CITIZENS AWARENESS NETWORK, WOMEN‘S VOICES FOR THE ENVIRONMENT, and CLARK FORK COALITION, Petitioners and Appellants, v. MONTANA BOARD OF ENVIRONMENTAL REVIEW, Respondent and Appellees, and MONTANA DEPARTMENT OF ENVIRONMENTAL QUALITY and THE THOMPSON RIVER CO-GEN, LLC, Respondent-Intervenors and Appellees.
No. DA 09-0070.
Supreme Court of Montana
Decided January 26, 2010.
2010 MT 10; 355 Mont. 60; 227 P.3d 583
Submitted on Briefs November 12, 2009.
For Appellees: David M. Rusoff, Attorney at Law; Helena (Department of Environmental Quality); Michael J. Uda, Susanne F. Bessette; Doney Crowley Bloomquist Payne Uda, P.C.; Helena (Thompson River Power).
JUSTICE LEAPHART delivered the Opinion of the Court.
¶1 Citizens Awareness Network, Women‘s Voices for the Environment, and Clark Fork Coalition (collectively, “Conservation Groups“) appeal the order of the District Court for the Twentieth Judicial District, Sanders County, denying their motion for summary judgment and upholding the decision of the Montana Board of Environmental Review (BER) that denied the Conservation Groups’ motion for leave to amend their administrative pleading in a contested casе hearing over the Montana Department of Environmental Quality‘s (DEQ) issuance of an air quality permit for a coal- and wood waste-fired power plant. We reverse and remand.
¶2 The sole issue on appeal is whether the District Court erred in
FACTUAL AND PROCEDURAL BACKGROUND
¶3 Thompson River Power LLC (TRP) owns a coal- and wood waste-fired power plant (“Thompson River facility” or “facility“) in Thompson Falls, Montana, and pursuant to the Clean Air Act of Montana seeks an air quality permit in order to begin operations. An air quality permit will allow TRP to emit air contaminants from the facility into the atmosphere, but will require TRP to take certain steps to control air pollution. See
¶4 DEQ initially issued an air quality permit to TRP‘s predecessor, Thompson Rivеr Co-Gen (TRC),1 in 2001 to construct and operate the Thompson River facility. TRP constructed the facility, installing a used stoker boiler purchased from R.J. Reynolds Corporation, and began to operate it intermittently from December 2004 to September 2005, primarily for testing purposes. DEQ modified TRP‘s permit in 2004 and again in 2005. TRP applied for further modification to its permit in early 2006, and DEQ issued a draft permit. In May 2006 DEQ denied issuance of the desired modification because TRP was not capable of complying with emissions limitations in either its existing permit or the proposed modified permit. TRP subsequently submitted another application for modifications to its air quality permit, and DEQ issued a modified permit to TRP on August 21, 2006. The question before the Court involves the issuance of this last modified permit.
¶5 On September 3, 2006, the Conservation Groups challenged the mоdified air quality permit by requesting a contested case hearing with BER within fifteen days of DEQ‘s decision to issue the permit. On September 19, 2006, the Conservation Groups filed the affidavit required by
¶6 In response to the Conservation Group‘s challenge, DEQ sent written discovery to thе Conservation Groups on November 22, 2006. Later in November, DEQ filed motions to dismiss a number of the Conservation Groups’ claims for failure to state a claim and for lack of subject matter jurisdiction. The hearing examiner eventually denied DEQ‘s motions to dismiss.
¶7 Three months after filing their affidavit, on December 19, 2006, the Conservation Groups sought leave from the hearing examiner to amend their affidavit to add a claim that potential emissions from the Thompson Falls facility would qualify it as a “major stationary source.” Classification of the facility as a major stationary source would subject it to additional air pollution controls under prevention of significant deterioration (PSD) regulations. The Conservation Groups argued that leave to amend was proper under
¶8 TRP and DEQ opposed the Conservation Groups’ motion, arguing that the thirty-day limit in
¶9 The hearing examiner, declining to adopt the reasoning of either party, denied the Conservation Groups leave to amend their affidavit on the basis of
¶10 Subsequently, the hearing examiner held a contested case hearing at which the parties presented evidence and argument. The hearing examiner then issued findings of fact, conclusions of law, and a
¶11 In the District Court, the Conservation Groups contended that BER‘s decision was arbitrary, capricious, an abuse of discretion, and otherwise unlawful. DEQ and TRP intervened. The Conservation Groups moved for summary judgment, which DEQ and TRP opposed. The District Court denied summary judgment and affirmed the decision of BER. In reaching its decision, the District Court reviewed the reasoning of the hearing examiner and concluded that the hearing examiner‘s decision was not arbitrary, capricious, an abuse of discretion, or otherwise unlawful.
¶12 The Conservation Groups timely appealed.
STANDARD OF REVIEW
¶13 We review a district court‘s ruling on summary judgment de novo. Signal Perfection, Ltd. v. Rocky Mt. Bank - Billings, 2009 MT 365, ¶ 9, 353 Mont. 237, 224 P.3d 604. When the district court‘s decision is based on review of an agency action, MAPA governs our review. See Bitterroot River Protective Assn. v. Bitterroot Conserv. Dist., 2008 MT 377, ¶ 18, 346 Mont. 507, 198 P.3d 219. Under MAPA, we will reverse an agency decision if it is based on an incorrect conclusion of law that prejudices the substantial rights of an appellant.
¶14 Justice Cotter, in dissent, objects to our chosen standard of review, raising a number of important points to which we hasten to respond. First, Justice Cotter observes that all parties to the appeal agreed that the standard of review should be abuse of discretion. However, while this is true, ultimately the appropriate standard of review is and should be determined by the Court, rather than by the parties.
¶15 Second, Justice Cotter asserts that the Court mistakenly
¶16 Under
¶17 For these reasons, we respectfully disagree with Justice Cotter that analysis of the propriety of granting leave to amend under
DISCUSSION
¶18 Whether the District Court erred in upholding BER‘s decision denying the Conservation Groups’ motion to amend their administrative pleading.
¶19
¶20 The procedures of MAPA govern a contested case hearing under
¶21
¶22 Once a suit is filed, “the defendant knows that the whole transaction described in it will be fully sifted, by amendment if need be, and that the form of the action or the reliеf prayed or the law relied on will not be confined to their first statement.” Barthel v. Stamm, 145 F.2d 487, 491 (5th Cir. 1944) (cited in Charles Alan Wright, Arthur R. Miller & Mary Kay Kane, Federal Practice and Procedure vol. 6A, § 1497, 93 (2d ed., West 1990)). In determining whether the claim in the amended pleading arises from the same conduct, transaction, or occurrence as the original pleading, we focus on “whether the amended and original pleading are based on the same set of operative facts.” Smith v. Butte-Silver Bow Co., 266 Mont. 1, 10, 878 P.2d 870, 875 (1994). “[A]n amendment which changes only the legal theory of the action ... will relate back.” Simmons, 246 Mont. at 208, 806 P.2d at 8 (quoting Rozan v. Rosen, 150 Mont. 121, 125, 431 P.2d 872, 875 (1967)). Ultimately, the policy of
¶23 Here, the claims that the Conservation Groups sought to add
¶24 The hearing examiner, in denying the Conservation Groups leave to amend the affidavit, reasoned that neither DEQ nor TRP would have been on notice, based on the Conservation Groups’ original affidavit, that the Thompson River facility should be permitted as a major stationary source, and thus subject to PSD regulations.
In the analysis of whether the proposed amendments make more specific what has already been alleged, there are no allegations in the Notice of Appeal and Request for Hearing, the original Affidavit or the comments that address factors which would cause the Department or the Permittee to consider that the permittee should be permitted as a major stationary source. It is a leap to say that the Department or the permittee should have been on notice from the comments that at the TRC plаnt the actual heat input to the boiler would result in the potential to emit at levels greater than 250 tons per year of NOx and SO2.
This reasoning is mistaken for a number of reasons. First, the hearing examiner did not expressly consider whether the proposed amended claims arose from the same transaction or occurrence as the original claim, and to the degree that the hearing examiner implied that each discrete fact alleged in the original affidavit was a separate transaction and occurrence, the hearing examiner‘s view was impermissibly narrow. Second, the hearing examiner was mistaken because the Conservation Groups’ original affidavit expressly revealed their contention, fully presented in their proposed amended affidavit, that the Thompson River fаcility should be subject to PSD regulations. In the original affidavit, the Conservation Groups asserted that the issuance of the modified air quality permit was invalid because DEQ did not require TRP to comply with the best available control technology (BACT) requirements of
¶25 Finally, DEQ argues that
¶26 The instant case is analogous to Simmons.
¶27 Justice Rice, in dissent, also contends that the thirty-day deadline in
¶28 This reasoning, which would disallow any amendments after the initial thirty-day period for filing the initiating affidavit, goes too far. First,
¶29 Second, we do not believe that the requirement of
¶30 Third, as a practical matter, in a contested case hearing, formal discovery will only occur after an adversely affected person files a request for a hearing and the affidavit setting forth the grounds for the requested hearing. This is particularly the case with regard to discovery of information from non-state actors, such as TRP here. In fact, in this case, DEQ filed its first discovery request two months after the Conservation Groups filed their affidavit. It would make little sense and would not foster resolution of contested cases on the merits to foreclose the possibility of amendments before significant discovery
¶31 While we agree with Justice Rice that parties should not be allowed to abuse procedural rules in order to obstruct the administrative process, we feel that the standard grounds for denying motions to amend (undue delay, bad faith, undue prejudice, repeated failure to cure deficiencies by previously allowed amendments, futility, etc.) are adequate to prevent abuse. E.g. Bitterroot Intl. Sys. Ltd. v. W. Star Trucks, Inc., 2007 MT 48, ¶ 50, 336 Mont. 145, 153 P.3d 627 (cataloguing reasons for denying leave to amend).
¶32 All parties devotе argument to whether the Conservation Groups’ proposed amendments would unduly delay completion of the hearing, causing prejudice to DEQ and TRP. The hearing examiner expressly declined to address this issue in the order denying the Conservation Groups’ motion to amend. Nor did BER or the District Court address the issue of potential prejudice from any delay occasioned by the proposed amendment. In the absence of any ruling on this issue below, we decline to address this matter here. The parties may address the issue of delay on remand.
¶33 We reverse the decision of the District Court. We remand this matter to the District Court, and ultimately to BER, for further proceedings consistent with this opinion.
JUSTICES MORRIS and NELSON and DISTRICT JUDGE BROWN, sitting for CHIEF JUSTICE McGRATH, concur.
JUSTICE COTTER dissents.
¶34 I dissent from the Court‘s decision to reverse the order denying the Conservation Groups’ motion for leave to amend their affidavit. In this connection, I dissent from the Court‘s sua sponte decision to modify the standard of review applicable to orders entered pursuant to
¶35 The Conservation Groups presented their appeal in these words: “The sole issue on this appeal is whether the BER abused its discretion by denying leave to amend on the grounds that the Conservation Groups’ proposed ‘major source’ claim did not arise out of the same ‘conduct, transaction, or occurrence’ as the original Affidavit.” The Conservation Groups stated that a decision to deny leave to amend pursuant to
¶36 In its response brief, DEQ cited our recent decision in Farmers Coop. Assn. v. Amsden, LLC, 2007 MT 286, ¶ 12, 339 Mont. 445, 171 P.3d 690, for the proposition that, under
¶37 At ¶ 13, footnote 2 of the Opinion, the Court engages in a somewhat lengthy analysis of what should be the standard of review under
¶38
¶39 I now turn to the precedent which the Court‘s decision seemingly overrules. In Lindey‘s v. Professional Consultants, Inc., 244 Mont. 238, 242, 797 P.2d 920, 923 (1990), cited by TRP, the plaintiff sought leave to amend its complaint after the scheduling order deadline had expired. The district court denied the motion, and on appeal, we affirmed. Citing multiple cases, we said that the decision to grant or deny a motion to amend lies within the discretion of the trial court. Lindey‘s, 244 Mont. at 242, 797 P.2d at 923. We further said that while the rule favors amendments, a trial court would be justified in denying a motion for such reasons as undue delay, bad faith, or a dilatory motive on the part of the movant, to name a few. We further said that a party seeking to overturn a district court‘s decision dеnying leave to amend must demonstrate an abuse of discretion. Lindey‘s, 244 Mont. at 242, 797 P.2d at 923.
¶40 Later in the same year, we decided the case of Simmons v. Mountain Bell, 246 Mont. 205, 806 P.2d 6 (1990). In that case, the plaintiff filed an amended complaint with the Montana Human Rights Commission (HRC) after the expiration of the statute of limitations, asserting an additional claim. The HRC denied leave to amend. On appeal, the district court held that
¶41 Most recently, we addressed a plaintiff‘s appeal from a district court‘s decision denying leave to amend its complaint to add an additional claim. In Farmers, we again announced the general rule that the decision to grant or deny a motion to amend lies within the discretion of the district court, and that we review such decisions to determine whether the court abused its discretion. Farmers, ¶ 12. In addition, we again cited the multiple justifications a court might have for denying such a motion. We then addressed the specific claims presented by the plaintiff in its original complaint, the prejudice to the opposing party who operated for a year under the presumption that the original allegations were discrete, and the failure of the plaintiff to provide a sufficient reason for the late amendment. We concluded that several concerns expressed by the district court supported its decision to deny leave to amend the complaint. Farmers, ¶ 22.
¶43 Thus, contrary to the Court‘s assertion that futility was the basis for the hearing examiner‘s “implicit reasoning,” I would find, as did the District Court, that the hearing examiner properly took account of several factors in rejecting leave to amend. Our well-reasoned precedent is clear: A court or hearing examiner is privileged to take account of multiple aspects of the case in deciding whether to exercise discretion in favor of or against an amendment. We err here, in my judgment, in jumping past this inquiry to an analysis of whether the facts provable under the amended complaint arose out of the conduct alleged in the original complaint, and in announcing a new standard of review applicable to this analysis. We should first lоok to whether the denial of the motion for leave to amend was an abuse of the hearing examiner‘s or the court‘s discretion, given the many factors taken into account by them in the first instance. It is this analysis which the hearing examiner conducted and which the District Court upheld. It is this analysis which invokes the hearing examiner‘s discretion, exercised based upon her knowledge of the status of the case and the possible problems attendant to a proposed amendment.
¶44 In sum, I dissent from our revision of the standard of review of
¶45 I therefore dissent.
JUSTICE RICE, dissenting.
¶47 The governing statute provides that “[a]n affidavit setting forth the grounds for the request must be filed within 30 days ....”
¶48
¶49 The Court rejects this position, insisting that it “conflicts with our reasoning in Simmons v. Mountain Bell, 246 Mont. 205, 207-09, 806 P.2d 6, 7-8 (1990)” and that this case is “analogous.” Opinion, ¶¶ 25-26. I disagree. The Court‘s reliance on Simmons is misplaced because
¶50 Adhering to the statute at issue here and prohibiting amendments raising new claims after the 30-day deadline would not, as the Court states, forbid all amendments. See Opinion, ¶ 28. Of course, prior to expiration of the 30-day deadline, any kind of amendment to the affidavit is permitted, even one setting forth entirely new grounds. See
¶51 The Court also cites to
¶52 The Court has reached its decision by looking to other rules, treatises discussing administrative law generally, and cases interpreting different statutes-everything but the wording of the actual statute at issue. The Court thus fails to enforce the specific requirements within the statute and the Legislаture‘s desire to conduct a prompt proceeding. By such maneuvering, the Court has failed to heed the admonishment provided by the United States
Indeed, administrative proceedings should not be a game or a forum to engage in unjustified obstructionism by making cryptic and obscure reference to matters that “ought to be” considered and then, after failing to do more to bring the matter to the agency‘s attention, seeking to have that agency determination vacated on the ground that the agency failed to consider matters “forcibly presented.”
Vermont Yankee Nuclear Power Corp. v. Nat. Resources Def. Council, Inc., 435 U.S. 519, 553-54, 98 S. Ct. 1197, 1217 (1978). Allowing an untimely amendment which raises a new issue not only violates the letter and spirit of the governing statute, but also incubates the kind of “unjustified obstructionism” about which the High Court warned.
¶53 I would affirm the District Court.
