425 F.2d 97 | 2d Cir. | 1970
The present appeal is a consolidation, ordered by this Court on October 27, 1969, of several separate appeals taken from a final order and judgment entered by the district court on July 25, 1969. Trial and judgment below in turn followed a consolidation of four separate actions brought by the various plaintiffs against the various defendants here on appeal. The opinion of the district court, setting out the facts, the various claims and Judge Murphy’s conclusions of law, is reported at 302 F.Supp. 1083 (S.D.N.Y.1969).
These actions arose out of a proposal by the New York State Department of Transportation for construction of the Hudson River Expressway. The plaintiffs object to the proposed construction of a six-lane arterial highway, designed for both commercial and passenger traffic, along a ten-mile stretch of the Hudson River’s eastern bank between Tarry-
Upon application of the State of New York, the United States Army Corps of Engineers (the Corps) issued a permit authorizing the dredge and fill operation pursuant to its authority under the Rivers and Harbors Act of 1899, 33 U.S.C. § 401 et seq. Arguing that the proposed construction involved both a “dike” and a “causeway” within the meaning of § 401, the plaintiffs sought (1) a declaration that the permit as issued was beyond the scope of the Army’s authority, and (2) injunctive relief to prohibit the issuance of any permit or the commencement of any construction in the absence of congressional consent and approval of the Secretary of Transportation.
The plaintiffs also appeal from a portion of the district court’s order which dismissed their claims against Mc-Morran as a primary defendant. These claims challenged the constitutionality of the Expressway Law,
Important threshold questions on this appeal involve the jurisdiction of the district court over the subject matter of these actions, and the standing of these plaintiffs to seek review of agency action in federal court. We turn first to jurisdiction.
I.
The district court rested its jurisdiction on the Administrative Procedure Act, 5 U.S.C. § 701 et seq. (Supp. IV). Section 702 provides as follows: “A person suffering legal wrong because of agency action, or adversely affected or aggrieved by agency action within the meaning of a relevant statute, is entitled to judicial review thereof.” Section 704 states that “[ajgeney action made reviewable by statute and final agency action for which there is no other adequate remedy in a court are subject to judicial review.” Section 706(2) (C) permits the reviewing court to set aside agency action found to exceed the agency’s statutory authority.
The statute pursuant to which the Army Chief of Engineers issued the disputed permit contains no provision for judicial review, nor does it include specific procedures for appeal of the Army’s decision. Review of the action is therefore determined by the provisions of the Administrative Procedure Act, applicable to all administrative actions or proceedings “except to the extent that — (1) statutes preclude judicial review; or (2) agency action is committed to agency discretion by law.” 5 U. S.C. § 701 (Supp. IV). Nothing in the Rivers and Harbors Act suggests that judicial review is precluded, and it is clear from a reading of § 401 that approval of projects involving the construction of “dikes” and “causeways,” rather than being “committed to agency discretion by law,” was, on the contrary, expressly reserved to Congress. The federal defendants contend that the landfill permit was governed by § 403, committing certain types of shoreline construction to the Army’s discretion. But whether or not the Army could exercise its authority under § 403 without reference to § 401 was a matter of statutory construction obviously subjected to full review in the district court by the Administrative Procedure Act, 5 U.S.C. § 706. The district court properly relied on the presumption of reviewability embodied in the Administrative Procedure Act where there was no evidence of a congressional intent to prohibit review in the Rivers and Harbors Act. As the Supreme Court has twice held “only upon a showing of ‘clear and convincing evidence’ of a contrary legislative intent should the courts restrict access to judicial review.” Abbott Laboratories v. Gardner, 387 U.S. 136, 141, 87 S.Ct. 1507, 1511, 18 L.Ed.2d 681 (1967); accord, Rusk v. Cort, 369 U.S. 367, 379-380, 82 S.Ct. 787, 7 L.Ed.2d 809 (1962); Kletscha v. Driver, 411 F.2d 436 (2d
There can be no question at this late date that Congress intended by the Administrative Procedure Act to assure comprehensive review of “a broad spectrum of administrative actions,” including those made reviewable by specific statutes without adequate review provisions as well as those for which no review is available under any other statute. Abbott Laboratories v. Gardner, supra, 387 U.S. at 140, 87 S.Ct. 1507; see S.Rep.No. 752, 79th Cong. 1st Sess., 26 (1945); H.R.Rep. No. 1980, 79th Cong. 2d Sess., 41 (1946). Since the Army’s issuance of this permit was final agency action for which there is no other adequate remedy in a court, and review is not clearly and convincingly precluded by the Rivers and Harbors Act, the Administrative Procedure Act must-be read to confer equitable jurisdiction on the district court to protect by injunctive relief such rights as the plaintiff may have standing to assert. Kletscha v. Driver, 411 F.2d 436, 445 (2d Cir. 1969). In our discussion of standing, infra, we conclude that these plaintiffs are “aggrieved by agency action within the meaning of a relevant statute” and are therefore entitled to review. The district court has the power under § 706 to set aside agency action in excess of statutory authority, and we agree with the district court that issuance of the permit here exceeded the Army’s authority. Under these circumstances, if the Administrative Procedure Act could not itself serve as a basis for jurisdiction, the important goal of subjecting final agency action to judicial scrutiny would be frustrated. We therefore conclude that the district court properly assumed jurisdiction.
II.
Reference was likewise made to the Administrative Procedure Act to determine the plaintiffs’ standing to obtain review. Their right to review was based on the Act’s provision that “[a] person suffering legal wrong or * * * aggrieved by agency action within the meaning of a relevant statute, is entitled to judicial review thereof.” 5 U.S.C. § 702. Two of the plaintiffs (the Citizens Committee and the Sierra Club) made no claim that the proposed Expressway or the issuance of the dredge and fill permit threatened any direct personal or economic harm to them. Instead they asserted the interest of the public in the natural resources, scenic beauty and historical value of the area immediately threatened with drastic alteration, claiming that they were “aggrieved” when the Corps acted adversely to the public interest. They are, as the federal defendants observe, serving as “private Attorney Generals” to protect the public interest. See Associated Industries of State of New York v. Ickes, 134 F.2d 694, 704 (2d Cir. 1943).
Allowance of standing to private attorneys general in “public actions”
The Supreme Court has observed that the law of standing is a “complicated specialty of federal jurisdiction, the solution of whose problems is in any event more or less determined by the specific circumstances of individual situations * * *United States ex rel. Chapman v. F. P. C., 345 U.S. 153, 156, 73 S.Ct. 609, 612, 97 L.Ed. 918 (1953). Judge (now Chief Justice) Burger, in his Office of Communication of United Church of Christ v. F. C. C., supra, opinion characterized the concept of standing as “a practical and functional one designed to insure that only those with a genuine and legitimate interest can participate in a proceeding * * *.” Id. 359 F.2d at 1002.
■We have already described the situation confronting the plaintiffs — the prospect of massive alteration of the Hudson River shoreline and of the physical environment for some ten miles along the river’s bank. The Citizens Committee for the Hudson Valley (Citizens Committee) is an unincorporated association of citizens who reside near the proposed Expressway. The Sierra Club is a national conservation organization with substantial membership also in the area of the Expressway, and a history of involvement in the preservation of national scenic and recreational resources. Tarry town is an incorporated village, and the planned Expressway would pass through its boundaries at the southern end of the roadway. All plaintiffs made a vigorous effort to present their views to the New York Department of Transportation and to the federal officials responsible for granting the disputed permit. They have evidenced the seriousness of their concern with local natural resources by organizing for the purpose of cogently expressing it, and the intensity of their concern is apparent from the considerable expense and effort they have undertaken in order to protect the public interest which they believe is threatened by official action of the federal and state governments. In short, they have proved the genuineness of their concern by demonstrating that they are “willing to shoulder the burdensome and costly processes of intervention” in an administrative proceeding. United Church of Christ, supra, 359 F.2d at 1005. They have “by their activities and conduct ■x- * # exhibited a special interest in” the preservation of the natural resources of the Hudson Valley. Scenic Hudson Preservation Conf., 354 F.2d 608, 616 (2d Cir. 1965). It remains for us to examine whether there is legal justification for their intervention — whether there is a “legally protected interest” at stake which they can assert because of their special concern.
In Scenic Hudson, supra, we set aside an order of the Federal Power Commission granting a license to Consolidated Edison Company of New York to construct a hydroelectric project on the west side of the Hudson River at Storm
The Rivers and Harbors Act has no review provisions corresponding to those in the Federal Power Act. Nevertheless, persons “aggrieved” by agency action pursuant to that statute are entitled to review on similar terms by the Administrative Procedure Act. We agree with the conclusion of Judge McLean in Road Review League v. Boyd, 270 F.Supp. 650, 661 (S.D.N.Y.1967) that the meaning of “aggrieved” in one act is not different from its meaning in the other.
* * * the decision as to whether a permit will be issued must rest on an evaluation of all relevant factors, including the effect of the proposed work on navigation, fish, and wildlife, conservation, pollution, aesthetics, ecology, and the general public interest. 33 CFR 209.120(d).9
Thus administrative as well as congressional concern for natural resources in the present exercise of federal authority is evident. We hold, therefore, that the public interest in environmental resources — an interest created by statutes affecting the issuance of this permit — is a legally protected interest affording these plaintiffs, as responsible representatives of the public, standing to obtain judicial review of agency action alleged to be in contravention of that public interest. Scenic Hudson Preservation Conf. v. F. P. C., supra; State of Washington Dept. of Game v. F. P. C., 207 F.2d 391 (9th Cir. 1953); Road Review League v. Boyd, supra.
III.
The federal defendants challenge the standing of the Village of Tarry-town on a somewhat different ground. Conceding that the Village may have standing to challenge construction of the Expressway itself,
IV.
We turn now briefly to the merits of the controversy. After 29 days of trial, during which numerous exhibits were offered (including a model of the proposed Expressway), experts were examined, maps, charts and technical dictionaries were consulted and the facts were exhaustively presented, the district court concluded that construction of both a “dike” and a “causeway” were contemplated by the State. The court was called upon to construe the meaning of those terms as they were used in § 401 of the Rivers and Harbors Act of 1899, and as they applied in fact to the Expressway plans before it. Having carefully reviewed the pertinent evidence and considered the governing rules of statutory construction, we adopt the conclusion of the district court that the word “dike” used by the defendants in their permit has the same meaning there as in § 401 of the Act, and that construction of a dike is forbidden by that Section without the consent of Congress.
We likewise agreed that the Corps of Engineers should not have ignored the prospect that a “causeway” within the meaning of § 401 was to be a part of the project it was approving, and that approval of the Secretary of Transportation would later be required. Any further federal role in consideration of this massive project would be effectively foreclosed by the Army’s acquiescence in a 9.5 million cubic-yard landfill, to be undertaken at great expense to the New York taxpayers. Indeed Congress, which also must approve construction of a causeway over navigable waters, would, in practical effect, be precluded from reversing such a course of action already begun pursuant to the present permit issued by the Army.
V.
The district court held that the plaintiffs’ constitutional claims were without merit, and we agree. As we understand their argument, three separate delegations of power to McMorran combine to constitute, in their view, an abdication of legislative responsibility in construction of this Expressway. The Expressway law itself is an eight-line statute
On this appeal, the plaintiffs have not developed the facts or the law sufficiently to be persuasive. The Expressway statute certainly offers very little guidance for major decision which the Department of Transportation is authorized to make. McMorran cites a bevy of regulations, as does the district court, as restrictions on this power, but few of them appear to be relevant to these major decisions. Thus the statute itself sets the bounds of McMorran’s discretion, which is very broad. However, nullification of statutory delegations of discretionary authority in major public works projects on grounds of due proc
Affirmed.
. Rivers and Harbors Act of 1899, section 9, 33 U.S.C. § 401, provides in pertinent part:
It shall not be lawful to construct or commence the construction of any bridge, dam, dike, or causeway over or in any * * * navigable river * * of the United States until the consent of Congress to the building of such structures shall have been obtained and until the plans for the same shall have been submitted to and approved by the Chief of Engineers and by the Secretary of the Army * * *.
The defendants contend that construction of the landfill as proposed was referable only to section 10 of the Act, 33 U.S.C. § 403, which provides in part:
The creation of any obstruction not affirmatively authorized by Congress, to the navigable capacity of any of the waters of the United States is prohibited ; and it shall not be lawful to build or commence the building of any wharf, pier, dolphin, boom, weir, breakwater, bulkhead, jetty, or other structures in any * * * navigable river, or other water of the United States * * * except on plans recommended by the Chief of Engineers and authorized by the Secretary of the Army ; and it shall not be lawful to excavate or fill [in a navigable waterway of the United States] * * * unless the work has been recommended by the Chief of Engineers and authorized by the Secretary of the Army prior to beginning the same.
Approval of the Secretary of Transportation is required where construction of a bridge or causeway is contemplated by virtue of the Department of Transportation Act, 49 U.S.C. § 1655(g) (1966), which transferred jurisdiction over bridges and causeways from the Secretary of the Army to the Secretary of Transportation. See Judge Murphy’s discussion of the statutory interrelationships in the opinion below, 302 F.Supp. at 1087.
. Highway Law § 340c, as amended (McKinney’s Consol.Laws, c. 25, 1966), reads in pertinent part:
Beginning at a point on interstate route 503 in the vicinity of Beacon or Wiccopee, to be determined by the superintendent of public works [now the Commissioner of Transportation], thence in a generally southerly direction to the*101 vicinity of Ossining and thence continuing southerly, west of U. S. route nine, along or near the Hudson River to a connection or connections with existing highways, as determined by the [Commissioner of Transportation] in the vicinity of the structure on the Governor Thomas E. Dewey Tliruway known as “The Tappan Zee Bridge.”
. See generally L. Jaffe, Judicial Control of Administrative Action 459-500 (1965); K. Davis, Administrative Law § 22.05 (1958).
. In Church of Christ, a citizens group pressing an organized protest against renewal by the ECC of a radio broadcasters license, alleging that the broadcaster had ignored the listening needs of nearly half the listening audience, was held to have standing before the Commission as a group representative of broadcast “consumers.” Judge Burger treated the question of standing before the Commission as equivalent to standing for judicial review, 359 F.2d at 1000 n. 8, and cited as authority for his grant of standing to members of the general public, inter alia, Scenic Hudson Preservation Conf. v. F. P. C., 354 F.2d 608 (2d Cir. 1965).
. Federal Power Act § 10(a), 16 U.S.C. § 803(a) reads in part:
All licenses issued * * * shall be on the following conditions: (a) That the project adopted * * * shall be such as in the judgment of the Commissioner will be best adapted to a comprehensive plan for improving or developing a waterway or waterways for the use or benefit of interstate or foreign commerce, for the improvement and utilization of water-power development, and for other beneficial public uses, including recreational purposes; * * *
. The pertinent review provisions are contained in section 313(b) of the Federal Power Act, 16 U.S.C. § 8251(b) :
(b) Any party to a proceeding under this chapter aggrieved by an order issued by the Commission in such proceeding may obtain a review of such order in the United States Court of Appeals for any circuit wherein the licensee or public utility to which the order relates is located * * *.
. The defendants concede that the Road Review decision, if correct, is controlling here. Road Review was decided under the Federal Highways Act, 23 U.S.C. § 101 et seg. which, like the Rivers and Harbors Act, contained no review provisions. Judge McLean relied on the Administrative Procedure Act to find both jurisdiction over the subject matter and stands ing for the plaintiffs, among whom were non-profit civic organizations and a town, for practical purposes identical to the plaintiffs in the present case. As our present decision makes clear, we believe Judge McLean’s decision in Road Review was correct.
. Department of Transportation Act of 1966, as amended by § 18(b) of the Act of August 23, 1968, 82 Stat. 824, 49 U.S.C. § 1653(f) (Supp. IV). The merits of the plaintiffs’ claims are entwined with their standing to maintain them. One of their contentions was that a portion of the proposed expressway constituted a causeway and, therefore, that the Corps erred in failing to secure the consent of the Secretary of Transportation pursuant to the Department of Transportation Act. Since we are in agreement with the district court that the plans for the expressway did envision the construction of a causeway, see infra, the Department of Transportation Act is a “relevant” statute, and the concern it evidences for preservation of the environment serves to reinforce our decision that the plaintiffs have standing to maintain this action.
. See also Fish and Wildlife Coordination Act of 1934, as amended, 16 U.S.C. § 662(a); Fish and Wildlife Act of 1956, as amended, 16 U.S.C. § 742a et seg.; Memorandum of Understanding between the Secretary of the Interior and the Secretary of the Army, 33 CFR 209.120(d) (11). Claims relevant to most of these factors were advanced by the plaintiffs throughout the proceedings in connection with their contention that issuance of the permit was “arbitrary and capricious.” The district court did not reach the “arbitrary and capricious” claim in deciding for the plaintiffs, and we need not consider it here.
. The district court found that the Village of Tarrytown would suffer “loss of tax revenues and interference with the Urban Renewal project already in progress in the Village.” 302 F.Supp. at 1092. See Scenic Hudson Preservation Conf. v. F. P. C., 354 F.2d at 616.
. Note 2, supra.