These appeals emanate from the same action which spawned an appeal in
Citadel Corp. v. Sun Chemical Corp.,
After an extended trial, a jury returned special verdicts finding that Citadel is entitled to certain damages on its claims against Sun Chemical; that Sun Chemical is entitled to zero damages as to its counterclaim against Citadel for damage to the “XLR plates” and that Citadel is entitled to zero damages as to its third-party claim against All-South for indemnification. After entry of judgment on the verdicts, Citadel filed a direct appeal in Case No. A95A0783 and All-South filed a cross-appeal in Case No. A95A0784. Held-.
1. Citadel contends the jury’s failure to award attorney fees under its third-party claim against All-South for reimbursement of costs incurred in defending against Sun Chemical’s counterclaim is contrary to law and not supported by the evidence. Citadel argues that it is entitled to a judgment (upon remand to the trial court) for the total amount of its attorneys’ billings as reflected on itemized statements introduced into evidence at trial. In response and in its cross-appeal, All-South asserts that Citadel failed to meet its burden of demonstrating a specific entitlement to attorney fees under the indemnity agreement. 1
“ ‘ “An award of attorney fees is unauthorized if [Citadel] failed to prove the actual costs of [their attorneys] and the reasonableness of those costs. (Cit.)”
Fiat Auto U.S.A. v. Hollums,
The indemnity clause in the roofing subcontract pertinently provides that “[All-South] shall indemnify, hold harmless and defend [Citadel] against all claims, damages, losses and expenses, including attorney fees, arising out of [All-South’s] Work under [the] Subcontract. . . .” This provision, however, does not provide for recovery of attorney fees and expenses incurred to enforce the indemnity agreement. Consequently, Citadel is not entitled to recover such costs. In order for Citadel to recover under the indemnity agreement, it must show the fees it claims are reasonable and prove them “with sufficient particularity to permit the [jury] to distinguish between time and expenses attributable to [recoverable fees for the XLR-plate counterclaim] and time and expenses attributable to [nonrecoverable fees incurred in enforcing the indemnity agreement].”
Mitcham v. Blalock,
In the cases sub judice, attorney Ira Smotherman testified that he reviewed the billing statements introduced into evidence by Citadel; that he “looked at just not page-by-page but in bulk the amount of depositions that had been taken concerning this part of the case[; that he reviewed exhibits from] several boxes full of documents that pertain to the issues in this part of the case” and that, based on his observations, the amount of attorney fees claimed by Citadel was “reasonable” for “fees generated in a construction litigation case by lawyers and a law firm that had some experience, background and expertise in handling this kind of case.” However, the billing statements relied on by Smotherman include not only attorney fees purportedly incurred by Citadel in defending the XLR-plate counterclaim, they also include billings for pursuing the third-party claim against All-South. And when cross-examined about these billings, Smotherman admitted that he “didn’t make any attempt to distinguish [between the attorney fees sought by Citadel for defense of the XLR-plate counterclaim and the fees incurred in pursuit of its third-
*739
party complaint against All-South].” It thus appears that “[n]o evidence was presented from which the jury could determine what portion of the total amount of [the] attorney time and litigation expenses incurred in this . . . litigation was attributable to the [recoverable fees incurred in defense of the XLR-plate counterclaim and the nonrecoverable fees incurred in connection with Citadel’s third-party claim against All-South].”
Arford v. Blalock,
2. In light of our holding in Division 1 of this opinion, it is unnecessary to address remaining issues in the appeal and the cross-appeal.
Judgment affirmed in Case Nos. A95A0783 and A95A0784.
Notes
All-South also contends the indemnity agreement is unenforceable because it is violative of public policy as enunciated in OCGA § 13-8-2 (b). We do not reach this issue and assume, without deciding, that the parties’ indemnity agreement is not violative of OCGA § 13-8-2 (b).