140 F. 225 | 8th Cir. | 1905
Lead Opinion
after stating the case as above, delivered the opinion of the court.
The parties to the contract in question in the most solemn form and explicit terms conferred upon Mr. Molitor, the chief engineer of the railroad company, most plenary powers and wide discretion in determining the nature and character of the work in its progress, the classification of material, the estimation for payments, and under what head the compensation therefor should be allowed. A reference to paragraph 25 of the contract shows that this power was conferred upon the chief engineer to prevent disputes or misunderstandings between the parties relative to any of the stipulations and provisions contained in the agreement, the true intent and meaning of the specifications, plans, profiles, and drawings, and also the matter of the performance of the contract by either of said parties'. It expressly stipulated that the chief engineer at the time was made, constituted, and appointed umpire to finally decide all such questions and matters; that he should determine and set forth in the final estimate the amount, quality, character, kind, and classification of all work and materials performed and furnished by the contractor under the contract, including all extra work and material, “and his decision and determination as to any and all such questions, matters, and things, and in construing any of the terms and provisions of this contract, shall have the force and effect of an award, and shall be final, binding and conclusive, to all intents and purposes and in all places, upon the said parties hereto; and the contractor hereby waives all objections to the appointment of said chief engineer as umpire by reason of his being a stockholder, director, or officer of the company.” It also conferred upon him the power to appoint all necessary assistants, resident and division engineers, etc., to represent him, and to vest in them all the powers conferred upon him. “Said chief engineer may take final action as umpire upon any and all questions, matters, and things arising under this contract, upon the reports and statements of said assistant, resident, and division engineers or other agents, without notice to the parties hereto or personal inspection of the work, and all of his acts in the premises shall be final and conclusive, and binding upon the parties to this contract.”
In making such a contract the parties dealt with each other at arm’s length. The contractors were at perfect liberty to consent to the provisions of the contract or to refrain from bidding. They are presumed, before bidding or signing the contract, to have fully advised themselves
The language of some of the courts, of highest authority, is that the proof of fraud must satisfy the mind of the court beyond a reasonable doubt. It is not sufficient that it should arise from a mere erroneous or unjust judgment or opinion of the umpire; nor can the award be disturbed upon the mere weight of evidence, in the conflicting opinions of expert witnesses, or based on the notion of a master resulting from a technical analysis of the evidence. As said by Justice Redfield, in Vanderwerker v. R. R. Co., 27 Vt. 130:
“After an estimate by the engineer, no recovery can be had beyond that sum, unless upon the most irrefragable proof of mistake in fact, or positive •fraud in the opposite party in procuring an underestimate, or corruption in the engineer.”
A mere mistake by the arbiter, not admitted by him, is insufficient to vacate the award. “How could the court adjudicate on the conflicting
While great deference is to be shown by the reviewing court to the master’s findings on such an issue, yet, where it is apparent that the evidence upon which he has acted fails to come up to the requirements of the adequate proof essential to warrant the court in overturning the award made by the umpire selected' by the parties themselves, it is the duty of the court to overturn the findings of the master. The allegations of the bill impeaching the award do not fully come up to the standard fixed by good rules of pleading. It will be observed that the allegations are in the alternative — either “through fraud, or some gross mistake in his estimates, as necessarily implied bad faith, or through failure to exercise an honest judgment, etc.” This was certainly bad for uncertainty, and invited a demurrer. But inasmuch as the respondents seem to have waived the objection by going to trial, and it is not apparent that they suffered any injury by the uncertainty, we are not disposed to halt on this objection.
A more serious, germane question, however, is presented by the direction given by the court in re-referring the case to the master. In his original report the master made no specific finding respecting the provisions of the contract above referred to, or as to the matter of the essential fraud or dishonesty of the engineer in rendering his final estimates, without which specific findings no decree vacating the award could be rendered. After sustaining this exception to the master’s report, the court, in recommitting it to the master with specific directions for additional findings, inter alia, said:
“To warrant a finding that the engineer, in his actions as umpire, was guilty of fraud or made gross errors in the measurements or classifications, or in the construction of the terms of the contract, the evidence must be reasonably convincing.”
The term “reasonably convincing” was liable to lead to a hurtful misconception on the part of the master. It might mean a mere preponderance of the evidence, a weighing of the relative strength of conflicting testimony, as would be sufficient to reasonably convince the mind that there were gross errors and the like. Whereas, the language of the law is that the evidence which will warrant a disturbance of such an award must be “the most irrefutable proof,” “overwhelming,” or persuasive “beyond a reasonable doubt,” or “free from all doubt and convincing,” or “so outrageous, etc.” There is, therefore, merit in the exception taken to said language by appellants, as the term “reasonably convincing” made the way easy for reaching the conclusions of the master.
It is difficult for the impartial mind to read the conflicting testimony of witnesses on many of the controverted matters on which the master made an adverse finding on the final estimates of the engineer without the conviction that the conclusion was reached by resolving too many reasonable doubts against the engineer, and accepting as his mentor
Borrow Pits.
The master found that the chief engineer “failed to carry into pay quantities in some of the monthly estimates, and in his said final estimate, a large quantity of classified material taken from borrow pits and placed in embankment.” What is known as “borrow pits” are pits dug along the side of the roadbed for the purpose of making embankments, where the material coming out of cuts and the like is insufficient for the construction of embankments. If, as the language of the master’s report implies, he found that there was a diminution by the engineer of borrow quantities consequent upon his failure to carry into pay quantities a large amount of classified borrow, it is in conflict with the evidence in the record. The total quantity shown by the final estimate of the engineer is 522,606 cubic yards. The aggregate quantities of all classifications made by the expert witness Reaugh is 514,233 cubic yards. By diminishing the quantity of earth and increasing the loose rock, as estimated by the engineer, Reaugh increased the value of the material to the extent of $34,324.33; while his estimate of quantity of all material is 8,373 cubic yards less than the engineer’s final estimate. The master, however, fixed the valuation at $29,634.19 in excess of the engineer’s allowance, and $4,690.16 less than Reaugh. How he made this differentiation his report is silent, as he gave no detailed specification.
The whole trouble over the borrow pit estimates grows out of a palpable disregard by the witness Reaugh, followed by the master, of the explicit provision of the contract respecting these borrow pits, and the designation of material that came out of them as “hard pan.” Paragraph 13 of the contract declares that:
“No classification whatever will be allowed, in borrow pits, unless such borrow pits are selected and approved by the chief engineer.”
This means exactly what it says. It is too explicit and mandatory to admit of controversy. It was intended to effectually interdict the very contention made by appellees that all the borrow pits claimed by them had either been recognized by the resident engineers or were essential for obtaining the necessary embankment material. The engineer testified, without contradiction, to the number of borrow pits designated by him or his deputies, and that he classified 19, including the slide material used as borrow, and 12 excluding the slides. Regardless of such designation, Reaugh classified all material coming from borrow pits, and arbitrarily set up his own judgment as to what were borrows for estimation and classification. The cross-bill does not even charge that the chief engineer failed and refused to designate the borrow pits, but is framed upon the theory that he failed to make proper classifications and estimates.
The exaggeration of the figures over those of the chief engineer, in this connection, furthermore resulted from Reaugh’s classification of an immense amount of material taken out of borrow pits as “hard pan.” As hard pan, under the specifications of the contract, was to be classified as lodse rock, to be paid for at 33 cents per cubic yard, and loose earth, at 13 cents per cubic yard, it made a wide difference in the computation whether the material in question was hard pan or earth. Hard pan, under paragrapth 12 of the contract, was to be classified as loose rock. Paragraph 13 declares that:
“Barth shall Include all loam, clay, sand, gravel, and all other material® which are not included in the above specifications of loose or solid rock.”
The evidence bearing upon the question as to what constitutes hard pan under this contract is most conflicting. The test applied by the witness Reaugh was that any earth or clay is hard pan which is hard enough to require a pick or other means to loosen it enough to pick it up with a spade or shovel. In this view he was corroborated by other witnesses. On the other hand, this theory was stoutly combated, not only by the chief engineer and the resident engineers on the work, but by outside experts of equal competency and integrity and as wide experience as those in behalf of appellees; and this is supported by the classification as earth made by the resident engineers and the chief engineer. The master himself in his report states that he found it impossible to reconcile the differences between the witnesses as to the-proper definition of hard pan, ana reached the conclusion that in railroad construction no unvarying standard or definition had been established to enable him to fix the term “hard pan.” Even the standard! dictionaries are not agreed thereon. He said in conclusion that:.
“With their varying ideas of just what constitutes hard pan, as employed in the specifications, it is not surprising that there should be a difference in-the classification of the material made by the engineers. When I say engineers, I do not refer to Molitor (the chief engineer) and Reaugh, but to all who have testified on that subject. And in this behalf it is not improper-that I should report that I have found the same difficulty in knowing how I should classify the material.”
And finally he accepted as the standard definition the Century Dictionary. I submit that the contract did not make the Century Dictionary the umpire on this question; but, on the contrary, the contract expressly declares that the chief engineer of the company—
“Is hereby made, constituted, and appointed the umpire to finally decide-all such questions and matters; and he shall also determine, and set forth in the final estimate, the amount and quantity, character, kind, and classification of all work and materials performed and furnished; * * * and his-decision and determination as to any and all such questions, matters, and things shall have the force and effect of an award, and shall be final, binding, and conclusive upon the said parties hereto.”
As said by Judge Gantt, in Williams v. Railroad Company, 153 Mo. 487, 543, 54 S. W. 689, 707:
“The fact that honest witnesses have deposed that there was hard pan, and equally honest witnesses testified it was not hard pan, cannot affect the-defendant, because it had a right to abide by the finding and classification of*237 the engineer to whom both parties had committed that question. It was to avoid this very conflict of evidence that this stipulation was placed in the contract”
Refills or Back Fills.
Paragraph 6 of the contract provides that:
“In rock excavation, material shall be taken out one foot below subgrade, and filled in again to subgrade line with good material for roadbed; such back filling to be paid for as earth excavation.”
In his final estimates the chief engineer allowed 7,523 cubic yards of back fill, and 26,669 cubic yards of subgrade on section “R” to 40, inclusive, on the construction work. On the same section Reaugh reported 27,888 cubic yards of back fill, an increase in quantity of 20,365 cubic yards and allowed 37,927 yards of subgrade, an increase of 15,258 cubic yards — a total increase of 35,623 cubic yards. This he effected by the following changes in classification of material: Earth reduced to 20,365 cubic yards, loose rock increased 4,446 cubic yards, and solid rock increased 10,817 cubic yards — an aggregate increase in value of $10,661.83. The master approximately followed Reaugh’s classification, increasing the money value, over the final estimate of the engineer, in the sum of $9,153.17, stating in his amended supplemental report that the chief engineer “had fraudulenty failed to credit the contractors with refill, which under the contract they are entitled to.”
The important evidence to support this change is that of the witness Reaugh, who simply stated that 13,256.17 cubic yards of back fill, as shown in the final estimates, had not been paid for, or even in pay quantities; and in another place in his testimony he gave a statement of the amount paid for or accounted for, and that the deficit occurred largely in the residency of MacCrea and Herring, resident engineers. The resident engineers on this work gave in detail the character of this work and their observation and accounting thereof. In substance it is that the subgrade was not taken out by the contractors to a foot below the profile grade throughout the extent of this work, and then back filled with select material, and therefore they allowed the full depth as excavation quantities; that the subgrade as to such points was carried as pay quantities, and not as back fill, because the subgrading was not down to the full depth, the regular foundation in place not having been disturbed. In such cases the subgrade to the full depth was allowed, whether taken out or not. On Herring’s residency, he testified that a large part of the material used in refilling was shale and slate, and the like — not at all suitable material — put in bv the contractors contrary to instructions and against protest. Mr. Beard, the assistant engineer on this division, testified that on inspection at the time he directed the resident engineers not to allow for this as back fill, for the reason that the material was unfit, taken by the contractors from ditches and the edges of cuts, composed of such materials as rendered it absorbent of water, and, furthermore, that the contractors had once been paid for this material in excavation taken from cuts.
Of all men acquainted with the foregoing asserted facts, the contractors themselves are to be presumed to have had knowledge; yet
The sole reliance, almost, for the master’s finding in respect of this back filling, is based upon superficial experiments and speculations of the witness Reaugh, who went over this work after the roadbed was completed and the ties and rails were down, and here and there along the line digging down to the foundation. This was, in the very nature of things, but superficial and speculative. We submit that if on such a state of facts the action of the chief engineer in making his final estimates, based upon the observation and memoranda made by the resident engineers on the work when being actually done, can be vacated for fraud or corrupt judgment, the provisions of such a contract as this are mere cobwebs.
The answer made to this by appellees’ counsel is that the chief engineer accepted this work after the alleged objection thereto by the division engineers. This contention is predicated of the correspondence between the contractors and Chief Engineer Molitor. On March 9, 1900, the contractors wrote to Molitor, calling his attention to paragraphs 24 and 25 of the contract, requesting him to furnish the final statements as therein provided. On the 14th day of the same month the engineer replied, calling the attention of the contractors to the fact that paragraph 23 of the contract contains a provision that before final settlement made for the work and material, and before any right of action could accrue to the contractors, they should furnish satisfactory evidence to the chief engineer that the work is free and clear from all liens for labor and material, and that there was no claim for which a lien could be enforced; that paragraph 24 provides that, when all that was agreed to be done by the contractors should have been performed and finished
“Until the provisions of paragraph 23 shall have been complied with, I would probably not be warranted in furnishing a certificate in connection with the final estimate in the form and to the extent contemplated by the provisions of paragraph 24; but I bare no disposition to embarrass you in any way by withholding the certificate. At the time the final estimate which you now have was furnished you, that question did not arise or occur to me, and X -had supposed that the final estimate, with my signature to it, would be taken as a compliance with the provisions of paragraph 24; but, since my attention has been called to the matter, I will say that I am willing to give you a certificate as provided in the paragraph referred to, subject to the provisions of the twenty-third paragraph.”
There might be some plausibility for said contention had the engineer, furnished the final estimate embracing the allowance for said material as back filling; but as this was not done, and the contractors were advised at the time the work was done that the material would not be accepted, there is no foundation for an estoppel, even if it had been pleaded, which was not done. The ruling in Fuller Co. v. Young Co., 126 Fed. 343, 61 C. C. A. 245, cited by appellees, is not apposite. The contract there did not contain an express provision that no intermediate action in allowing monthly estimates, or other action in limine, should avail, and that the final estimates should be conclusive, and the like. Nor was there any objection to the work at the time it was done, as here.
Differences in Classification of Material in Certain Cuts.
Without going into detail as to the differences resulting from the classification rather than the quantity of material in cuts, the final estimates of the witness Reaugh, practically followed by the master, result from his large allowances for solid rock and the elimination of earth and loose rock. A careful reading of all the evidence persuades us that his conclusions were necessarily based largely upon theory rather than actual facts proved, and were speculative rather than specific.. He went over these cuts some considerable time after they were made, when the roadbed was completed and the ties and rails were generally in place. As the cuts ran along hillsides, with only the back wall facing, it is at once manifest that, in taking the indications of this facing as a basis of classification and estimation, there was in it such an element of uncertainty as to invite the closest scrutiny into even its approximate accuracy. He could know nothing reliable as to the earth debris overlying the surface within the prism of the slope stakes. The testimony, without any material contradiction, shows that overlying these cuts, before the excavation, were from one to two, and two to three, and three to four feet of earth debris; that the rock lay in irregular strata, with a mixture of loose and solid rock and other loose material, running in irregular dips, rendering it mere guesswork by any expert, viewing it after the completion of the road, as to how much solid rock extended throughout the cut. The witness Reaugh testified that in such case he ascertained where the rock formation extended to the base of the roadbed by digging around in a few places and finding within a
We submit that no railroad company would consent in advance to pay for such a large amount of construction work on such methods. It -requires no expert eye to see that in taking a platted cross-section of the hillside, with irregular strata of varying dip, where the classification line is drawn from such back wall to an intersection with the bottom line of the cut, that a removal of two to four feet either way would inevitably make a considerable, if not vast, difference in the quantities of material within the sides of the triangle. On the other hand, it is the direct testimony of the resident engineers engaged on the work, .and the assistant engineer who made observations and noted the work in its progress from day to day, who cross-sectioned it, as to the large quantity of earth and débris overlying, as to the loose rock and solid rock within the prism, .as shown by the sectionized plats filed as exhibits, which formed the basis of the final estimates made by the chief •engineer. Superadded to this is the testimony of the expert witness Bontecue, an outside engineer, of wide experience and manifest intelligence, who testified, after inspection and examination of the finished -work, that it was practically impossible for any engineer, no matter Tiow skilled or painstaking, to make approximate reliable classification of the solid material taken out of cuts of such geological formation. He .gives as a reason for this, as to one of the principal cuts, that he did not consider that an intelligent classification could be made; that there -was only one side .of the cut generally exposed, with a very large face extending 1,000 feet along one side, and that evidently á more or less -triangular section had been removed in making the roadbed; that the face of the cut showed various kinds of rock, so that there was nothing to guide an after-comer in determining how far out into the triangular section the material originally extended; that it presented a case where there had been loose rock and solid rock, and possibly earth; and that it was not practical to tell how far into the cut the solid rock ran, or the .amount or rubbish that may have overlain it, or how much of loose rock was intermixed.
The witness Reaugh himself testified, in substance, that, where there -was only one wall of the cut visible, the general contour of the bluff was irregular, the angles or dips were not uniform, and the conditions were not usual; that if the stratified material was’ level, in making his classifications he would assume that such strata continued to the surface, .and if the strata inclined downward, toward the outer edge of the bluff, he assumed that the bottom of the cut would define the place where the top stratified rock cut the grade line or the grade plane. On such a state of evidence, to vacate the award of the chief engineer, upon the ground that he had arbitrarily and wantonly refused to make such a classification of solid rock as the witness Reaugh thought he should 'have made, would be nothing more than to substitute Mr. Reaugh for 4he umpire agreed upon by the parties.
What is known as the “Pinnacle Cut,” about 1,500 feet long, is a fair sample of the weakness of Mr. Reaugh’s methods and their unreliability. From this cut was removed 15,207 cubic yards of material, distributed in the final estimate as follows: 1,520 cubic yards of earth, 13,281 loose rock, and 400 yards of solid rock. Reaugh classified it: 1,841 earth, 10,450 loose rock, and 2,914 solid rock. The resident engineer’s testimony shows that this cut at one end was composed of red clay, with a mixture of yellow and red clay at the other end, with a few boulders intermixed therein, and that there was no material in the cut that came up to the requirement of solid rock, except a few boulders exceeding a cubic yard in size; that during the time he was engaged on that work he never saw a half dozen rocks that would measure enough to make a yard; that they were all below the specifications for solid rock. This testimony of Bowles pertains to his observation after he came on the work, when about one-third of it was completed. The assistant superintendent engaged on this division testified that he was present at the time of the stripping of the surface of this work, and that he gave it particular attention after about two-fifths of the material had been removed ; that the material was very similar from top to bottom, and throughout its length; there were houlders imbedded in clay and hard pan, but he found no material which would entitle it to be classified as solid rock; that before he took charge there were some estimates returned by the resident engineer opposite the boulders taken from the south end of the cut; that there was nothing in his observations which would entitle it to be classified as solid rock, and that the 400 yards of solid rock allowed was ample; that there was nothing in the cut after the work had been completed to enable any engineer to estimate the quantity of solid rock that had been removed, for the reason that the material had been moved away; and that there was no indication on the side of the cut or around it of boulders to be classified as solid rock. The expert witness Bontecue made a thorough inspection of this cut and tested the sides with a pick. He testified that in the only places he deemed it possible there might be a solid rock ledge, he found none ; that in his judgment 400 cubic yards, allowed by the chief engineer, amply covered the probabilities of the situation. His judgment was that the allowance of 2,914 cubic yards of loose rock, made by Reaugh, was approximately correct, and that no accurate estimate of the amount of boulders which should have been measured as solid rock could be made. The exaggerated amount of solid rock estimated by Mr. Reaugh, we think, was simply arbitrary, and on the mere weight of evidence it should be rejected.
Timber, Piling, and Extra Work.
The witness J. T. McCarthy, relied upon by appellees, testified that there was a difference between what he estimated and the final estimates in the item of timber of 167,946 feet, making a difference in value in favor of the contractors of $3,694.71, and of the piling of the value of $1,476.74. The cross-examination developed the fact that he had in-
Said McCarthy presented a claim of $2,242.28 for extra work, and the master allowed him $2,322.86. By what process the master reached this beneficent result in favor of McCarthy the record does not disclose. The examination of the claimant showed that he had little personal knowledge of the work; that his claim was based much upon reports of subordinates. On the other hand, the testimony of Mr. Bowles, the assistant engineer on this division, is direct to the effect that the items disallowed had been paid, that many of them came within the specifications of the contract as work capable of measurement, and, therefore, they were excluded as extra work, but were included in the estimates made. Paragraph 6 of the contract provides that all extra work shall be done on the written order of the chief engineer, fixing the price to be paid for the same; that the obtaining of the certificate of the chief engineer as to the work done and the price thereof shall be a condition precedent to the right of the contractor to be paid for any such extra work, and that nothing shall be deemed extra work which can be measured; that all claims for extra work or material be presented to the chief engineer at the close of the month in which it was done or furnished, to be included in the estimate for that month, otherwise all claims therefor shall be deemed waived by the contractors, and the contractor shall not be allowed or paid for the same. The testimony fails to show that these provisions of the contract were complied with. McCarthy himself testified that he wasjmable to state whether the extra work was ordered by the chief engineer; that while his bills were rendered in March, 1900, he said he was never able to find them at the
The Slides.
The principal controversy in this case centers around what is designated as “slides,” on the bluffs known as “Ross Hollow,” and on residency D4, embracing sections 23 to 31. The roadbed at these points was located along steep bluffs near the south bank of the Arkansas river. Much of the roadbed was cut out of the side of the bluffs, which were quite steep in places, and extending 'several hundred feet above the roadbed. At some points the bluff was so steep as to prevent the growth of vegetation on it. The testimony of the resident engineer was to the effect that underlying a debris of earth, etc., was rock of irregular strata of various thicknesses, ranging from four inches to three or four feet, of irregular formation. The roadbed, of course, was made by blasting the material out of the side of the mountain. Paragraph 5 of the general specifications declares that:
“Excavations in rock shall be taken out 18 or 20 feet base, with slopes of one-quarter horizontal to one vertical. In rock excavations, all projections toward the-center line of the track beyond the plane of the measured prism, and all material on slopes loose or liable to fall, shall be removed.”
No excavations were necessary on the river side; but the work was on .the hill side, where the slope in some places continued below the roadbed for a distance of 30 or 40 feet, and at some points the face of the bluff extended to the water’s edge, "and at others there were intervening flats between the foot of the slope and the water. In blasting for the construction of the roadbed, large quantities of material fell outside of the roadbed into the river and onto the flat places, and some of it was thrown even beyond the river. Owing to the peculiar geological formation of the rock, lying in irregular strata, when the supporting rock at the base of the roadbed was removed, the superincumbent strata of rock would break and slide down, much of it falling beyond the railroad bed, and much of it on the roadbed. .It is this material which is designated as “slide,” distinguished from that which was taken out within the slope stakes in the estimates of the engineer. That taken out within the slope stakes was treated as roadbed excavation, and was classified with reference to its original position in the bluffs, and a large part of it as solid rock. The slide began to fall in December, after work begun. About the month of March, 1899, a large amount of this slide attracted especial attention, and the contractors began to complain that the resident engineers, in their monthly estimates, were only carrying this material as earth, instead of solid rock, to their great distress and embarrassment in not receiving the 90 per cent, to which they claimed they were entitled. In April following the chief engineer directed the bluffs cross-sectioned for the purpose of ascertaining the extent of the excavation; the evidence on his part tending to show that he was in great doubt in his mind as to how this slide material should be classified. On account of the falling of this slide material and the difficulty of the construction of the road on the bluff side, the engineer abandoned this location and
The contention of the contractors is that they were entitled to pay for all the slide material, to be classified in its original condition in the bluff before it was dislodged, and, therefore, to be estimated and paid for as solid rock. This view was sustained by the master in his report. On the other hand, the chief engineer classified it principally as loose rock, including all that which went beyond the roadbed into the river or beyond the embankment, as well as that which fell on the roadbed. The testimony on behalf of appellants tended to show that perhaps 40 per cent, of this material fell beyond the roadbed, and was not handled at all by the contractors, and that the great mass of that which fell on the roadbed was thereby so broken and shattered as to make it loose rock, removable with shovel, and with very little blasting of the larger stones. So that in estimating it as loose rock, both as to the quantity that was not handled at all and that which was handled in removing it from the roadbed, the chief engineer deemed his classification and estimation more than just to the contractors.
The contention that said paragraph 5 of the contract warrants the classification of this slide material as solid rock in its place before its dislodgement is evidently an afterthought, as it is contrary to the allegations of the cross-bill of complaint. In respect of this slide the cross-bill declares “that it is the universal custom, in cases where the slopes in solid "stone are not sufficient to prevent the sides of the cut from falling into or upon the cut made for the railroad, to pay for the removal of such solid rock, loose rock, and earth,” and that they have not been made adequate allowance therefor. There was no removal of this material by the contractors, except where it lodged on the roadbed or was used by them as borrow in constructing the embankment. They were allowed for all the quantity of material in place within the prism of the railroad excavation. They employed neither powder nor pick, or other force, to bring down the slides. They came of their own momentum. The clear meaning of paragraph 5 is that, as in excavations, there might be outside thereof projections of rock or material dangerous to the road, it should be removed' by the contractors, and that there might be material on the slopes which was loose or liable to fall, and the contractors would be required to remove that. But they neither removed the slides as projections nor otherwise in their natural position. If the contention of the contractors, that all this slide material should be paid for as solid rock, is correct, it would, by the same reason and law, follow that if the bluff had extended back 1000 feet, and after the roadbed was blasted out the superincumbent strata of rock, to the mountain summit, had broken loose, and 100,000 cubic yards thereof tumbled into the river, beyond the roadbed, and was never touched by pick or spade- or hand of the contractors, they would be entitled to receive pay for it as solid rock in its original position.
Chief Jutice Redfield, in Herrick v. Belknap’s Estate, 27 Vt. 694, in discussing the question of classification of slides under a contract on a not dissimilar state of facts, said:
*245 “The slide of 10,000 feet of earth Into the river, which was allowed by the masters at $1,000 as earth excavation, seems to me manifestly not to come within any just idea of excavation under the contract. It does not seem to have been the result of any art or contrivance, like bringing a stream of water to bear upon the bank, which has been treated as a legitimate mode of excavation under similar contracts. But this slide, and others at thi3 point, were altogether accidental, and neither expected nor desired. Neither did they come within the range of what was originally intended as the bed of the road. This slide, and numerous others near the same point, resulted from the. breaking away of the bank from time to time, which rendered it necessary to carry the bed of the road further back) into the hills. At the price to be paid for earth excavation, these slides, at this point, would, in all, amount probably to nearly $10,000. And where they fell into the roadbed, and were required to be again removed, the engineers uniformly estimated the removal. But where they fell at once into the river, from a point not originally, or until the convulsion, intended to have been excavated, there seems no reason why they should be estimated as excavation under the contract, even if the whole hill, from its very base, had been at once removed by an earthquake or a volcano. It seems to us the engineers did right in rejecting this claim; and, right or wrong, their decision, if fairly made, is conclusive upon the parties.”
The difference in classification made by Reaugh, and followed by the master, in the estimation of this slide material, amounts to $25,228.16. Even this result was reached by entirely eliminating any earth material,' diminishing the loose rock, and exaggerating the amount of solid rock. We are unable to understand how it was found that the material contained no loose earth and so little loose rock. Without contradiction from any direct testimony, the evidence of the engineers present on the work is that on the slopes were large quantities of earth, supporting a growth of large trees, undergrowth, and vegetation, with a large mixture throughout the strata of material constituting loose rock; and this was corroborated by other evidence. Mr. Reaugh necessarily based his conclusions on observation of the face of the wall on the slope. He never saw the surface of the bluff before the excavation. He could not, at the time he took his observations, make any approximate estimate of the amount of loose earth and loose rock. His total estimate of material exceeds the aggregate of the chief engineer by 12,832 cubic yards. Exactly how he reached this difference in quantity is not made apparent. As a general rule throughout the estimations along the line of the road there is little difference between the finál estimates of the chief engineer, or the resident engineers, as to the quantity of materials, and that of the witness Reaugh. There was evidence ‘ on behalf of appellants that the jarring down of this slide was attributable in some degree to overcharging the shots made by the contractors, evidenced by the fact that it blew large quantities, in large bulk, across the river, and across a near-by creek, into adjoining fields, which became a matter of complaint by the owners of the farms; and this was corroborated to some extent by observations taken by experts, who afterwards examined the premises. One of the expert witnesses, who testified in behalf of appellants, stated that in his opinion the classification of the amount of solid rock and loose rock, made by the chief engineer, was too small; but at the same time he stated that it was more a matter of
Evidence of Fraud and Conspiracy.
The master did not specify in his report the particular acts evidencing fraud, oppression, or corrupt judgment on the part of the chief engineer. The learned counsel for appellees animadvert upon the prior statement claimed to have been made by the chief engineer in a letter written to one Dandridge. One Kavanaugh, a witness introduced by appellees, testified that Dandridge showed him a letter addressed to his firm, signed by Molitor, which contained the statement that “McCarthy & Reichardt have the contract, but they may be very sorry that they ever received it.” He gave no date of this letter. Molitor testified that he did not write any letter to Dandridge, or to any member of his firm, after the contract was let to McCarthy & Reichardt. Dandridge testified that he was not in the city of Dittle Rock at the time and place testified to by Kavanaugh; that he had no conversation with Kavanaugh in regard to the contract; that he did have a casual conversation, in Frankfort, Ky., with Kavanaugh, in which Kavanaugh told him he heard of some complaint by the contractors, and that probably he told him he had rather expected that, because he thought the figures bid by all the contractors were too low; that he did not know Molitor personally, and that his recollection was that he did not show Kavanaugh any such letter, and felt sure he had no such letter in his possession. We submit that such testimony hardly warrants making it the basis of finding a hostile mind on the part of the chief engineer. It is true that the chief engineer did complain to the construction company of their action in awarding the contract to McCarthy & Reichardt at a higher figure than that of other bidders. This, it seems to us, should rather redound to the credit of the spirit of honesty and fairness of the chief engineer than to make it the basis of a motive for being dishonest- in dealing with the contractors.
Appellees also put in evidence the deposition of one Knobel, who testified that down in the Indian Territory he had a conversation with Mr. Molitor regarding the location and construction of railroads in general; that during the conversation the witness remarked that as a rule railroad companies did not take sufficient time to find the best location to be had through the country, and when once located and built the necessary changes were very expensive work; that Molitor differed with him, and stated that he could make great savings to any railroad company in the construction of its road, no matter how it was located; that he asked Molitor how he could change the general result in the cost of construction after the final location was adopted, and profile and gradients approved, showing almost exactly the quantities of every piece of work under the contract; that Molitor asserted that there were a good many ways, not mentioning any particular one; that he said to Molitor the only way he knew of was in not returning full estimates for the work done, or failing to classify the work properly; that this ended the conversation. On cross-ex-
Special reliance for proof of a disposition on the part of the chief engineer to defraud and wrong the contractors is based upon the conduct of the chief engineer in the progress of the work in withholding from the contractors full monthly estimates, to entitle them to the 90 per cent, pay therefor. It may be conceded, as the facts turned out, as shown by the results of the final estimates, that the resident engineers and the chief engineer dealt illiberally with the contractors in the monthly allowances, especially in respect of the work where the slides occurred, and on what is known as the “Slayton Residency." As already stated, in the classification of materials at the slides for the first two or three months on the bluff work, the resident engineer, under the direction of the chief engineer, returned the whole amount as loose earth. This was done, as testified by the chief engineer and the resident engineer, because of the uncertainty in the mind of the engineer as to how that material should be classified, as the respective quantities could not be approximately ascertained until the excavation was done and the work cross-sectioned, intending to rectify the matter in the final estimates. The delay in respect of the proper monthly allowances on the Slayton residency the engineer accounts for on the ground that the first resident engineer on this work proved to be quite incompetent; that the confused condition of his notes kept of the work rendered it quite impossible for Slayton, who succeeded him, to make an approximate, ■ reliable estimation, so that it was necessary to cross-section the work to bring order out of confusion. With detail Slayton explained the peculiar condition of the work on- which he was engaged, and the difficulties with which he had to contend, preventing approximate estimates, as under ordinary normal conditions; that he had to cross-section at different times, as he had opportunity. He explained why it was that in the October, 1899, estimate, where the
After all the denunciatory epithets heaped upon the chief engineer respecting this work, the analysis shown in tabulated form by counsel for appellants, presenting in detail the comparative estimates made by the chief engineer and the witness Reaugh, demonstrates little foundation therefor in fact. The analysis shows the following result:
Molitor’s final estimate:
Earth ................................................ 17,643
Loose rock............................................ 85,492
Solid rock............................................ 71,942
Total quantities in cuts, per Molitor .......................... 175,077
Reaugh’s estimate shows:
Earth ................................................ 6,627
Loose rock ........................................... 85,603
Solid rock............................................ 83,S85
Total quantities in cuts, per Reaugh ........................ 176,115
Reaugh’s excess ........................................... ,1,038
Total value cut quantities, per Reaugh ............$79,441.50
Total value cut quantities, per Molitor ............73,681.35
Reaugh’s increase ....................... $ 5,760.35.(8 per cent)
As thus shown, Mr. Reaugh, who did not see the work while being done, minimized the quantity of loose earth and increased the quantity of solid rock. It does seem to us that it is but fair to say that such a difference so reached is not sufficient foundation for a charge of fraud and corruption, even if it were conceded that Reaugh’s figures are nearer correct than those of Molitor, when the law commands that every reasonable intendment shall be indulged in favor of the honest judgment of the umpire.
The contention of appellees is that the underlying purpose of the chief engineer in withholding the proper monthly classifications and allowances, was to so embarrass and burden the contractors with lack of funds during the progress of the work as to compel them to abandon the contract, and that, failing in this, he carried his animus into the final estimates. - The gravamen of the cross-bill of complaint is that the final estimate of the chief engineer is wrong. If the final estimate had been -satisfactory or just, no cause of action would exist, for the palpable reason that the contract provides that the monthly estimates shall in no wise be conclusive, but the same “and all of the particulars i elating thereto, including quantity, quality, and price, shall be subject to revision and adjustment of the chief engineer of the company,” and “the company shall not be liable for any errors or omissions in said approximate monthly estimates, nor for any loss or damage suffered by the contractor by reason of his having settled with his subcontractors on the faith thereof, or otherwise.”
Possibly, during the progress of the work, had the resident engineer refused to make proper returns, the contractors might háve resorted to the writ of mandamus against the engineer to compel proper action ; or they might- have been justified in abandoning the contract and suing for breach thereof. But when, as in this case, they elected to continue, their reliance for- justice was in the righting of wrongs in
At the hearing counsel for appellees animadverted upon the fact that on the bluff cuts nearest to Little Rock, where the chief engineer was located, he often saw this work during its progress, and must have known that inadequate monthly estimates of the work there done were being reported by the resident engineers, and that this showed improper conduct and an evil disposition towards the contractors. Then in the same argument the contention was made that the chief engineer, in making his final estimates, did not make sufficient inspection of the detailed work; that the time he occupied thereon warrants the conclusion that he depended upon the monthly estimates, and not upon personal knowledge and investigation. The two positions are hardly reconcilable. The testimony of the chief engineer, supported by a number of credible witnesses, is that he spent a great deal of time on the work along this line during its progress, more so than usual, and that with the knowledge that he had of the work and the examination he made his final examination was amply sufficient to give him all the information necessary.
There is no dispute in the case that on the final estimate made by the chief engineer there was a balance of $122,911.02 due the contractors, subject to liens thereon by their subcontractors. The master, in his final estimation, holds that in the aggregate it was over $100,000 less than it should have been. The total length of the line of construction was 168 miles, at an estimated cost of about $2,500,000, and the work of McCarthy & Reichardt amounted to over $834,000. Even such a discrepancy on such a large amount of work might afford little reason for vacating the award for fraud and oppression. But when, as. shown by this discussion, Mr. Reaugh and the master, by misconstruction and misapplication of the plain provisions of the contract, improperly found in favor of the contractors for nearly 60 per cent, of the difference, the remaining margin, in view of all the evidence, hardly furnishes a basis for disturbing the chief engineer’s award on the mere weight of evidence.
There is not a word of evidence presented in this record to support the charge made in the cross-bill of complaint that the failure of the engineer in making proper allowances on the monthly estimates was influenced by the fact that the construction company or the railroad company was short of sufficient funds to meet the payments, or that there was any such understanding between the engineers and the companies.
It is not unimportant, before closing this part of the discussion, to say that the appellees are hardly in position to justify their denunciation of Molitor and the resident engineer, Herring, who was engaged
The testimony of these witnesses, like that of any other witness, should rather be judged by its internal probability, its specific particularization, candor, and sensibleness. On the other hand, it is difficult for the unprejudiced mind to read this record without the impression that the testimony, the opinions, and deductions made by the expert -witness Reaugh were deferred to and followed as if he were almost an infallible guide.
Interest.
The master has allowed interest upon the whole sum found by him to be due to the contractors from the 11th day of July, 1903, the date of the decree, at. 6 per centum per annum. Section 23 of the contract declares that:
“Before final settlement is made between the parties hereto for work done and materials furnished under this contract, and before any right of action shall accrue to the contractor against the company therefor, the said contractor shall furnish evidence satisfactory to the chief engineer of the company that the work covered by this contract is free and clear from all liens for labor or materials, and that no claim then exists against the same for which any lien could be enforced.”
As the master has found that there were large amounts of outstanding claims against the contractors in favor of subcontractors, which are declared by the decree to be liens on the corpus of the railroad, it is contended that the suit on the cross-bill at least was prematurely brought, and that consequently no interest should be allowed on the balance admittedly due the contractors under the final award. At the hearing, when the foregoing paragraph of the contract was brought to the attention of the court, it was suggested to counsel that, if this view of the effect of paragraph 23 should be taken by the court, it might result in disposing of the whole case on appeal on that ground, without determining the merits; and inquiry was made of
“If the court should determine (1) that the master’s report should be set aside and (2) th'at this action was prematurely brought, the appellants consent, subject to all their legal rights in the matters of costs and interest growing out. of the fact that the action was prematurely brought and the provisions of the contract as to the time when the alleged indebtedness should become due and the right of action therefor accrue, that the court may set aside the findings and report of the master, and consider and decide the issues arising in said cause on this appeal under the evidence contained in the record, the same as if it had been brought in apt time, and make all proper orders in reference to the matters of costs and interest in accordance with the legal rights of the parties as if this consent had not been made or given.”
The sum of $122,911.02 is conceded by appellants to be due the contractors on the final award of the chief engineer. The aggregate amount of the sums found in favor of subcontractors is $30,043.88. The Circuit Court allowed interest on the balance found due from the date of entering its decree, July 11, 1903. Had the respondents below, on the entering of this decree, paid the said sum of $122,911.02 into court, subj'ect to its order of distribution, according to the rights of the lienors, no interest could have been allowed thereafter; and as it has had the use of said balance during this appeal, we think it within the reasonable discretion of the court, under all the circumstances of this case, to allow the specified rate of interest on said balance from the 11th day of July, 1903.
It results that the decree of the Circuit Court in favor of the cross-complainants against appellants is reversed, and the cause remanded, with directions to the Circuit Court to set aside its decree approving the master’s findings, and to enter a decree in favor of said appellees, McCarthy & Reichardt, in the sum of $122,911.02, with interest thereon at the rate of 6 per cent, per annum from the 11th day of July, 1903, declaring a lien upon the corpus of the railroad property for that sum, to be enforced by execution if not paid within 30 days after the entering of said decree; that out of the proceeds of said fund the other special liens found by the master and the court to be due and owing to the complainant and interveners be first paid; and to tax the costs of this proceeding against the appellees and appellants in the proportion of three-fourths to the appellees, McCarthy & Reichardt, and one-fourth to the appellants.
Dissenting Opinion
(dissenting). The conclusions of the majority that the master erroneously disregarded the provision of the contract that “no classification whatever will be allowed in borrow pits, unless such borrow pits are selected and approved by the chief engineer,” and that he classified a large amount of material as “hard pan” and loose rock which the chief engineer had the right in his discretion to designate loose earth, seem to me to be correct; but I am unable to assent to the other views expressed in the opinion or to the general result of the decision of the court.
It is conceded by the witnesses for all the parties that 90 to 95 per cent, of the slide material was originally solid rock in place, and the concession is also made that the material in the measured prism within the stakes was properly measured in excavation and allowed as solid rock, although a large portion of it was thrown over the precipice when blasts were fired and required no farther handling. The contract provided that:
“In rock excavations all projections toward the center line of track beyond the plane of the measured prism and all material on slopes loose or liable to fall shall be removed.”
If the rock which slid from above the prism had remained overhanging and liable to fall, the contractors would have been required by this provision of the contract to blast it out and to remove it; and if they had done so they would have earned payment for rock measured in excavation. The natural interpretation of the provision appears to me to be that they were entitled to the same payment, although the rock slid from its place upon the removal of the prism. For a long time after large quantities of this rock had descended upon and beyond the prism the chief engineer refused to allow any estimates whatever on account of it, and for a still longer time he classified it as loose earth, and in his final estimate changed his classification to loose rock, but never allowed any substantial part of it as solid rock. Complaint was made t.o him as early as April that this slide material was not carried into pay quantities in the approximate estimates. He absolutely refused in that month to carry any part of it into these estimates, except a small portion in certain borrow pits which he designated. In other words, he refused to give to the contractors approximate estimates to
There are many other facts which this record discloses that appear to me to point in the same direction. When all the facts which the evidence establishes are considered together, they seem to me inconsistent with the exercise of good faith by the engineer, and ample to sustain the finding of the master and of the court below that he intentionally reported the amounts due the contractors in both his approximate and final estimates much less than he knew they were •entitled to receive; and this conclusion leads directly to the result that the findings of the master and of the court below should be sustained in all things, except in the allowance of the increase on account of the •material taken from the borrow pits, which they gave under a mistaken view of the terms and effect of the contract in this regard.