205 P. 541 | Or. | 1922
— Section 10191, Or. L., in effect provides that every person performing labor upon, or furnishing material of any kind, to be used in the construction, alteration, or repair, of any building, shall have a lien upon the same for the work or labor done, or material furnished, at the instance of the owner of the building, or his agent; it also in effect provides that every contractor or other person having charge of the construction in whole or in part, of any building, shall be held to be the agent of the owner for the purposes of the act; it requires every person furnishing material to any person other than the owner, for which a lien may be claimed, to deliver or mail to the owner of the property on, upon, or about which the material is to be used, not later than five days after the date of the first delivery, a notice in writing, stating that he has commenced to deliver material for use thereon, with the name of the contractor or other person ordering the same, and that a lien may be claimed for the material furnished; it also provides that unless this written notice is given, a lien cannot be enforced for such material. It contains no provision requiring notice to the owner of work being done on the building.
It appears from the testimony that the contracts under which Christman, Portland Hardwood "Floor Co., Stevens, and Sanders performed labor and furnished material, were entire contracts, entered into by the claimants with the contractor to furnish both labor and material, for which they were each to be paid a specific sum, and that no separate price was
It has often been held in this state that:
“An account containing a lumping charge, in which is mingled an item for which no lien is given, will not support a lien; and the defect cannot be cured by oral evidence, by means of which the items for which a lien is given may be separated from those for which a lien is not given.” Williams v. Toledo Coal Co., 25 Or. 426 (36 Pac. 159, 42 Am. St. Rep. 799); Dalles Lumber Co. v. Wasco Woolen Mfg. Co., 3 Or. 527; Kezartee v. Marks, 15 Or. 529 (16 Pac. 407); Harrisburg Lumber Co. v. Washburn, 29 Or. 150 (44 Pac. 390); Hughes v. Lansing, 34 Or. 118 (55 Pac. 95, 75 Am. St. Rep. 574); Portland Floor Co. v. Spaulding Logging Co., 64 Or. 316 (130 Pac. 52); Stewart v. Spaulding, 71 Or. 310 (141 Pac. 1127); Barr v. World Keepfresh Co., 77 Or. 95 (150 Pac. 747).
The word “account,” as used in the rule above quoted, refers to the statement of account contained in the claim of lien filed, and not to an account kept between the parties of their transactions. If, in the account stated in the notice of lien, lienahle and nonlienabíe items are separately stated, and the amount of the lienahle items can be ascertained from an inspection of the claim of lien itself, and no other rea
An inspection of each of these claims discloses that there is no lumping charge contained in the statement of account, and that the charges for labor and for material are separately stated therein. The amount charged for labor can be readily ascertained from the accounts themselves, and therefore the liens are not subject to the objection that they contain a lumping charge in which are mingled items for which no lien is given, with items for which a lien is given.
“Where lienable and nonlienable items are included in one contract for a specific sum, or are made the basis of a lumping charge, so that it cannot be perceived from the contract or account what proportion is chargeable to each, the benefit of the mechanic’s lien law is lost. In such cases the court cannot, by extrin
This rule was restated in Getty v. Ames, 30 Or. 573 (48 Pac. 355, 60 Am. St. Rep. 835), and Title Guarantee Co. v. Wrenn, 35 Or. 62 (56 Pac. 271, 76 Am. St. Rep. 454). In the former case the claimant had contracted with the owners of the property against which the liens were sought to be enforced, to furnish a carriage and team, and to work for the term of one year at a monthly salary of $125, and to perform such services as from time to time might be directed. At irregular intervals, when not otherwise employed, he had done some work on a building and fence, but kept no separate account of the time he worked on either, and had made no separate charge therefor. He filed two liens, one on the fence and one on the building. After stating the rule above quoted, the court said:
“He was employed by the month to render such services as his employers might require or demand, which it now seems included lienable and nonlienable work indiscriminately. This, however, does not- entitle bim to a lien for such labor or services as might otherwise come within the provisions of the lien law, for the court cannot undertake from extrinsic evidence to apportion the amount of his monthly salary between the lienable and nonlienable work performed by him.”
This is the only Oregon case we can find where the question of the enforcement of a mechanic’s lien
Building contracts, as a general rule, are entire. A contractor or other person having charge of the construction of a building for the owner is, by force of the statute, and by virtue- of his contract with the owner, the agent of the owner for the purposes of the statute. One of these purposes is to authorize him to employ labor and to purchase material for use upon the property of the owner, and when he does so, the law imposes a lien against the property for the reasonable value thereof: Quackenbush v. Artesian Land Co., 47 Or. 303, 306 (83 Pac. 787); Osburn v. Logus, 28 Or. 302 (37 Pac. 456, 38 Pac. 190, 42 Pac. 997); Smith v. Wilcox, 44 Or. 323, 327 (74 Pac. 708, 75 Pac. 710). In the employment of labor and purchase of material, the owner has impliedly contracted through the agency of the contractor: Smith v. Wilcox, supra.
The statute does not, in terms or by implication, deny the right to a lien to one who performs labor
No rule is more firmly established in this state than, that where labor is performed or materials furnished at the instance of the contractor of the owner, and not to the owner himself, or to a common-law agent of the owner, the law fixes the amount for which a lien may be had, as the reasonable value of the labor or materials, and not the price which the contractor agreed to pay therefor: Fitch v. Howitt, 32 Or. 396 (52 Pac. 192); Beach v. Stamper, 44 Or. 4 (74 Pac.
“The statute makes every contractor and subcontractor having charge of the construction of any building, wharf, bridge, ditch, etc., the agent of the owner for the purpose of binding the property with a lien for the reasonable value of materials furnished to be used in or labor performed upon such improvement at the request of the former: B. & C. Comp., § 5640: Fitch v. Howitt, 32 Or. 396 (52 Pac. 192); Cooper Mfg. Co. v. Delahunt, 36 Or. 402 (51 Pac. 649, 60 Pac. 1); but it does not make him an agent of the owner with power to determine the value of the materials furnished or labor performed. Upon this question the owner is entitled to be heard when it is sought to enforce a lien against his property.”
If the contracts had been made with the owner, or with some common-law agent of the owner, the amount for which liens would be given would be determined by the contract price. In such cases, if the right to a lien for a part of that which was to be furnished for an entire consideration failed, and there was no way to determine from the contracts themselves what proportion of the contract price was to be paid for the remainder, there could be no lien for the whole, or for any part. But as these contracts were not made with the owner, nor with any person who had authority to bind him to pay the contract price, and as his property is not chargeable for the contract price or for any proportional part thereof, but only for the reasonable value of the labor performed, there can be no necessity to apportion the contract price between labor and material, nor do we see any reason why the contract price should be considered at all in determining the amount
In the case of Heim v. Elliott, 66 Wash. 361 (119 Pac. 826), labor and material had both been furnished under an entire contract for an agreed sum to be paid for both. The right to a lien for the material was lost for want of notice to the owner. The statute of that state is nearly identical with ours. The question presented was the same as that presented here. In passing upon this question the court said:
“The respondents contend that these items are lien-able. The appellants assert that they are not lien-able, because the contract of each of the respondents with the general contractor was entire. They had no contract with the appellants. Hence there was no privity of contract between them. Hunnicutt & B. Co. v. Van Hoose, 111 Ga. 518 (36 S. E. 669). Rem. . & Bal. Code, § 1129, entitles these respondents to a lien for their labor, and we do not think that this right is defeated because the contract with the general contractor was indivisible.”
Our attention is directed to Morrison v. Minot, 5 Allen (Mass.), 403; Graves v. Bemis, 8 Allen (Mass.), 573; Mulrey v. Barrow, 11 Allen (Mass.), 152; Evans Marble Co. v. International Trust Co., 101 Md. 218 (60 Atl. 667, 109 Am. St. Rep. 568, 4 Ann. Cas. 831); Adler v. World Pastime Exposition Co., 126 Ill. 373 (18 N. E. 809); Phillips on Mech. Liens (3 ed.), 296.
In the Massachusetts cases cited, it was in effect held that under entire contracts where both labor and
By the application of this rule it was held that as there could be no recovery for the labor alone, there could be no debt due for the labor alone. The statute of Massachusetts, 1860, Chapter 150, under which these decisions were rendered, expressly makes the existence of a debt due a condition precedent to the right to a lien.
In the Maryland case' cited, the question involved was upon an entire contract for labor and material furnished to a building in the City of Baltimore, for an entire consideration, with no stipulated price agreed to be paid for either, and the statute of that state expressly provided that no lien could be had for material furnished for use in the construction of a building in the City of Baltimore. It also contained a somewhat similar provision to that contained in the Massachusetts statute, requiring a debt to be due for labor before a lien could be had. That decision cited and applied the doctrine announced in the Massachusetts cases above cited, although in that case the claimants had not lost their right to liens for want of notice to the owner as in the Massachusetts cases.
While these decisions support the contention of the appellant, we do not consider the rules there applied are applicable to a case arising under our statute, where the contract was not made with the owner, nor with a person having authority to bind the owner upon the contract.
Under our statute, to create the right to a lien, there must be a contract for the doing of that for which the statute gives the lien. But the contract need not be made with the owner or a common-law agent of the owner, but may be made by a person whom the statute makes the agent of the owner for the purposes of the statute, and when made with the statutory agent, the claimant has the requisite authority to do the thing for which the statute gives a right to the lien. In other words, there must be an employment of the labor, or a purchase of the material by someone authorized to do so, before the right to a lien for labor performed or material purchased can arise, but when the work is done, or the materials are furnished under the authority of a statutory agent, the property of the owner then becomes subject to a lien, not for the amount which the statutory agent agreed to pay, but for the reasonable value of the work or material. Upon complete performance of an entire contract made by the claimant with the contractor, the contractor is bound to pay the entire contract price, but the owner is not, and therefore, so far as the owner’s rights are concerned, the question of
Although claimants, in determining the amount for which they should assert a lien for their labor, had the right to disregard the amount for which they had agreed to furnish both labor and material, they did not do so. In their statement of account they set out as a separate charge the amount they had actually paid out to their employees, for the labor actually performed upon the building, and then they set out separately as a charge for material, the difference between the total contract price and the charge separately stated for labor. To this extent they did attempt to apportion the contract price between labor and material. Upon the trial, they abandoned all claim for material and claimed only for the labor performed. As they were not compelled to make the apportionment, and as the amount for which the liens are enforced by the decree appealed from is the rea
The same situation arose and was considered by this court in Bohn v. Wilson, 53 Or. 490 (101 Pac. 202), in which case the court said:
“It is next claimed that two causes of suit have been improperly united — one for materials furnished to Lee, and the other for those furnished to Wilson. This defect, if it is one, appears on the face of the complaint, and was waived by failure to demur on that ground. Section 72, B. & C. Comp.; Owings v. Turner, 48 Or. 462 (87 Pac. 160).”
In this case, as in that, if this was a defect, it appeared on the face of the complaint, and was waived by a failure to demur on that ground.
Our statute, Section 10195, Or. L., requires every lien claimant to file:
*685 “A claim containing a true statement of Ms demand, after deducting all just credits and offsets, with the name of the owner, or reputed owner, if known, and also the name of the person by whom he was employed, or to whom he furnished the materials, and also a description of the property to be charged with said lien, sufficient for identification, which claim shall be verified by the oath of himself or some other person having knowledge of the facts.”
It is also contended that the claims filed do not contain true statements of claimants’ demands, because the claims fail to disclose on their face that the demands arose under entire contracts. In support of these contentions, appellant cites decisions of courts rendered under statutes requiring liens to show the terms, time given and other like conditions of the contract under which the demand arose.
The validity of a lien in this state depends upon a substantial compliance with all of the essential requirements of the statute. The claimant is required to do all that the statute requires him to do, and having done that, if the case falls within the provisions of the statute, he is entitled to a lien. The claims in question do contain a true statement of the amount demanded for labor and of the amount demanded for material, each stated separately, and the amount claimed for the lienable items can be readily ascertained from the claims themselves without the aid of extrinsic evidence. They are, therefore, sufficient.
“The contractor is entitled to his lien, not only for his own labor, but for the labor of those under him, and even though his workmen have taken out liens the effect is only to diminish the contractor’s lien pro tanto.” 27 Cyc., p. 84.
The converse of the rule contended for was applied and followed in Bar v. World Keepfresh Co., 77 Or. 95, 100 (150 Pac. 747).
“So far as the time is limited within which a verified copy of the account must be delivered, the statute is only directory.” Raski v. Wise, 56 Or. 72 (107 Pac. 984), and authorities cited.
“The rule is well settled that the trial court may, in its discretion, relieve a party from default in failing to furnish a bill of items when it satisfactorily appears that good and sufficient reason exists for such failure at the time and one is furnished.” Raven v. Hurd, 20 Or. 229, 234 (25 Pac. 635); Raski v. Wise, supra.
“When a debtor owes a creditor more than one obligation he may, at or before making a payment, direct upon which debt the credit should be applied, but, if he give no instruction in respect to the matter, the creditor may apply the payment on account of any demand he may have against him.” Meier & Frank Co. v. Mitlehner, 75 Or. 331, 340 (146 Pac. 796). See, also, Gile Grocery Co. v. Lachmund, 75 Or. 122, 125 (146 Pac. 519); Trullinger v. Kofoed, 7 Or. 228, 230 (23 Am. Rep. 708); Montour v. Grand Lodge, 38 Or. 47, 61 (62 Pac. 524); Anderson v. Griffith, 51 Or. 116, 120 (93 Pac. 934).
The application by Sanders of the $80 paid to him upon his claim for materials furnished does not deprive him of the right to assert a lien for the labor performed. We have held that if no payment had been made to him at all, he could assert his lien for
This disposes of all tbe questions of merit to which our attention has been directed, except tbe objection urged by appellant against tbe claim of Inman Poulsen Lumber Co. Tbe principal objection against this claim, and tbe only one necessary to be considered, is that tbe claim is not verified as required by law.
“Notaries public shall have full power and authority * * to administer oaths in all cases where oaths are required by law to be made.” Section 3183, Or. L. “Every notary public, before he enters upon the duties of his office, shall provide an official seal, and deposit an impression of the same * * in the office of the secretary of state.” Section 3182, Or. L. “Every notary public shall, on all instruments executed by and before him in his official capacity, write or stamp after his signature the date of expiration of his commission.” Section 3176, Or. L. “Pull faith and credit shall be given to all the protestations, attestations and other instruments of publication of all notaries public, now in office or hereafter to be appointed under the provisions of this chapter.” Section 3184, Or. L.
“What the law requires to be done and appear of record, can only be done and made to appear by the record itself, or an exemplification of the record. It is perfectly immaterial whether there be an acknowledgment or privy examination in fact, or not, if there be no record made of the privy examination; for, by the express provisions of the law, it is not the fact of the privy examination merely, but the recording of the fact, which makes the deed effectual to pass the estate of a feme covert.”
Applying this principle to the question presented here, it is wholly immaterial whether the oath was administered or not, unless the claim of lien itself when recorded shows that an oath was administered; for it is necessary under the express provisions of our
The question involved in Elliott v. Peirsol, supra, was involved in Harty v. Ladd, 3 Or. 353, where a certificate of acknowledgment of a deed by a married woman failed to recite that she was examined separately and apart from her husband, as required by the statute then in force. It was held that parol evidence was not admissible to show that she was in fact so examined.
In the early cases of Blanchard v. Bennett, 1 Or. 328, and Dennison v. Story, 1 Or. 272, it was held that “the jurisdiction and authority of a person administering an oath must appear in his certificate.” While Blanchard v. Bennett was overruled upon another point in Ramsey v. Pettingill, 14 Or. 207 (12 Pac. 439), its ruling upon the question as to what must appear in the certificate of an officer administering an oath is still an authority.
That this must be the rule follows from the fact that “A lien notice is incapable of amendment, and cannot be made good by averment. It must stand or fall by reference to its own terms”: East Side Mill Co. v. Wilcox, 69 Or. 266, 269 (138 Pac. 843). “The lien notice, as recorded, is the foundation of plaintiff’s right to recover”: Kelley v. Anderson, 85 Or. 138, 140 (166 Pac. 555). “It should be borne in mind,” says the court, “that a mechanics’ lien is purely a creature of the statute, and that it can be obtained only by a substantial compliance therewith. It is a remedy given by law which secures the preference provided for, but which does not exist, however
The affidavit without- the signature of the notary public was incomplete and the claim was not properly verified and afforded no evidence that the affidavit was sworn to when it was filed and recorded. This defect cannot be supplied by proof aliunde. The claim of lien must be complete in itself and must upon its face show that it was duly verified when filed and recorded. Because of this defect this lien cannot be enforced.
This cause will therefore be remanded to the court below, with directions to enter a decree disallowing the item of $20 contained in the lien of the plaintiff Christman, and disallowing the claim of the Turnan Poulsen Lumber Co. In all other respects the decree of the court below will be affirmed.
Modified. Rehearing Denied.