OPINION AND ORDER
This matter is presently before the court on plaintiffs application for a temporary restraining order and motion for a preliminary injunction brought pursuant to 28 U.S.C. § 1491(b) (1994), as amended by Administrative Dispute Resolution Act of 1996, Pub.L. No. 104-320, 110 Stat. 3870, 3874-74 (1996). Plaintiff, a disappointed bidder, seeks to enjoin defendant from proceeding with the perfоrmance of a contract awarded to interve-nor, Western Data Systems (WDS), under Solicitation No. M67004-96-R-0006. In its motion to dismiss and opposition to plaintiffs application for a temporary restraining order and motion for a preliminary injunction, defendant argues that such relief should not issue.
Factual Background
On April 9, 1996, defendant issued a solicitation for commercial off-the-shelf Manufacturing Resource Planning software (MRP II) for use in reparables management at Department of Defense maintenance depots. In response to defendant’s solicitation, plaintiff submitted a proposal contemрlating a single server configuration in order to implement its solution. Subsequently, defendant requested additional information from plaintiff. In answering that request, рlaintiff indicated that two additional software packages, Oracle Distributed Database Option and Oracle Parallel Query Option (Oraclе software), would be required if defendant chose to utilize multiple servers. Prior to contract award, defendant determined that plaintiffs solution requirеd the additional Oracle software. Accordingly, defendant adjusted plaintiffs proposal by adding the cost of the Oracle software. Defendant determined that WDS offered the best value to defendant, and, on September 27, 1996, awarded the contract to WDS.
Plaintiff filed a bid protest with the General Accounting Office (GAO) on October 11, 1996, claiming defendant erroneously deter
Discussion
In determining whether to grant an appliсation for a temporary restraining order, the court applies a four-part standard. See Magnavox Elec. Sys., Co. v. United States, 26 Cl.Ct. 1373, 1378 (1992) (citing Zenith Radio Corp. v. United States,
A. Irreparable Harm
Plaintiff claims it will be irreparably harmed if a temporary restraining order does not issue, asserting that, absent an injunction, it will be forever deprived of the opportunity to participate in this procurement. Performance on the subject contract, however, is still in its early stages. WDS indicates it is currently on site at only one оf the eighteen sites contemplated in the contract. Further, defendant noted at oral argument that, should plaintiff ultimately prevail on the merits of its claim, “[plaintiff] could be substituted for WDS.”
B. Likelihood of Success on the Merits
Although plaintiff has demonstrated that its success on the merits of its claim “may be possible,” plaintiff, at this time, has not shown that such success is “likely.” See id. In reaching this conclusion, the court is mindful of the heavy burden рlaced on plaintiff, as well as the existence of a GAO decision unfavorable to plaintiff, to which the court should give due deference. See Honeywell, Inc. v. United States,
C. Balance of Harms
Plаintiff contends any harm that injunctive relief may cause defendant is less
D. Public Interest
It is axiomatic that the public has an interest in honest, open, and fair competition in the procurement process. Whenever a plaintiff is improperly excluded from that process, that interest is compromised. Magellan Corp.,
Conclusion
For the above-stated reasons, the court determines that plaintiff has not dеmonstrated, by clear and convincing evidence, that it has met its burden under the four-part standard applied by the court. See Baird,
IT IS SO ORDERED.
Notes
. Defendant argues, in the alternative, that plaintiff's complaint should be dismissed because plaintiff is not a proper party in interest in this case. The arguments raised regarding plaintiff's standing will be considered in the parties’ cross-motions for summary judgment, which are to be filed by February 19, 1997.
. Transcript at 85.
. This case is distinguishable from Honeywell, Inc. v. United States,
. Initial screening criteria required offerors to be capable of operating on the Sun Sparc 2000 platform server. At the time plaintiff submitted its proposal, plaintiff was not capable of operating on this system. Plaintiff, however, infоrmed defendant that it would have this capability by September 30, 1996, the award date provided in the solicitation. The parties dispute whether plaintiff аchieved this capability by that date.
. Affidavit of Steven C. Hannaford, Defendant’s Motion to Dismiss and Opposition to Plaintiff’s Application for a Tempоrary Restraining Order and Motion for Preliminary Injunction, App. at 2. By agreement of the parties, the submissions to the court are under a Protective Order. These materials are kept under seal by the Clerk of the Court.
