220 Conn. 362 | Conn. | 1991
This appeal is the sequel to our decision in Cioffoletti v. Planning & Zoning Commission, 209 Conn. 544, 552 A.2d 796 (1989) (Cioffoletti I). In our
In Cioffoletti I, the trial court, Moraghan, J., had upheld the decision of the commission, but had refused to admit evidence offered to the court by the plaintiffs of the economic impact of the partial denial of their permit application, thus limiting the evidentiary basis for determining their claim of a taking of property without due process of law to the record of the hearing before the defendant commission. We concluded that General Statutes 22a-43a (a)
At the remand hearing, the plaintiffs were permitted to present their economic impact evidence as well as other testimony. Their expert witnesses testified that, if an excavation permit had been granted, as requested, for the entire ten acre tract, which consisted mostly of wetlands that included a 2.6 acre pond, the plaintiffs’ property would have a value of $1,685,000, but that its value with the permit granted by the commission, limiting the excavation area to 4.6 acres, was only $760,000, a diminution in potential value of $925,000. Evidence was also presented that the plaintiffs had acquired the ten acre wetlands area as part of a twenty-four acre property purchased on October 15, 1982, for $260,000.
At the remand hearing it appeared that the plaintiffs had applied for a permit to remove no more than 200,000 cubic yards of sand and gravel from the ten acre wetlands tract over a period of ten years.
The trial court made two findings that it considered decisive: (1) the value of the plaintiffs’ property had increased from $260,000, its purchase price on October 15, 1982, to $760,000 on April 10, 1985, the date of their expert’s appraisal, as a result of the commission’s approval of mining operations on the 4.6 acre parcel; and (2) the plaintiffs, under the permit granted, could remove approximately the same amount of material that they had declared to the commission they intended to remove if their application were granted in full. Relying upon these findings, the court concluded that “no taking ha[d] occurred without just compensation.”
I
The plaintiffs claim that there is no competent evidence to support the trial court’s finding that the value of their property had increased as a result of the commission’s grant of a permit to excavate 4.6 acres of the
The plaintiffs have not attacked the evidentiary basis for the finding of the trial court that the permit granted by the commission allows the removal of approximately 200,000 cubic yards of material, approximately the same quantity that they stated at the hearing before the commission that they intended to excavate from the entire ten acre tract, if their application had been granted as proposed.
II
The plaintiffs claim that the trial court departed from our remand order in Cioffoletti I by failing to set forth the facts they claim to have proved relating to the financial loss they have sustained from the denial of permis
Our rescript in Cioffoletti I, supra, 563, set aside the judgment and remanded the case “for further proceedings in respect to the takings issue.” We explained in the opinion that the trial court ruling excluding the evidence offered by the plaintiffs of the financial loss resulting from the denial of an excavation permit for 5.4 acres of their property “necessitated a remand for further proceedings related to that claim so that the trial court [could] make findings related” to that issue. Id., 562. We indicated that, in determining whether a taking had occurred, consideration should be given not only to “the degree of diminution in the value of the land but also to the nature and degree of public harm to be prevented and to the alternatives available to the landowner.” Id., 562-63; Brecciaroli v. Commissioner of Environmental Protection, 168 Conn. 349, 356, 362 A.2d 948 (1975). We also declared that “[a]t the further proceedings in the trial court that we have ordered, evidence may be admitted that is material to the taking issue both as it relates to the plaintiffs’ financial detriment and as it relates to the advancement of the public interest.” Cioffoletti I, supra, 563.
The plaintiffs make no claim that any evidence offered by them on the taking issue was excluded. Their claim that the findings made by the court are inadequate apparently relates to the absence of any statement in the memorandum of decision quantifying the plaintiffs’ economic loss resulting from the refusal to grant their application fully. The court did refer to
Although this court in Cioffoletti I did refer to that standard, our mandate “for further proceedings in respect to the takings issue” was not so limited as to preclude other methods of resolving that issue. We have rejected efforts to construe our remand orders so narrowly as to prohibit a trial court from considering matters relevant to the issues upon which further proceedings are ordered that may not have been envisioned at the time of the remand. Blaker v. Planning & Zoning Commission, 219 Conn. 139, 592 A.2d 155 (1991). So long as these matters are not extraneous to the issues and purposes of the remand, they may be brought into the remand hearing. We conclude that the court did not exceed the scope of our remand by resolving the taking issue on grounds not mentioned in Cioffoletti I.
Ill
Finally, the plaintiffs contend that the application of the Inland Wetlands and Watercourses Act, General Statutes §§ 22a-36 through 22a-45, to their land constituted a taking because sand and gravel mining operations had been conducted there prior to zoning and were a nonconforming use. We agree with the trial court that no such taking claim can be based upon the action of the commission in granting permission to
“It follows from the nature of a regulatory takings claim that an essential prerequisite to its assertion is a final and authoritative determination of the type and intensity of development legally permitted on the subject property.” MacDonald, Sommer & Frates v. Yolo County, 477 U.S. 340, 348, 106 S. Ct. 2561, 91 L. Ed. 2d 285 (1986). Because the plaintiffs have received under the permit as granted by the commission all of the economic benefit that they had indicated they were seeking, it is unclear whether the commission has made a final determination as to the extent of the mining operations that may ultimately be allowed on the plaintiffs’ property. Whether or not the commission was aware of the consequences of its decision, its effect was to authorize the plaintiffs to remove as much material as they had requested.
Counsel for the commission does not maintain that the plaintiffs are forever barred by the commission’s action from applying for permission to excavate additional material from the remaining 5.4 acres at some later time. As he suggests, it is conceivable that such
Furthermore, the opponents of the application, as well as the commission members, were entitled to rely on the representations of the plaintiffs about the quantity of material to be excavated from the wetlands area. The testimony at the public hearing, even that offered by the plaintiffs, might have been quite different if it had been known that the plaintiffs sought to remove a substantially greater amount of material than indicated by their application. Because the plaintiffs will have an opportunity to apply at the appropriate time for permission to excavate on their remaining land, they have failed to satisfy the requirement that the decision of the regulatory agency be final, so that a reviewing court may properly consider whether an unconstitutional taking of property without just compensation has occurred.
The judgment is affirmed.
In this opinion the other justices concurred.
The plaintiffs do not cite but presumably rely upon article five of our federal constitution, which provides in part: “No person shall ... be deprived of . . . property, without due process of law; nor shall private property be taken for public use, without just compensation.”
The planning and zoning commission of the town of Ridgefield also serves as its inland wetlands board.
General Statutes § 22a-43a (a) provides: “If upon appeal pursuant to section 22a-43, the court finds that the action appealed from constitutes
The plaintiffs’ written application stated that they sought a permit for “[r]emoval of approximately 80,000 cubic yards of sand and gravel for use by the applicant.” After a question was raised at the December 18, 1984 public hearing about this quantity as inconsistent with the depth and area of the proposed excavation, counsel for the plaintiffs reported that revised calculations indicated that the total volume of material to be removed from the ten acre site would be between 180,000 and 200,000 cubic yards.
The plaintiffs’ permit application indicated that approximately ten years would be required to complete the proposed excavation of the ten. acre tract.