Lead Opinion
This appeal is taken from a summary judgment entered against Chief Industries in an action brought by it to foreclose a materialman’s lien.
The material facts are not in dispute. In November 1975, defendant-respondent Dean Schwendiman entered into a contract with W & W Sales and Service, Inc., which called for W & W to construct an all-steel building for fertilizer and grain storage on the Schwendiman property. During February 1976, plaintiff-appellant Chief Industries, at the request of W & W, delivered construction materials valued at approximately $28,000 to a location on the Schwendiman property. Shortly after the delivery of the materials, W & W abandoned the construction project and no building or structure of any kind was constructed or has been constructed with those materials. The record before us does not disclose the ultimate disposition of those building materials.
According to the contract between Schwendiman and W & W, periodic payments were to be made by Schwendiman to W & W, including $30,000 upon the delivery of the building materials. At the time W & W abandoned the construction project, Schwendiman had paid to W & W a total of $37,536.80. No direct contractual relationship existed between the Schwendimans and Chief Industries. Chief Industries failed to receive payment for the materials from W & W and filed and recorded a notice of claim of lien within the statutory time limitations in the amount of $28,000.
That notice of claim of lien recited that it had furnished materials “to be used in the construction of a building or structure situ
That this lien is claimed against the above described building together with the portion of the above described lot on which said building is constructed or situated, together with a convenient space about the same, or so much as may be required for convenient use and occupation thereof, to be determined by the Court on rendering judgment. (Emphasis supplied.)
Thereafter Chief Industries commenced this action by filing a complaint which sought not only foreclosure against the legally described premises, but also against the building supplies and materials. The Schwendimans sought summary judgment which was supported by an affidavit reciting most of the above noted facts and which also revealed that • several buildings were situated on the land described in the notice of claim of lien, none of which had any relationship to the contract between Schwendiman and W & W. Following hearing thereon, the court held that the Schwendimans were entitled to summary judgment as a matter of law since a materialman’s lien may not be foreclosed when the materials were not incorporated in a structure located on the land.
On appeal Chief Industries asserts: first, that the district court erred in holding that a materialman’s lien may not be sustained where a construction project is abandoned after delivery of materials but before actual construction of any building or structure; second, that the descriptions contained in the notice of claim of lien were sufficient to give Chief Industries a lien on the materials furnished and on the land upon which the building was to have been constructed.
In Idaho materialman’s liens are to be liberally construed so as to effect their objects and to promote justice. Pierson v. Sewell,
Although Chief Industries’ notice of claim of lien mentions the materials supplied in general terms, at no point does it specifically claim a lien against the materials or describe them adequately for identification and, therefore, no lien may be sustained against the materials. While the complaint does assert a right to foreclose on the materials, such does not rectify the deficiencies of the notice of claim of lien since a defective claim of lien may not be amended after the statutory period for filing the claim has expired. Ross v. Olson, supra.
The notice of claim of lien created no claim against the building for the obvious reason that no building then or thereafter existed. Lien statutes operate in rem, Pierson v. Sewell, supra; Valley Lumber & Mfg. Co. v. Nickerson,
The notice of claim of lien filed by Chief Industries describes some 160 acres of the Schwendimans’ property. Under the facts presented here, that notice of claim is insufficient to support the lien sought to be foreclosed by plaintiffs-appellants. I.C. § 45-505, provides:
. The land upon which or in connection with which any professional serv*686 ices are performed or any building, improvement or structure is constructed, together with a convenient space about the same, or so much as may be required for the convenient use and occupation thereof, to be determined by the court on rendering judgment, is also subject to the lien .
It is not necessary that the lien claimant allege the amount of land required for the use of a building since the statute imposes the duty upon the court to ascertain the amount of land. Dybvig v. Willis,
The area of land which is subject to the lien in a given case is largely dependent upon the character of the improvement. Durfee v. Parker,
An additional, if not overriding, reason for failure of the lien here is the lack of incorporation of the building materials into a building or structure.
I.C. § 45-501 grants a right of lien to a materialman or laborer against a building, structure or other improvement.
Idaho’s materialmen’s lien statutes appear to have been adopted from those of California. Hendrix v. Gold Ridge Mines, Inc.,
As stated in Chamberlain v. City of Lewiston,
Appellant argues a contrary result based on the theories expounded in Chamberlain v. City of Lewiston, supra, and Idaho Lumber & Hardware Co. v. DiGiacomo,
Notes
. 45-501. Right to lien. — Every person performing labor upon, or furnishing materials to be used in the construction, alteration or repair of any mining claim, building, wharf, bridge, ditch, dike, flume, tunnel, fence, machinery, railroad, wagon road, aqueduct to create hydraulic power, or any other structure, or who grades, fills in, levels, surfaces or otherwise improves any land, or who performs labor in any mine or mining claim, and every professional engineer or licensed surveyor under contract who prepares or furnishes designs, plans, plats, maps, specifications, drawings, surveys, estimates of cost, on site observation or supervision, or who renders any other professional service whatsoever for which he is legally authorized to perform in connection with any land or building development or improvement, or to establish boundaries, has a lien upon the same for the work or labor done or professional services or materials furnished, whether done or furnished at the instance of the owner of the building or other improvement or his agent; and every contractor, subcontractor, architect, builder or any person having charge of any mining claim, or of the construction, alteration or repair, either in whole or in part, of any building or other improvement, as aforesaid, shall be held to be the agent of the owner for the purpose of this chapter: provided, that the lessee or lessees of any mining claim shall not be considered as the agent or agents of the owner under the provisions of this chapter.
. 45-505. Land subject to lien. — The land upon which or in connection with which any professional services are performed or any building, improvement or structure is constructed, together with a convenient space about the same, or so much as may be required for the convenient use and occupation thereof, to be determined by the court on rendering judgment, is also subject to the lien, if, at the commencement of the furnishing of professional services or other work or of the furnishing of the material for the same, the land belonged to
Concurrence Opinion
specially concurring.
I do not disagree with the Court’s conclusion that the description of materials was insufficient. Ross v. Olson,
I do not agree with the statement that “there must be a res to which the lien may attach,” because it is my opinion that I.C. § 45-501 as written can and should be read as allowing a materialman, whose materials have been furnished to be used (but which are not used) a lien on those materials:
Every person . . . furnishing materials to be used in the construction . of any . . . building . . . has a lien upon the same for the . materials furnished .
I.C. § 45-501 (emphasis added.) The language of I.C. § 45-507 buttresses a construction that the lien may be claimed and foreclosed against the materials alone, if the materialman files for record
a claim containing a statement of his demand, after deducting all just credits and offsets, with the name of the owner, or reputed owner, if known, and also the name of the person by whom he was employed or to whom he furnished the materials, and also a description of the property to be charged with the lien, sufficient for identification .
It is only where the claimant’s materials have actually gone into the building that the lien can also attach to the real property upon which the building has been constructed. I.C. § 45-505.
