited to ones that would avoid or substantially lessen any of the significant effects of the project.'” (CEQA Guidelines, § 15126.6, subd. (f), italics added; see Pub. Resources Code, § 21083, subd. (b)(2) [EIR did not need to consider impacts that are not “effects of [the] individual project”]; see also In re Bay-Delta, supra, 43 Cal.4th at pp. 1167-1168 [appellate court should not have considered alternative concerning delta environmental problems that would continue to exist even without the proposed project; such problems were part of the baseline, and the alternative did not address adverse environmental impacts of the proposed project]; Tracy First v. City of Tracy (2009)
The same analysis applies here. The final EIR identified potential significant impacts due to oil spills, but not due to impediment of recreation. Accordingly, the EIR did not need to address the causeway removal and buried pipeline alternative urged by plaintiffs, since it was directed at an asserted impact not identified in the EIR. Furthermore, given that the baseline properly reflected existing conditions, which included the causeway and pipelines supported thereby, the final EIR correctly concluded the asserted impact on recreational uses was not a potential significant impact of the lease renewal project.
A project “refers to the activity which is being approved and which may be subject to several discretionary approvals by governmental agencies.” (CEQA Guidelines, § 15378, subd. (c).) Plaintiffs assert the final EIR did not adequately describe the “project” before the Lands Commission and, specifically, claim the project description should have included Chevron’s entire refinery operation, as well as continued use of the Long Wharf marine terminal.
However, the only approval at issue is the Lands Commission’s renewal of the lease for continued use of the marine terminal on submerged land owned by the state and controlled by the commission. The refinery, in contrast, sits on private property presently owned by Chevron and requires no approvals by the commission for continued operations.
The cases cited by plaintiffs in support of their broader project description argument are inapposite. Both Tuolumne County Citizens for Responsible Growth, Inc. v. City of Sonora (2007)
c. Cumulative Impacts
Even though a project’s impact may be “individually limited,” such impact may be “cumulatively considerable.” (§ 21083, subd. (b)(2); CEQA Guidelines, § 15065, subd. (a)(3).) “ ‘[Cjumulatively considerable’ means that the incremental effects of an individual project are considerable when viewed in connection with the effects of past projects, the effects of other current projects, and the effects of probable future projects.” (§ 21083, subd. (b)(2); see CEQA Guidelines, § 15065, subd. (a)(3).) “An EIR shall discuss cumulative impacts of a project when the project’s incremental effect is cumulatively considerable . . . .” (CEQA Guidelines, § 15130, subd. (a).) Plaintiffs assert the final EIR failed to address environmental impacts of the marine terminal cumulatively with impacts of the refinery. They specifically complain the EIR
However, the final EIR did consider the cumulative impact of water discharges from the terminal and the refinery into the bay. Section 4.2.1 of the draft EIR sets forth the state of the bay’s water quality, and page 4.2-5 of that section discusses discharges from the refinery. Pages 4.2-55 to 4.2-58 of the draft EIR address cumulative impacts of the terminal’s discharge and other discharges into the bay, including those from the refinery. Moreover, consideration of these water discharges was not required here. As we have discussed, the baseline for assessing the environmental impacts of the lease renewal project properly reflected the marine terminal’s then current operative condition, which included the water discharges. Accordingly, the EIR did not need to consider the cumulative impact of these discharges because they were not “effects of [the] individual project” under consideration. (See § 21083, subd. (b)(2).)
d. San Francisco Bay Area Water Trail Act
The San Francisco Bay Area Water Trail Act (Gov. Code, §§ 66690-66694) provides for the future creation of a water trail for recreational boating around the San Francisco Bay. Plaintiffs complain the final EIR failed to identify renewal of the marine terminal lease as “inconsistent” with the act. We need not and do not decide whether the act is merely enabling legislation (as the Lands Commission and Chevron maintain), or a regional “plan” requiring attention and discussion in a CEQA review. Nor do we need to decide whether the terminal’s presence in the bay truly obstructs such a water trail. Again, as we have discussed, the baseline for assessing the environmental impacts of the lease renewal project properly reflected the marine terminal’s then current operative condition, which included its physical structure. Accordingly, the EIR did not need to consider impacts of that existing structure on the water trail because they were not “effects of [the] individual project” under consideration. (See § 21083, subd. (b)(2).)
Local and regional plans call for construction of the Bay Trail, a multipurpose, land-based recreational trail around the San Francisco Bay. Plaintiffs complain the Lands Commission also failed to acknowledge “inconsistency” between the terminal lease renewal and Bay Trail plans.
However, the draft EIR clearly considered the issue at pages 4.5-15 to 4.5-16. It concluded the Bay Trail, if built to plan, would run through the privately owned “upland” area containing supporting facilities for the terminal—land not considered to be subject to a public trust easement and the Lands Commission’s control, and land not involved in the marine terminal lease renewal project at issue here. Accordingly, the Lands Commission believed it had no authority to impose trail conditions in connection with renewal of the terminal lease. Nevertheless, the Lands Commission urged the interested parties to discuss the issue and see if they could reach some agreement to facilitate development of the trail. It thus deferred final approval of the EIR and lease renewal for a month, and the parties voluntarily entered into a side agreement whereby Chevron agreed to provide two easements across its refinery property and $2 million toward security along that portion of the trail once it is constructed.
In any case, as we have discussed, the baseline for assessing the environmental impacts of the lease renewal project properly reflected the conditions “on the ground” at the time, which included the presence of supporting facilities, such as the pipelines crossing the upland area. Accordingly, the EIR did not need to consider impacts of the existing terminal support facilities on the Bay Trail plans because these impacts were not “effects of [the] individual project,” i.e., the marine terminal lease renewal, under consideration. (See § 21083, subd. (b)(2).)
f. Trustee Agencies
Citing sections 21080.4, subdivision (a), and 21104, plaintiffs contend the Lands Commission failed to “consult” with the State Coastal Conservancy (Conservancy) and California’s Department of Fish and Game (Department) about the marine terminal lease renewal project.
Section 21080.4, subdivision (a), requires a lead agency (responsible for the environmental review of a proposed project) to “send notice” to other
Section 21104 requires “the state lead agency [to] consult with, and obtain comments from, each responsible agency, trustee agency, any public agency that has jurisdiction by law with respect to the project. . . .” (§ 21104.) The notice the Lands Commission sent to the Conservancy and Department asked for comments within 45 days as provided for by CEQA and its guidelines. (§21091, subd. (a); CEQA Guidelines, §15105, subd. (a).) Neither the Conservancy nor the Department provided comments. CEQA Guidelines anticipate there may be no response, and therefore provide if “any public agency or person who is consulted with regard to an EIR . . . fails to comment within a reasonable time as specified by the lead agency, it shall be assumed, absent a request for a specific extension of time, that such agency or person has no comment to make.” (CEQA Guidelines, § 15207.) Accordingly, there was no failure by the Lands Commission to consult with trustee agencies.
g. Response to Public Comments
Public comments allow an agency “to identify, at the earliest possible time in the environmental review process, potential significant effects of a project, alternatives, and mitigation measures.” (§ 21003.1, subd. (a).) Considering timely comments from the public on draft EIR’s is a statutory obligation. (§ 21091, subd. (d)(1).) But not all comments require a response. “ ‘[A] lead agency need not respond to each comment made during the review process, however, it must specifically respond to the most significant environmental questions presented....’ ” (A Local & Regional Monitor v. City of Los Angeles (1993)
To begin with, both the draft EIR (in §§ 4.5.1 and 4.5.4) and responses to comments addressed comments raising recreational and Bay Trail issues. In any case, as we have explained, these were existing conditions and not impacts the EIR for the marine terminal lease renewal project was required to discuss. Accordingly, no response to these comments was required. (See Environmental Protection Information Center v. California Dept. of Forestry & Fire Protection (2008)
Finally, plaintiffs assert the Lands Commission’s statement of findings and overriding considerations, adopted when it approved the lease renewal, was not supported by substantial evidence.
If an EIR finds a project will have significant environmental impacts, the agency responsible for the project must make a statement of findings for each impact. The agency may find (a) it has adopted changes to the project that mitigate or avoid the impact, (b) another agency has or should adopt such changes, or (c) economic, social, or other considerations make such changes infeasible. (§ 21081; Village Laguna of Laguna Beach, Inc. v. Board of Supervisors (1982)
Plaintiffs’ argument that the Lands Commission’s statement of findings and overriding considerations is inadequate is a recycled medley of their separate challenges to the final EIR, each of which we have already addressed and rejected. We therefore do not revisit these issues here. As we have discussed, the Lands Commission selected an appropriate baseline by which to assess environmental impacts of the lease renewal, and the final EIR properly addressed identified impacts of the lease renewal project and adequately addressed those impacts.
B. Public Trust Doctrine
In addition to their CEQA challenge, plaintiffs contend the Lands Commission violated the public trust doctrine when it renewed the marine terminal lease. Plaintiffs do not dispute that the maintenance and operation of the terminal is a permissible public trust use. Nor do they dispute that the Lands Commission may, in its capacity as acting trustee of the public trust for the state, lease out the marine terminal facilities. Rather, plaintiffs claim that before approving the lease renewal, the Lands Commission was required to consider other public trust uses of the property, specifically recreational uses, and to mitigate impacts on those uses to the greatest extent possible. In other words, plaintiffs maintain the CEQA environmental review process was insufficient, and the Lands Commission was required, under the public trust doctrine, to undertake an additional review process and impose additional mitigation conditions. As we explain, in this case, where the Lands
1. Overview of the Doctrine
When California was admitted to the Union in 1850 it acquired ownership of all tidelands and the beds of all inland navigable waters within its borders. (City of Berkeley v. Superior Court (1980)
The public trust doctrine, “traceable to Roman law, rests on several related concepts. First, that the public rights of commerce, navigation, fishery, and recreation are so intrinsically important and vital to free citizens that their unfettered availability to all is essential in a democratic society. [Citation.] ‘An allied principle holds that certain interests are so particularly the gifts of nature’s bounty that they ought to be reserved for the whole of the populace. . . . Ffl] Finally, there is often a recognition, albeit one that has been irregularly perceived in legal doctrine, that certain uses have a peculiarly public nature that makes their adaptation to private use inappropriate. The best known example is found in the rule of water law that one does not own a property right in water in the same way he owns his watch or his shoes, but that he owns only an usufruct—an interest that incorporates the needs of others. It is thus thought to be incumbent upon the government to regulate water uses for the general benefit of the community and to take account thereby of the public nature and the interdependency which the physical quality of the resource implies.’ ” (Zack’s, supra,
2. Standard of Review
The parties dispute the standard by which we should review the Lands Commission’s action. Plaintiffs focus on the commission’s renewal of the marine terminal lease, maintain the renewal was a quasi-adjudicatory, decision, and therefore the commission’s determination to continue the existing public trust use of the bay land and waters should be reviewed under the abuse of discretion standard set forth in Code of Civil Procedure section 1094.5. That section, which provides for, and specifies the scope of judicial review in, administrative mandamus actions, applies when the underlying administrative proceeding is one “in which by law a hearing is required to be given, evidence is required to be taken, and discretion in the determination of facts is vested in” the agency. (Code Civ. Proc., § 1094.5, subd. (a).) “[T]he intent of the Legislature in enacting [Code of Civil Procedure section] 1094.5 was to authorize ‘.. . judicial review only of the exercise by an administrative agency of an adjudicatory or quasi-judicial function.’ ” (Langsam v. City of Sausalito (1987)
The scope of judicial review of such an adjudicatory or quasi-adjudicatory decision is set forth by the statute: “The inquiry in such a case shall extend to the questions whether the respondent has proceeded without, or in excess of, jurisdiction; whether there was a fair trial; and whether there was any prejudicial abuse of discretion. Abuse of discretion is established if the respondent has not proceeded in the manner required by law, the order or decision is not supported by the findings, or the findings are not supported by the evidence.” (Code Civ. Proc., § 1094.5, subd. (b).) On appeal, the Court of Appeal applies the same standard of judicial review as the trial court. (See Ryan v. California Interscholastic Federation-San Diego Section (2001)
Chevron focuses on the Lands Commission’s decision to continue the existing public trust use, namely the maintenance and use of a marine terminal. Chevron contends the commission’s choice of this trust use, rather than another, is a quasi-legislative determination subject to judicial review under the traditional mandamus statute, Code of Civil Procedure section 1085. (See Western States, supra, 9 Cal.4th at pp. 567-568 [quasi-legislative actions are properly challenged in traditional mandamus action under § 1085, even when agency is required to hold a hearing and take evidence]; Langsam, supra,
Judicial review of agency actions that are quasi-legislative in character is under a more deferential, arbitrary and capricious standard. (See San Francisco Fire Fighters Local 798 v. City and County of San Francisco (2006)
3. Procedural Requirements
Plaintiffs contend National Audubon, supra,
The Supreme Court observed, “the public trust doctrine and the appropriative water rights system . . . developed independently of each other” and “[e]ach developed comprehensive rules and principles which, if applied to the full extent of their scope, would occupy the field of allocation of stream waters to the exclusion of any competing system of legal thought.” (National Audubon, supra,
“[D]rawing upon the history of the public trust [doctrine] and the [appropriative] water rights system, the body of judicial precedent, and the views of expert commentators,” the court arrived at several guiding principles, including that “[t]he state has an affirmative duty to take the public trust into account in the planning and allocation of water resources, and to protect public trust uses whenever feasible.” (National Audubon, supra, 33 Cal.3d at pp. 445-446.) The court also noted that while the state may “prefer one trust use over another,” it may not simply “abrogate the public trust merely by authorizing a use inconsistent with the trust.” (Id. at pp. 439, fn. 21, 440.) The court thus concluded the water resources agency could not recognize private water rights in nonnavigable streams to the complete derogation of public trust uses in downstream navigable waters. Rather, the agency had both the authority and obligation to consider harm to the public trust when making such water allocation decisions. (Id. at pp. 447-448.)
Plaintiffs also rely heavily on Carstens v. California Coastal Com. (1986)
“The administrative record demonstrate[ed] the [coastal commission considered the conflicting policy concerns and fashioned a compromise to address the practical realities.” (Carstens, supra,
National Audubon and Carstens are distinctly different from the case at hand. In National Audubon, supra,
Here, in contrast, the Lands Commission did not approve a nonpublic trust use in derogation of public trust uses (let alone balance the policies and dictates of the appropriative water rights system and the public trust doctrine), as was the case in National Audubon. Nor did the commission change public trust uses, as was the case in Carstens. (See also Zack’s, supra, 165 Cal.App.4th at pp. 1179-1180 & fn. 8, 1182-1183 [discussing the “complexity” of choosing between sometimes conflicting public trust uses, observing the petitioner did not contest the city’s “general power as [delegated] trustee to reallocate tidelands from one use to another that also serves trust purposes,” and stating “the questions regarding such a reallocation are whether the other use would be more restricted than the present use or would elevate the interests of private parties over the public interest”].)
Rather, the Lands Commission simply continued the existing, longstanding public trust use of the navigable waters and submerged and partially submerged lands in question. “Ordinarily, a public trustee’s decision that trust land shall be used for a specific purpose . . . stands . . . until the trustee decides to reallocate the land to some other public purpose or to dispose of it if that is congenial to the interests protected by the trust.” (Zack’s, supra, 165 Cal.App.4th at pp. 1182-1183.) Accordingly, we do not read National Audubon or Carstens as imposing on the Lands Commission, here, an obligation to evaluate the other public trust uses urged by plaintiffs, particularly since those recreational uses are to some degree incompatible with the trust use to which the navigable waters and submerged and partially submerged lands in question here have been put for over a century. (Cf. Colberg, Inc. v. State of California ex. rel. Dept. Pub. Wks. (1967)
But even assuming some obligation to “consider” other public trust uses, neither National Audubon nor Carstens impress into the public trust doctrine any kind of procedural matrix. Yet, under plaintiffs’ construction of the doctrine, the Lands Commission was required to (a) identify “other” public trust uses, (b) analyze the impact of maintaining the existing public trust use on those other uses, and (c) determine and require measures to mitigate those impacts to the greatest extent possible. No case discussing the public trust doctrine alludes to such procedural requirements. Indeed, imposing such
Further, National Audubon and Carstens indicate evaluating project impacts within a regulatory scheme like CEQA is sufficient “consideration” for public trust purposes. In National Audubon, for example, the Supreme Court observed: “Amendments to the Water Code enacted in 1955 and subsequent years codify in part the duty of the Water Board to consider public trust uses of stream water. [Citation.] The requirements of the California Environmental Quality Act (. . . § 21000 et seq.) impose a similar obligation. (See Robie, [Some Reflections on Environmental Considerations in Water Rights Administration (1972)] 2 Ecology L.Q. 695.) [f] These enactments do not render the judicially fashioned public trust doctrine superfluous. Aside from the possibility that statutory protections can be repealed, the noncodified public trust doctrine remains important both to confirm the state’s sovereign supervision and to require consideration of public trust uses in cases filed directly in the courts without prior proceedings before the board.” (National Audubon, supra,
In Carstens, as we have observed, the Court of Appeal discussed the public trust doctrine in the context of the regulatory scheme established by the coastal act. The court pointed out that act (like CEQA) expressly makes reference to the public trust doctrine, and the court essentially made no distinction between compliance with the act and the public trust doctrine. (See Carstens, supra, 182 Cal.App.3d at pp. 289-291.)
Center for Biological Diversity, Inc. v. FPL Group, Inc. (2008)
Here, the Lands Commission duly and properly engaged in the environmental review process required by CEQA. In invoking the public trust doctrine, plaintiffs are essentially trying to override significant provisions of that act, namely those pertaining to the baseline used to assess the environmental impacts of a proposed project, and those pertaining to project alternatives and mitigation measures. Plaintiffs have cited no case, and we are aware of none, that suggests that where no change is being made to a public trust use and there has been compliance with CEQA, the public trust doctrine independently imposes an additional impact analysis requirement and requires the consideration of additional project alternatives and mitigation measures in connection with other public trust uses.
Moreover, the CEQA review process here encompassed discussion of other public trust uses. For example, section 4.5 and comment response 4.2 of the draft EIR discussed impacts to recreational boating and other water recreational uses at and around the marine terminal and concluded the lease renewal would not have significant new impacts. During the Lands Commission’s public hearings on the lease renewal on December 3, 2008, and January 29, 2009, commission representatives and members of the public also discussed these issues.
The Lands Commission also facilitated discussions in connection with plaintiffs’ desire to secure significant concessions from Chevron with respect to the Bay Trail. Even though the Lands Commission did not believe it had authority to impose mitigation measures on Chevron’s upland private property, over which there was no public trust servitude, the commission encouraged discussions between Chevron, the proponents of the trail and officials of the City of Richmond. These efforts resulted in Chevron agreeing to provide two mile-long easements across its upland property, and $2 million for any security measures necessary to keep trail users out of sensitive refinery areas. Accordingly, we need not decide the extent of the Lands Commission’s authority. Even if it had such authority, there was no violation of the public
III. Disposition
The judgment is affirmed.
Marchiano, P. J., and Margulies, J., concurred.
A petition for a rehearing was denied January 27, 2012, and the opinion was modified to read as printed above. Appellants’ petition for review by the Supreme Court was denied March 14, 2012, S199966. Baxter, L, and Corrigan, J., did not participate therein.
Notes
These submerged and partially submerged lands were previously owned by the state and sold to Chevron’s predecessor in interest during the 1870’s.
We use the term “renewal” genetically, referencing continued leasing of the property for the same uses.
At the outset of the review process, the Lands Commission concluded the lease renewal did not qualify for the exemption from CEQA for projects involving minor alterations to existing facilities. At the final hearing on the renewal, commission staff acknowledged the exemption arguably applied. However, neither the commission nor Chevron pursued this point during the administrative proceedings. Nor did they do so in the trial court, although the trial court inquired about it. Likewise, on appeal, neither the Lands Commission nor Chevron has urged the exemption as an alternative ground to affirm the judgment.
Chevron’s agreements concerning the Bay Trail, including those made to the City of Richmond in the community benefits agreement of 2008, were reduced to a letter agreement with the Lands Commission. Although the community benefits agreement is no longer in force, the letter agreement persists.
All further statutory references are to the Public Resources Code unless otherwise noted.
Plaintiffs’ distinction between “use” of the marine terminal and its physical structure, seems to us illusory since the terminal was built and exists for the specific use to which it is being put; use and structure, in other words, being hand in glove.
Chevron’s predecessor, Standard Oil, began using the terminal in 1905. Plaintiffs point out the 1947 lease allowed the state to request removal and restoration of the premises to their prelease condition if it conferred with the lessee at least six months before lease termination. However, the state never made any such request.
Yamaha Corp. of America v. State Bd. of Equalization (1998)
Plaintiffs also assert in passing that a hydrogen pipeline project should have been considered in a cumulative impact analysis. This project involves a pipeline originating at the refinery and transporting excess hydrogen to offsite consumers. However, plaintiffs have not identified any impact of the pipeline project the commission should have considered. Furthermore, this court has already concluded, in an earlier case, that the pipeline project is severable for CEQA purposes from a project at the refinery to improve its ability to process crude oil—let alone from the marine terminal lease renewal project at issue in this case. (Communities for a Better Environment v. City of Richmond (2010)
Plaintiffs also cite section 21167.6.5, but make no argument concerning it. Accordingly, they have waived any issue as to this section, and we do not address it. (See McComber v. Wells (1999)
“ ‘The term “tidelands” is often used genetically to cover all the state bust lands in and fronting on the ocean or the bay; but in California, where statutes distinguished various kinds of lands for purposes of disposition, it is useful to separate submerged lands—which are those always covered by water, even at low tide—from tidelands—those covered and uncovered by daily tides, that is, the lands lying between mean high-tide and mean low-tide—and from swamp and overflowed lands—those which are above mean high-tide, but subject to extreme high tides so that marsh grasses grow on them; they are commonly called marshlands.’ ” (Zack’s, Inc. v. City of Sausalito (2008)
