162 Ind. 303 | Ind. | 1904
Appellant, engaged in the construction of a railroad from Cincinnati to Chicago, the line of which intersects appellee’s railroad at a point two miles west of Peru, Indiana, having failed to agree with appellee with respect to said crossing, on October 29, 1901, filed in the office of the clerk of the Miami Circuit Court an instrument of appropriation of so much of appellee’s railroad as would enable appellant to construct its railroad there-over. Proceedings were thereafter had under the statute, whereby, on Hovember 28, 1901, an award was made fixing the point and manner of crossing, and the amount of the consideration to be paid by appellant at $4,000. The amount awarded was paid by appellant to the clerk of the Miami Circuit Court, for the use of appellee, on December 4, 1901, pursuant to the award. Exceptions to the award were timely filed by appellee, and afterwards, and while its exceptions remained undisposed of, appellee appealed the cause to the Appellate Court, which appeal was dismissed on the ground that the same was prematurely taken.. Wabash R. Co. v. Cincinnati, etc., Railroad, 29 Ind. App.. 546. Before the appeal, the venue of the cause was changed from the Miami to the Fulton Circuit Court, and was pending in the latter court when the appeal to the Appellate Court was dismissed. Said appeal was dismissed March 13, 1902, and on. March 21, 1902, appellee filed in said cause its cross-complaint to enjoin appellant from taking possession of the condemned premises,' and from constructing thereon a crossing, interlocking tower, etc., until the appropriation proceeding should be fully heard and determined by the. Fulton Circuit Court; and on the following day, and without notice, and on said cross-complaint, procured the issuance, by the judge of the Fulton Circuit Court, of a temporary restraining order against appellant, and, appellant having appeared to said cross-complaint, the judge of said court, on March 28, in vacation, granted appellee a temporary injunction, restraining
'An earnest effort has been made by counsel for appellee to bring into this action for injunction and into this appeal questions which belong exclusively to the appropriation proceeding, and which remain undisposed of and pending in the Eulton Circuit Court.
An assignment of cross-error has been made calling in question the action of the Miami Circuit Court in overruling appellee’s demurrer to appellant’s instrument of appropriation, in its orders and decrees' establishing and relating ■to said crossing, and in'overruling and sustaining divers (subsidiary motions involving the sufficiency of the pleadings in the appropriation proceeding, and the regularity :and legality of the order and decree made thereon. Appellee’s exceptions to the award filed in the Miami Circuit Court, and which are still pending in the Eulton Circuit Court, embody the same facts that formed the basis of appellee’s objections to the instrument of appropriation and order of decree of the court, and which are brought forward and presented in the cross-complaint as grounds for an injunction.
It was held by the Appellate Court in the former appeal (Wabash R. Co. v. Cincinnati, etc., Railroad, supra), which ruling was subsequently, on October 8, 1902, upon appellee’s application to transfer, reviewed and affirmed by this court, that all questions of law and fact, which arose upon the instrument of .appropriation, the interlocutory order and decree of the court, and award of the commissioners thereon, were by appellee’s exceptions filed thereto, and the appeal carried forward to the circuit court for final determination. This ruling settles the law on that point so far as this case is concerned, and rules in all
The questions thus referred to the Eulton Circuit Court have not been considered and finally determined, and there they must remain until the body of the ease is fully disposed of. Appellee can not be allowed to execute a flank movement, and in a collateral way secure the adjudication of questions by this court until they have been first decided at nisi. It may be that when such questions are decided below it will have no ground of complaint. There is not a question argued or arises, either upon the direct or the assignment of cross-eiTor,. that does not arise and properly belong to. the main case, and within the rule above announced, save only as to the right of appellant, upon its payment of the award, to take possession of the condemned premises and proceed with the construction of its crossing. The complaint shows that appellant was proceeding to do this, and, if it did not have the right, injunction will lie. If it did, it will not lie. And to this question we must confine ourselves.
We have many sections of the statute relating to the rights and obligations of railroad corporations in the construction of their railroads, in crossing other railroads, and in appropriating the property of others for their tracks; but so far as concerns the question before us it is only important to call attention to §5160 Burns 1901. It is therein provided that the corporation having failed to agree with the owner “shall forthwith deposit with the clerk of the circuit court, or other court of record of the county where the land lies, a description of the rights and interests intended to be appropriated; and such land, rights and interests shall belong to such company, tó use for the purpose specified, by making or tendering payment as hereinafter provided. * * * Upon filing such act of, appropriation * * * the circuit court * * * in
The company’s authority to take the property of another for the construction of its railroad proceeded from an exercise of the State’s right of eminent domain. In conferring this right the legislature might and did prescribe the exact terms of its enjoyment, within the limits of the Constitution. It is manifest from the statute that the legislature intended that the right to appropriate should be summary and indefeasible by prepayment or tender of just compensation, and the exercise of the right in the mode prescribed. If the appropriating company is within
Doubtless the reason for making the right to such an appropriation unquestionable is that it contravenes public policy to permit an individual or corporation to impede, by litigation and incidental delays, the progress of a great enterprise which involves important public interests, as well as the outlay of large sums of money. At any rate, it is settled by the decisions of this court that the proviso of §5160, supra, with respect to the right of the appropriating company to take immediate possession, means what it says. We quote from- what is said in Lake Erie, etc., R. Co. v. Kinsey, 87 Ind. 514, the following: “The payment of the amount awarded by the appraisers gives the corporation a right to the immediate possession and a prima facie claim to the land subject to an appeal in ten days after the award is filed. If no appeal is taken, at the end of the ten days the title vests and relates back to date of payment. If an appeal is taken no title vests, and the corporation has no greater right than that of a license under the statute to hold possession and proceed with the construction of its road pending litigation. When the compensation has been finally fixed on appeal, then the cor
Appellee chiefly, bases its claim for injunctive relief upon the following facts shown by the record: The place of the crossing in controversy is on a curve in appellee’s railroad, by reason whereof the outer' rail of its track at that point is two and one-lialf inches higher than the inner • rail. Appellant’s instrument of appropriation claimed and demanded the right to intersect and cross appellee’s railroad at grade, and the Miami Circuit Court, in determining the mode of crossing, prior to the assessment of damages as required by §5158a Burns 1901, to make a practicable crossing, at grade, on the level, among other things ordered . that appellee’s railroad be made straight for a distance of 100 feet on each side of the center line of the crossing, and that appellee so straighten it within twenty days, and in default appellant should thereafter have the right to enter and straighten it at appellee’s cost. The insistence of appellee is that so much of the court’s order as directed a change in the construction of its road, and the mandate that appellee accomplish the change within twenty days, or suffer appellant to enter and make it, is void, because it is a right not demanded in the instrument of appropriation, and consequently not appropriated; and notwithstanding the assessment of damages therefor, and payment of the same into the clerk’s office for the use of appellee, it did not warrant the taking of possession, because the proviso of the statute only operates as to property that has been legally appropriated.
The order for a temporary injunction is reversed.