Children's Corner Learning Center v. A. Miranda Contracting Corp.Children's Corner Learning Center v. A. Miranda Contracting Corp.
Gogick, Byrne & O’Neill, LLP, New York City (Anthony W. Vaughn, Jr. of counsel), for George E. Berger & Associates, LLC, appellant.
Zeichner Ellman & Krause LLP, New York City (Bryan D. Leinbach and Barry J. Glickman of counsel), for JAM Consultants, Inc., appellant.
Ellen Rothstein, New York City, for Children’s Corner Learning Center, respondent.
Milber Makris Plousadis & Seiden, LLP, Woodbury (Sarah M. Ziolkowski and Lorin A. Donnelly of counsel), for Henry Loheac, P.C., respondent.
OPINION OF THE COURT
MAZZARELLI, J.
In March 2004, plaintiff retained defendant Henry Loheac, P.C. to provide architectural services for plaintiff’s planned conversion of premises it leased into a day care center. Plaintiff alleges that it advised Loheac that it intended to begin operating the day care center in January 2005. Plaintiff also claims that Loheac assured it that all necessary construction permits and licenses would be obtained by November 2004. Construction was delayed, causing the day care center to open approximately six months later than the target date of January 2005.
Thereafter, plaintiff commenced this action against Loheac, A. Miranda Contracting Corp. (plaintiff’s general contractor), Newman Design Group (the architect retained by the building’s owner), MF Electrical Service Co., Inc. (the electrical subcontractor hired by the general contractor) and High Rise Fire Protection Corp. (the fire alarm installer allegedly hired by either the general contractor or the electrical subcontractor). Plaintiff’s claims against Loheac are found in the fourth, fifth and sixth causes of action in the complaint. In the fourth cause of action, plaintiff asserts Loheac breached its contract by, generally, failing to perform its work in a timely fashion. As a result, plaintiff alleges it was unable to obtain the licenses necessary to open a fully operational day care center in January 2005. Plaintiff says it was damaged because it “was caused to incur additional expenses to help correct the defective, faulty, improper and inadequate work caused by LOHEAC’s breach of contract so that Plaintiff could open and operate as a fully licensed day care center.”
The fifth cause of action also sounds in breach of contract. Plaintiff claims that Loheac caused it “unanticipated, uncontemplated and/or unreasonable delay and disruption” by not obtaining the necessary licenses and permits for, and otherwise failing to properly supervise the installation of, a fire alarm system. In the fifth cause of action, plaintiff maintains it was damaged to the extent that it “has incurred, expended or has been deprived of payment and damaged for all consequential and inconsequential damages, including, but not limited to, those incurred for additional labor, supervision, supplies, material, equipment, and losses for rent and additional rent, loss of operating expenses, and lost profits.”
Plaintiff asserts in the sixth cause of action that Loheac was negligent in the performance of its duties, and that its acts and
“opening of the day care center was severely disrupted and impeded and was rendered uneconomical and costly beyond its anticipation or reasonable expectation; among other things, Plaintiff was delayed from opening for six months, or more than 100% of the original contract period; Plaintiff’s planned opening was delayed into seasons contrary to the original schedule; Plaintiff was forced to incur additional expenses to be able to open the day care center on an interim basis and on a full time basis; Plaintiff’s initial advertising and initial operating costs were rendered a loss, as Plaintiff was unable to open as scheduled; Plaintiff was deprived of the benefit of its bargain with its landlord in that Plaintiff was unable to fully operate during the initial six month lease period in which Plaintiff had been given a 100% rent abatement; Plaintiff was deprived of the ability to collect revenues from which to pay, among other things, operating expenses; Plaintiff was deprived of its profits to be derived from the fully operational the day care center [sic] for approximately six months; the value of the Premises was diminished based upon Plaintiff’s inability to utilize same in the manner intended, at the capacity intended and of which defendant was fully aware for approximately six months.”
Loheac commenced a third-party action against, among others, appellants George E. Berger and Associates and JAM Consultants, Inc. The third-party complaint identified both Berger and JAM as having been retained by plaintiff, the building owner or the property manager “as an expediter with respect to the filing of applications to obtain permits, licenses and other approvals of the work performed at the subject building including but not limited to the electrical system, fire sprinkler system and alarm system.” Loheac alleges in the third-party complaint that Berger and JAM “failed to possess the requisite skill, knowledge and ability to obtain such permits” and that their “fail[ure] to timely obtain the necessary permits, approvals and licenses within a reasonable time period result[ed] in
Defendant Newman Design Group moved, pursuant to
In opposition to the cross motions by Berger and JAM, Loheac stressed that the claims made by plaintiff against it included a claim for professional malpractice, in addition to those for breach of contract. The possibility it might be found liable in tort, Loheac asserted, permitted it to make claims for common-law contribution and indemnity. In opposing the cross motions, Loheac did not identify any agreements between it and either Berger or JAM that supported its claims against them for contractual indemnification and breach of contract.
The motion court granted the cross motions of Berger and JAM only to the extent of dismissing Loheac’s third-party claims for contractual indemnification and breach of contract. This was based on Loheac’s failure to oppose those parts of the cross motions which addressed those claims. However, the court refused to dismiss the claims for common-law contribution and indemnification. Relying on Tower Bldg. Restoration v 20 E. 9th St. Apt. Corp. (295 AD2d 229 [2002]), the court held that plaintiff’s claim for professional malpractice against Loheac supported Loheac’s third-party claims against Berger and JAM. The court further held that Loheac stated valid causes of action against Berger and JAM for common-law indemnification by alleging that Loheac’s failure to obtain permits in a timely fashion was solely the result of the negligence of Berger and JAM.
“Except as provided in sections 15-108 and 18-201 of the general obligations law, sections eleven and twenty-nine of the workers’ compensation law, or the workers’ compensation law of any other state or the federal government, two or more persons who are subject to liability for damages for the same personal injury, injury to property or wrongful death, may claim contribution among them whether or not an action has been brought or a judgment has been rendered against the person from whom contribution is sought” (
CPLR 1401 ).
In the cases which have followed since the Court of Appeals decided Dole v Dow Chem. Co. and this statute was enacted, it is well established that “purely economic loss resulting from a breach of contract does not constitute ‘injury to property’” (Board of Educ. of Hudson City School Dist. v Sargent, Webster, Crenshaw & Folley, 71 NY2d 21, 26 [1987]). In Sargent, a case similar to this, the plaintiff, a school district, commenced a breach of contract action against the architectural firm that designed a school construction project and the general contractor that built the school. The school’s roof began to leak shortly after construction was completed. The school district claimed that the architects breached their contract with the district by not obtaining proper approval of the roofing subcontractor and by failing to secure a guarantee from the roof manufacturer. The architects sought contribution from the general contractor. In that case, the Court of Appeals, after reviewing Dole v Dow Chem. Co. and the legislative history of
“[t]o permit apportionment of liability, pursuant to
CPLR 1401 , arising solely from breach of contract would not only be at odds with the statute’s legislative history, but also do violence to settled principles of contract law which limit a contracting party’s liability to those damages that are reasonably foreseeable at the time the contract is formed” (71 NY2d at 28).
Loheac tries to distinguish the present matter from Sargent. It argues that, unlike here, there was no claim for professional malpractice in Sargent, asserting that the presence of a tort claim against it in this action permits a claim for contribution. While claims for professional malpractice and breach of contract may coexist, even though both arise out of the professional’s contractual obligations (see Sommer v Federal Signal Corp., 79 NY2d 540, 551 [1992]; 17 Vista Fee Assoc, v Teachers Ins. & Annuity Assn. of Am., 259 AD2d 75, 83 [1999]), Loheac’s argument must be rejected. This is because the touchstone for purposes of whether one can seek contribution is not the nature of the claim in the underlying complaint but the measure of damages sought therein (see Trump Vil. Section 3 v New York State Hous. Fin. Agency, 307 AD2d 891, 897 [2003], lv denied 1 NY3d 504 [2003]; Rothberg v Reichelt, 270 AD2d 760, 762 [2000]; Rockefeller Univ. v Tishman Constr. Corp. of N.Y., 240 AD2d 341, 343 [1997], lv denied 91 NY2d 803 [1997]). Here, the damages sought from Loheac are economic only. That is, plaintiff seeks only to be returned “to the point at which the breach arose and to [be placed] in as good a position as it would have been” had Loheac secured the permits in a timely fashion (Brushton-Moira Cent. School Dist. v Thomas Assoc., 91 NY2d 256, 261 [1998]). That Loheac seeks the same measure of damages for breach of contract as for professional malpractice is confirmed by the fact that the specific damages sought in the fifth cause of action for breach of contract are substantially similar to the specific damages sought in the sixth cause of action for professional malpractice.
In arguing to the contrary, Loheac relies, as did the motion court, on Tower Bldg. Restoration v 20 E. 9th St. Apt. Corp. (295 AD2d 229 [2002], supra). However, that case is distinguishable. Although the decision in Tower Bldg. Restoration did not specify the nature of the damages sought against the fourth-party plaintiff architect, a review of the briefs does. They reveal that the third-party plaintiff there, a cooperative apartment corporation, sought traditional tort damages from the architect in connection with the architect’s alleged damaging of the floor and roof of one of the apartments in the building. In this case, plaintiff does not claim any damages that seek traditional tort remediation.
Loheac’s reliance on Castle Vil. Owners Corp. v Greater N.Y. Mut. Ins. Co. (58 AD3d 178 [2008]) is also misplaced. The claim
Loheac also looks to the Third Department’s decision in Robinson Redevelopment Co. v Anderson (155 AD2d 755 [1989]) for support. In that case, the Third Department held that contribution is available even where the plaintiff seeks purely economic damages as a result of professional malpractice. However, this Court has expressly declined to follow Robinson (see Rockefeller Univ. v Tishman Constr. Corp. of N.Y., 240 AD2d at 343). Moreover, the Third Department has implicitly overruled Robinson (see Rothberg v Reichelt, 270 AD2d at 762 [2000] [citing Rockefeller University in dismissing common-law contribution claim where plaintiff’s underlying complaint sought only the benefit of a contractual bargain]).
Loheac’s common-law indemnification claim against JAM should also have been dismissed pursuant to
However, Loheac’s claim for common-law indemnification against Berger should continue. On a motion pursuant to
Accordingly, the order of the Supreme Court, Bronx County (Wilma Guzman, J.), entered July 16, 2007, which, to the extent appealed from, denied the cross motions of third-party defendants-appellants for summary judgment dismissing defendant/third-party plaintiff-respondent’s common-law claims for contribution and/or indemnification, should be modified, on the law, to grant summary judgment to third-party defendant-appellant JAM Consultants, Inc. dismissing the third-party complaint as against it, and to grant summary judgment to third-party defendant-appellant George E. Berger & Associates, LLC dismissing defendant/third-party plaintiff-respondent’s common-law claim for contribution, and otherwise affirmed, without costs.
GONZALEZ, P.J., ANDRIAS, MOSKOWITZ and RENWICK, JJ., concur.
Order, Supreme Court, Bronx County, entered July 16, 2007, modified, on the law, to grant summary judgment to third-party defendant-appellant JAM Consultants, Inc. dismissing the third-party complaint as against it, and to grant summary judgment to third-party defendant-appellant George E. Berger & Associates, LLC dismissing defendant/third-party plaintiff-respondent’s common-law claim for contribution, and otherwise affirmed, without costs.