MEMORANDUM OPINION
Presently before the Court is defendants’ motion to dismiss plaintiffs’ (collectively “CARE”) complaint for lack of subject matter jurisdiction on the grounds that plaintiffs lack standing and their suit is moot. Because the defendant Agency has already disbursed all grant funds, and therefore no remedy is available to plaintiffs, defendants’ motion is granted.
BACKGROUND
In this suit, plaintiffs seek injunctive and declaratory relief against defendants, who are the EPA Administrator, its regional Administrator (collectively “the Agency”), and the Chairman of the Jefferson Township Sewer Authority (“the Sewer Authority”) in Lackawanna County, Pennsylvania. Plaintiffs identify purported flaws under the National Environmental Policy Act (“NEPA”) in the Agency’s Environmental Assessment and its Finding of No Significant Impact (“FONSI”) concerning the sewer project recently built in Jefferson Township near the Moosic Mountain Barrens (“the project”). The chief problem they isolate is the Agency’s purported “failure to consider the secondary and cumulative impacts that will be spurred by construction of a sewer pipeline, particularly in the undeveloped Moosic Mountain barrens.” (Pis.’ Opp’n at 7.) They contend
This sewer project has generated substantial litigation in this Court, as well as others. In 1995 the Honorable Gladys Kessler enjoined federal defendants from moving ahead with development plans related to it until they complied with NEPA.
See CARE I,
Following the Circuit’s decision, the Agency completed its EA of the sewer project and signed the final FONSI on August 6, 2004, a copy of which the Agency sent to plaintiffs, as well as others who had commented on the project. On August 25, the Agency executed a grant award offer to the Sewer Authority, which the latter accepted on September 7. The Agency, based on an intervening inspection showing that the project was between ninety-five and ninety-eight percent complete, disbursed ninety percent of the $1.7 million grant on September 27. Following notification that the project was entirely complete (absent a few minor punchlist items), the Agency authorized disbursal of the remaining ten percent on November 9. (See Defs.’ Mot. at 7 and sources cited therein.) At this juncture, the federal grant has been paid in full and the locally-administered sewer project is complete and operational. (See Defs.’ Mot. Ex. 9.)
ANALYSIS
Defendants submit that this Court lacks subject matter jurisdiction over this suit for two reasons. First, they contend that the suit is moot because the project has been completed and the grant funds have been disbursed. Second, they argue that plaintiffs lack standing both because there is no causation between the federal grant and plaintiffs’ purported injuries and because plaintiffs’ injuries are not remediable through this suit.
Plaintiffs, however, object that the Court may not rule on defendants’ Fed.R.Civ.P. 12(b)(1) motion because it relies on disputed issues of fact. (Pis.’ Opp’n at 3-5.) A complaint should not be dismissed “unless it appears beyond doubt that the plaintiff can prove no set of facts in support of his claim which would entitle him to relief.”
Conley v. Gibson,
Plaintiffs’ argument fails, for the issue they raise is a question of law. Production of the administrative record and discovery would not shed light on the question of whether the Agency, as a matter of law, may retroactively add conditions to or even rescind its grant to the Sewer Authority. Such authority either exists by virtue of statute, the existing terms of the grant, or some other legal source, or it is nonexistent. Neither production of a record detailing the agency’s analysis of the project’s environmental effects on the Moosic Mountains and other Scranton environs or any other type of discovery would clarify this legal question.
As defendants rightly note, this Court has an “an affirmative obligation to ensure that it is acting within the scope of its jurisdictional authority.”
Grand Lodge of Fraternal Order of Police v. Ashcroft,
I. Mootness
For this Court to rule on plaintiffs’ complaint, the suit must present a live case or controversy. “Even where litigation poses a live controversy when filed, the [mootness] doctrine requires a federal court to refrain from deciding it if ‘events have so transpired that the decision will neither presently affect the parties’ rights nor have a more-than-speculative chance of affecting them in the future.”
Clarke v. United States,
Plaintiffs’ point is well taken that “any effective relief’ encompasses acts that may not necessarily undo a fait ac-compli, but that may serve to mitigate it.
See Neighbors of Cuddy Mountain v. Alexander,
Rather, this controversy is governed by principles of contract law, and the Sewer Authority was offered and accepted the grant on the basis of certain conditions, which this Court may not retroactively revisit. As a general matter,
legislation enacted pursuant to the spending power is much in the nature of a contract: in return for federal funds, the States agree to comply with federally imposed conditions. The legitimacy of Congress’ power to legislate under the spending power thus rests on whether the State voluntarily and knowingly accepts the terms of the “contract.” There can, of course, be ho knowing acceptance if a State is unaware of the conditions or is unable to ascertain what is expected of it. Accordingly, if Congress intends to impose a condition on the grant of federal moneys, it must do so unambiguously. By insisting that Congress speak with a clear voice, we enable the States to exercise their choice knowingly, cognizant of the consequences of their participation.
Pennhurst State Sch. & Hosp. v. Halderman,
The same principles govern the Agency’s contract with the Sewer Authority. Unless the Sewer Authority explicitly agreed to be bound by NEPA or to comply with conditions the Agency recommended as a result of its Environmental Assessment, the Authority had no such compliance duty.
See CARE III,
Plaintiffs direct the Court’s attention to the Agency’s powers, pursuant to 40 C.F.R. § 35.965, to terminate or annul grants, debar the grantee from future federal assistance, and the like.
(See
Pis.’ Opp’n at 9.) But those powers are explicitly limited to circumstances where the
“grantee
has failed to comply with any
Plaintiffs also point to 40 C.F.R. § 6.512, which provides for Agency monitoring of “mitigation measures and other grant conditions identified in the [FONSI],” and for enforcement actions where “the
grantee
fails to comply with grant conditions” (emphasis added). Because the FONSI at issue contains no grant conditions and sets forth no mitigation measures
(see
Defs.’ Mot. Ex. 2), this regulation likewise provides no basis for amending the grant to provide the relief sought here. Again, there is no allegation that the Sewer Authority as grantee has failed to meet the conditions of the grant as envisioned by 40 C.F.R.. § 6.512; rather, plaintiffs’ “primary thrust” is against the Agency instead. Where the alleged wrongdoing is the Agency’s failure to meet its obligations under NEPA, the principles of
Pennhurst
do not permit the other, innocent contracting party to have the grant retroactively rewritten to its detriment on account of the government’s purported mistakes in entering into the contract without meeting
the Agency’s
obligations.
See Pennhurst,
The result here might have been different if the grant offer had been withdrawn and reissued subject to plaintiffs’ proposed conditions prior to its acceptance. But plaintiffs failed to seek a restraining order ór a preliminary injunction to arrest the grant-making process before the Sewer Authority accepted the government’s grant offer. As stated, the Authority has long since accepted the Offer, and the grant has been paid in full. Indeed, if plaintiffs are correct that the Agency did not comply with NEPA, they could have moved in early November for emergency relief to argue that the Agency must be precluded from finalizing payment of the second grant installment, which was processed on November 9, 2004. (Defs.’ Mot. Ex. 7.) The fact that in
CARE II
the Court was unable to enjoin the
Sewer Authority’s
construction of the project did not make it futile to move in the instant proceeding to enjoin the
Agency
from disbursing a grant allegedly granted in violation of NEPA.
Compare CARE II,
Plaintiffs argue that their suit falls within the mootness exception for actions that are capable of repetition but evade review.
See Weinstein v. Bradford,
In sum, this Court is unable to grant plaintiffs any effective relief, and as a re-suit, their suit is therefore moot because the Court lack jurisdiction.
II. Plaintiffs’ Standing
As an alternative basis for its dismissal of plaintiffs’ suit, the Court holds that plaintiffs lack standing, and therefore, the Court has no subject matter jurisdiction to hear this case.
To establish that this Court has jurisdiction to hear plaintiffs’ claims, plaintiffs must show that they have standing to raise them.
See Florida Audubon Soc’y v. Bentsen,
The same reasoning underlying the Court’s mootness decision compels the suit’s dismissal for lack of standing. For the reasons stated, plaintiffs’ alleged injuries will not be redressed through the relief sought, because such relief cannot be granted pursuant to the now-final terms and conditions of the grant and because the Sewer Authority has not done anything wrong that would warrant enforcement actions against it. Plaintiffs therefore fail the redressability prong of the standing analysis.
CONCLUSION
While only one of the above-discussed issues would be sufficient to deprive this Court of subject matter jurisdiction, in fact there are three independent reasons why the Court may not hear this case. The suit is moot, plaintiffs cannot demonstrate causation between their injuries and the challenged action sufficient to establish standing, and plaintiffs cannot show that their injuries are redressable so as to afford them standing. It therefore cannot proceed, and defendants’ motion is granted and this case is dismissed with prejudice. An appropriate Order accompanies this Memorandum Opinion.
ORDER
For the reasons stated in the accompanying Memorandum Opinion, it is hereby
ORDERED that Federal Defendants’ motion to dismiss [# 7] is GRANTED; and it is
FURTHER ORDERED that this case is dismissed with prejudice.
This is a final appealable order.
Notes
. Citing the Ninth Circuit,
see Cantrell,
