Citizens for a Better Environment-California v. Union Oil Co. of CaliforniaCitizens for a Better Environment-California v. Union Oil Co. of California
This case arises under the federal Water Pollution Control Act (the “Clean Water Act”),
I.
The Clean Water Act regulates the discharge of pollutants into navigable waters. The Act prohibits all discharge of pollutants except inasmuch as one of several enumerated statutory exceptions applies.
UNOCAL owns and operates a petroleum refinery in the San Francisco Bay area of California. Wastewater from the refinery is subject to UNOCAL’s NPDES permit issued by the Regional Board. On February 20, 1991 the Regional Board issued Order No. 91-026, which amended the UNOCAL’s NPDES permit for the San Francisco Bay area refinery. The order set a “final” concentration limit on selenium discharges of 50 parts per billion (“ppb”) and a mass emission rate of .85 pounds per day, calculated on a running annual average. The final selenium limitation was to take effect December 12, 1993. On June 16, 1991 the Regional Board issued Order No. 91-099 amending UNO-CAL’s NPDES permit to include an “interim limit” less stringent than the final limit which took effect immediately and which was to remain in force until the final limit came into effect. UNOCAL is in substantial compliance with the interim limit but is not in compliance with the final limit.
The Regional Board issued these orders pursuant to
The state water board denied an appeal by UNOCAL and other refiners challenging the selenium discharge limits. Shortly thereafter, on October 12, 1992, UNOCAL and others filed a petition for a writ of mandate in the Solano County Superior Court of California seeking to set aside the interim and final limits on the grounds that the Regional Board’s listing of the San Francisco Bay as a “hot spot” violated the Clean Water Act and its implementing regulations.
Over the course of 1993, UNOCAL and others were in settlement discussions with the Regional Board. Although other refiners in the area became able to meet the final limits, UNOCAL and other refiners maintained their inability, due to technological constraints, to meet the final selenium limits. On November 8, 1993, UNOCAL, along with other refiners, reached a settlement agreement whereby UNOCAL and others would dismiss the state lawsuit and the Regional Board would adopt a proposed cease and desist order- (“CDO”). The parties dispute whether the settlement agreement and proposed CDO were released for public comment on November 9, 1993 or November 12, 1993. On November 19, 1993 and December 15, 1993 public hearings were held on the proposed CDO at which CBE participated. The Regional Board, with some minor modifications, issued the CDO on January 19, 1994 as Order No. 94-015.
The principal elements of the settlement agreement and the CDO were that UNOCAL and the other refiners dismissed their state court lawsuit without prejudice, UNOCAL and others paid the state a total of $2 million ($780,000 of which was contributed by UNO-CAL), and the Regional Board issued the CDO which, among other things, relieves UNOCAL and others from meeting the final selenium limit until July 31, 1998. The CDO states, with respect to the latter element, that:
Compliance with this Order shall be in accordance with the following tasks and time schedules:
c. The dischargers shall implement a removal technology or technologies, or an alternate control strategy, which has been determined by the dischargers to be capable of achieving compliance with the discharge limitations as specified in [the NPDES permits] and shall comply with these limits, no later than July 31, 1998.
II.
UNOCAL asserts two arguments as to why dismissal of the effluent standards claim is proper. First, UNOCAL argues that dismissal is warranted because the citizen suit is barred under
A. Is the Citizen Suit Barred Under
The citizen suit provision of the Clean Water Act,
Except as provided in subsection (b) of this section andsection 1319(g)(6) of this title, any citizen may commence a civil action on his own behalf—
(1) against any person ... who is alleged to be in violation of (A) an effluent standard or limitation under this chapter or (B) an order issued by the Administrator [of the EPA] or a State with respect to such a standard or limitation. ...
The district courts shall have jurisdiction ... to enforce such an effluent standard or limitation, or such an order, as the case may be, and to apply any appropriate civil penalties undersection 1319(d) of this title.
[A]ny violation—
(i) with respect to which the Administrator [of the EPA] or the Secretary [of the Army] has commenced and is diligently prosecuting an action under this subsection,
(ii) with respect to which a State has commenced and is diligently prosecuting an action under a State law comparable to this subsection, or
(iii) for which the Administrator, the Secretary, or the State has issued a final order not subject to further judicial review and the violator has paid a penalty assessed under this subsection, or such comparable State law, as the case may be,
shall not be the subject of a civil penalty action under subsection (d) of this section or section 1321(b) of this title orsection 1365 of this title.
1. Applicability of
a. “penalty”
UNOCAL maintains that the $780,000 it paid to the Regional Board constituted a “penalty” within the meaning of
UNOCAL argues, essentially, that it has paid out over $780,000 (10% of which went into the California Water Pollution Cleanup and Abatement Account that is the repository of fines levied pursuant to § 13385, and 90% into a “Selenium Mitigation Fund”)
In support of the formal reasoning of the district court, CBE asserts two additional reasons why UNOCAL may not characterize the payment as a penalty. First, UNOCAL itself insisted on characterizing the financial transfer as a “payment” and not a “penalty” at the time of the state action settlement. CBE notes that counsel for UNOCAL stated at the hearing on the motion to dismiss at the district court that UNOCAL would not, at the time of the settlement of the state lawsuit, “sign on to paperwork that characterized it as a penalty, because of the punitive and bad conduct implications that the general public takes from that term.” CBE, appropriately, in the Court’s view, argues that UNOCAL simply “cannot have it both ways” and that the fairest characterization of the $780,000 payment is that it was not a penalty but, instead, the price of avoiding the stigma of a formal enforcement action.
Second, CBE argues that there are other significant advantages that were obtained by UNOCAL by making a payment independent of the state statutory provision, California Water Act § 13385, that is analogous to the administrative penalty provision of the Clean Water Act,
The Court determines that the fairest characterization of the payment at issue is that it was, indeed, a settlement made to avoid an enforcement action by the Regional Board. Accordingly, because UNOCAL has not paid a “penalty,” the
b. “comparable state law”
Having determined that the payment at issue was not a “penalty,” the district court also concluded that the payment was not “assessed under this subsection, or such comparable State law” within the meaning of
The district court held that the “comparability assessment is conducted by examining the state statutory enforcement provision involved,” here
In Scituate the First Circuit held that the comparability requirement of
alty provisions does not alter the comparability of the State Act’s statutory scheme the scheme found in the Federal Act. While the specific statutory section under which the State issued its Order does not, itself, contain a penalty provision, another section of the same statute does contain penalty provisions. These two coordinate parts are cogs in the same statutory scheme implemented by the State for the protection of its waterways.
Scituate,
In Washington Public Interest Research Group v. Pendleton Woolen Mills this Court interpreted the terms of
The Court concludes that the requirement in
2. Applicability of
The district court concluded that the
UNOCAL has made no contention in its briefs as to why the district court erred in concluding that the action was no longer being “prosecuted” within the meaning of
B. Did the Regional Board’s Cease and Desist Order Effectively Defer the Compliance Date for Selenium Discharges so that UNOCAL is not “in Violation” of an Effluent Standard or Limitation?
UNOCAL asserts that CBE has failed to state a claim because the facts it alleges do not constitute a “violation of an effluent standard or limitation” within the meaning of
The district court concluded that the issuance by the Regional Board of the CDO extending the compliance schedule was akin to an exercise of prosecutorial discretion and did not suspend the limits and deadlines contained in the NPDES permit or shield UNOCAL from this citizen suit. While UNOCAL concedes that the CDO did not purport to modify the NPDES permit and did not constitute a formal amendment or modification of the NPDES permit,
The Court concludes that the federal courts are not precluded from addressing the issue of whether the CDO effectively modified the NPDES compliance date. While it is true that there, were procedures available for CBE to appeal the CDO within the state system, this action does not challenge the validity of the CDO but rather seeks to enforce the requirements of the Clean Water Act. Furthermore,
The Court further concludes that the CDO at issue did not modify, effectively or otherwise, the terms of UNOCAL’s NPDES permit. This conclusion is appropriate for the following reasons.
First, the CDO does not purport to modify the NPDES permit. In the Findings to the CDO, the Regional Board states in paragraph 4 that “[t]he effluent limitations imposed under Order No. 91-026 [amending the NPDES permit to include the final selenium limits] become effective on December 12, 1993_ The Regional Board is adopting this Order to enforce the provisions of
Second, as noted above, federal and state regulations govern the modification of NPDES permits. It is not disputed that these regulations were not followed in this case. These regulations, both procedural and substantive, ensure that the standards embodied in an NPDES permit cannot be evaded with the cooperation of compliant state regulatory authorities. For instance, there are public notice requirements for a permit modification process that are different than those required in an enforcement action. Further, there is a five year duration on the life of an NPDES permit that the “effective modification” asserted here would violate.
Third, even if the CDO were to be construed as having effectively extended the compliance date in the NPDES permit, such a modification would likely run afoul of the substantive constraint on the ability of regulators to modify permits found in
III.
For the foregoing reasons, the district court’s denial of UNOCAL’s motion to dismiss is AFFIRMED.
Notes
. The CDO states, in part, that:
[t]he Regional Board has considered the various enforcement and penalty options available to it regarding the violation [of the NPDES permit], including the issuance of a cease and desist order or a cleanup or abatement order, imposition of an administrative civil penalty and referral to the Attorney General for civil prosecution. Under the circumstances detailed in the Findings set forth above, the Regional Board has determined that the most appropriate course of action is settlement of the litigation and issuance of a cease and desist order.
. The Appellees argue, however, that this cuts against the Appellant because
. Although the parties dispute the degree of similarity to the requirements of
. As the Supreme Court has stated, "the starting point for interpreting a statute is the language of the statute itself." Gwaltney,
. Indeed, the Appellant raised this provision in the district court only in a footnote of its briefs and it was dealt with by the district court in a footnote to its decision.
.
Except as provided in subsection (b) of this section andsection 1319(g)(6) of this title, any citizen may commence a civil action on his own behalf—
(1) against any person ... who is alleged to be in violation of (A) an effluent standard or limitation under this chapter or (B) an order issued by the Administrator [of the EPA] or a State with respect to such a standard or limitation....
. There are specific, mandatory procedure for NPDES permit modification. Cal.Code Regs. Tit. 23, § 2235;
. Appellant has asserted that two such exceptions are applicable. Appellant asserts that "new information is available” that "would have justified" a less stringent standard under