The interlocutory appeals subject of the motion before us arise from conjoined multi-party actions in the United States District Court for the Southern District of New York (Preska, C.J.). The actions arise from a March 8, 2005, maritime disaster (the “Casualty”), during which the M/V Rickmers Genoa vessel (the “Rickmers” or “Rickmers Genoa”) collided with another vessel, the MW Sun Cross, in the Yellow Sea. The Rickmers Genoa sustained flooding in one of her cargo holds, and a few hours later, an explosion and a fire occurred in the No. 1 cargo hold of the Rickmers Genoa, resulting in the loss of cargo and a life.
Owners and subrogated insurers of certain cargoes (the “Cargo Interests”) that had been destroyed during the Rickmers Genoa incident filed four individual admiralty actions in the Southern District, seeking to recover for damage to the cargo in addition to amounts that were paid in salvage, against, inter alia, the (1) entities that owned and chartered the Rickmers Genoa on the date of the maritime casualty, defendants and third-party plaintiffs-appellants, Genoa Sehiffahrtsges mbH & Cie. KG, Genoa Navigation Company Ltd., and Rickmers-Linie GmbH & Cie. KG (the “Rickmers Interests”); (2) Rickmers Genoa; and (3) defendants-third-party defendants-cross defendants-cross claimants-counter claimants-appellees ESM Group Inc. (“ESM Group”) and ESM (Tianjin) Co., Ltd. (“ESMT”) (collectively, the “ESM Parties”). The ESM Parties were sued in their capacities as the manufacturer, shipper, and/or owner of the cargo (the “ESM Group Cargo”) that is believed to have caused the explosion in the No. 1 cargo hold. Among the Cargo Interests were plaintiffs-appellants Chem One, Ltd., et al. (the “Chem One Plaintiffs” or “Chem One”), 1 the owners (or their subrogated underwriters) of a portion of the cargoes carried aboard the Rickmers Genoa. The *630 Chem One Plaintiffs predicated their claims on theories of common law negligence and common law strict liability; the Carriage of Goods by Sea Act (“COGSA”), ch. 229, 49 Stat. 1207 (Apr. 16, 1936), 46 U.S.C. App’x § 1300-15 (re-codified at 46 U.S.C. § 30701 Notes, pursuant to Pub.L. 109-304,120 Stat. 1485 (Oct. 6, 2006)); and breach of contract.
In turn, the Rickmers Interests filed a third-party action asserting liability on the part of the ESM Parties as manufacturer, shipper, and/or owner of the ESM Group Cargo. The Rickmers Interests predicated their claims on theories that included strict liability failure to warn; negligent failure to warn; breach of contract; breach of warranty; negligent misrepresentation; indemnity; and detrimental reliance. They sought to recover damages in compensation for their losses, along with costs and disbursements, in the total amount of $40 million.
On November 8, 2007, the ESM Group filed a motion for summary judgment “seeking the dismissal of all claims asserted against it in the[ ] conjoined] maritime actions arising from the collision between the vessels Rickmers Genoa and the Sun Cross in the Yellow Sea on March 8, 2005.” By Order dated March 31, 2009, the District Court denied in part and granted in part the ESM Group’s motion for summary judgment, dismissing some of the direct claims against it to the extent that they were predicated on theories of (1) common law negligence; (2) common law strict liability; (3) COGSA; and (4) breach of contract.
In re M/V Rickmers Genoa Litig.,
On April 16, 2010, the ESM Parties filed a motion for summary judgment seeking dismissal of all remaining direct claims and third-party claims alleged against them. By Order dated November 4, 2010, the District Court granted in its entirety the motion for summary judgment and dismissed the remaining claims to the extent that they were predicated on theories of (1) strict liability; (2) negligent failure to warn; (3) breach of contract; and (4) detrimental reliance on a letter of indemnity.
In re M/V Rickmers Genoa Litig.,
The Chem One Plaintiffs’ Notice of Appeal, filed December 6, 2010, in the District Court, appealed both from the District Court’s March 31, 2009, Order and the court’s November 4, 2010, Order. In their capacity as third-party plaintiffs-appellants, the Rickmers Interests filed Notices of Appeal appealing from the Order entered November 4, 2010.
In the motion before us, dated January 4, 2011, the ESM Parties moved to dismiss all of the captioned interlocutory appeals as premature, or, in the alternative, to consolidate the captioned appeals. The ESM Parties argue that the March 31, 2009, and November 4, 2010, decisions of the District Court, which form the basis of these interlocutory appeals, do not dispose of all the claims in the underlying multiparty litigation and therefore are not eligible for appeal pursuant to Federal Rule of Civil Procedure 54(b). The ESM Parties *631 also argue that because both the ESM Group and ESMT alleged counterclaims and cross-claims in the underlying multiparty litigation, which remain pending in the District Court, there is no basis for interlocutory maritime jurisdiction pursuant to 28 U.S.C. § 1292(a)(3), which provides us with jurisdiction over “[ijnterlocutory decrees of such district courts or the judges thereof determining the rights and liabilities of the parties to admiralty cases in which appeals from final decrees are allowed.”
For the reasons that follow, we deny the ESM Parties’ motion to dismiss the captioned appeals and grant the motion insofar as it seeks to consolidate the captioned appeals.
BACKGROUND
The following account of the facts is derived from the District Court’s descriptions as set forth in its decisions of March 31, 2009, and November 4, 2010.
In re M/V Rickmers Genoa Litig.,
1. Events Leading up to the M/V Rickmers Casualty
Defendant-appellee ESM Group is a limited liability corporation organized under the laws of Delaware and registered to do business in the State of New York. Id. at 60. Prior to 2005, ESM Group was affiliated with a group of related companies consisting of ESM II Inc., ESM II L.P., and ESM Manufacturing, L.P. 2 The ESM companies have or have had plants in several locations around the United States and abroad. The ESM companies produce, inter alia, a family of magnesium desulphurization reagent products, including a reagent product designated “SS-89.” Id.
SS-89 is “[u]sed as a desulphurizing reagent in steelmaking ... [and] is designed to be injected into molten iron ore to remove sulphur and make the steel less brittle. Because it removes sulphur and consists of approximately 89% magnesium, it is regularly identified under the English language trade name ‘Super-Sul Mg-89.’ ” Id. Magnesium-based products liberate hydrogen gas when they come into contact with water, especially sea or salt water. Id. Hydrogen gas is flammable and susceptible to exploding. “According to a Material Safety Data Sheet (‘MSDS’) prepared by ESM Manufacturing L.P., SS-89 poses unusual fire and explosion hazards and should be kept dry and away from water and moisture.” Id. (internal quotation marks omitted).
In 1996, ESM Group formed a wholly-owned subsidiary, defendant-appellee ESM (Tianjin) Co., Ltd. (“ESMT”) in Tianjin, China. ESMT is a limited liability corporation organized under the laws of the People’s Republic of China. ESM Group allegedly formed ESMT to save production costs, obtain lower prices for materials previously imported by ESM Group, and avoid United States’ anti-dumping regulations concerning the manufacture of SS-89. ESM Group established the ESMT plant, trained ESMT personnel, *632 transferred equipment from United States sites to the ESMT plant, and provided ESMT with the formula for SS-89. Id. ESM Group also brought ESMT’s engineers and plant manager to the United States for technical and corporate training. ESM Group’s CEO became President of ESMT. ESMT’s Board of Directors included, at times exclusively, ESM Group employees. ESM Group directly paid ESMT’s raw materials suppliers. ESM Group executives regularly visited the ESMT plant to monitor its operations, manufacturing, and shipping procedures. Id. at 61.
When ESM Group desired a shipment of a magnesium desulphurization reagent, such as SS-89, from ESMT, ESM Group would send ESMT a Purchased Material Service Specification outlining the chemical and physical make-up of the desired product. Aside from these purchase orders, ESM Group and the related United States companies corresponded with ESMT managers about conforming the chemical composition of SS-89 to ESM Group’s requirements. Id.
Sometime in 2000, ESM Group created and provided ESMT with a draft MSDS for the SS-89 product. Although ESM Group alleges that it “did not get involved in providing recommendations to [ESMT] regarding safety measures in the production, storage or transportation of products which [ESMT] produces,” ESM Group, acting through its predecessor ESM II, directed ESMT to include its own MSDS for shipments of SS-89 and requested test data on the product from ESMT before shipments were to be made. Id. ESMT created its own MSDS for magnesium granules but apparently never created an MSDS for SS-89. ESMT’s plant manager acknowledged that ESMT would have distributed an MSDS for SS-89 upon ESM Group’s instruction to do so. Id.
In 2005, all of ESMT’s production of SS-89 was sold to ESM Group, and ESM Group did not allow ESMT to sell SS-89 to other buyers. Of the other products that ESMT produced, only half were sold to buyers other than ESM Group. As such, 85% of ESMT total production was sold or supplied to ESM Group. ESMT’s net profits in 2004 and 2005 were $10,000 and $45,000, respectively. ESMT did not report the payments ESM Group made to ESMT’s raw material suppliers as taxable income. Id.
On or about January 25, 2005, ESM Group sent ESMT a purchase order for 900 metric tons of SS-89, “C.I.F. Baltimore.” 3 Id. ESMT then arranged for the SS-89 to be shipped from the ESMT Tianjin plant to the United States aboard the Rickmers. ESMT contracted with defendant-third-party defendant Pudong Trans U.S.A., Inc. (“Pudong” or “Pudong Trans USA”), a Non-Vessel Owning Common Carrier (“NVOCC”), to transport the SS-89 from the Tianjin plant to port in Xingang, China, where the Rickmers was docked. Id. at 62.
On or about March 3, 2005, Pudong issued ESMT a bill of lading 4 identifying *633 ESMT as the shipper and identifying “To Order of Shipper” as the consignee. Id. Pudong then contracted with the Rickmers Interests to have the Rickmers carry the SS-89 from China to Camden, New Jersey. Sometime thereafter, the Rickmers Interests issued a bill of lading identifying Pudong as the shipper and identifying U.S. Shipping, Inc. (“U.S. Shipping”) as the consignee. U.S. Shipping was to act as an intermediary NVOCC and releasing agent in the United States, “apparently tasked to transport the SS-89 from Camden to Baltimore.” Id. The District Court found that there was “no evidence that ESMT informed any of these entities about the risks associated with transporting SS-89 by sea” and that “ESMT also did not provide an MSDS” on SS-89. Id.
On or about March 2, 2005, ESMT placed 600 metric tons of SS-89, of the 900 total metric tons of SS-89 ordered, into sacks. ESMT tested the sacks to ensure that they complied with U.S. Hazardous Material Regulations “dangerous when wet” criteria. Based on fresh-water testing, the results were normal and within United States regulatory standards. Id. ESMT placed the packages into containers. Then, Pudong picked up the containers and delivered them to the Xingang port that same day. On or about March 8, 2005, the containers were loaded aboard the Rickmers into Hold No. 1. Id.
On March 8, 2005, after having departed from the Xingang port and apparently stopping at other Chinese ports, the Rickmers collided with the M/V Sun Cross in foggy weather in the Yellow Sea.
Id.
The Rickmers suffered damage to her forward double-hull plating, and flooding occurred in Hold No. 1, where the SS-89 was being stored. Approximately four hours after the collision, an explosion occurred in Hold No. 1, and a fire ensued. The containers of SS-89 were completely destroyed.
Id.
The Chief Officer of the Rickmers died in the explosion.
In re M/V Rickmers Genoa Litig.,
II. Proceedings in the District Court
In the wake of the disaster, the Cargo Interests — i.e., the owners and subrogated insurers of cargoes, other than the ESM Group Cargo, that had been destroyed during the Rickmers Casualty — filed four individual admiralty actions in the District Court, pursuant to Rule 9(h) of the Federal Rules of Civil Procedure, seeking damages for their losses. Specifically, (1) the Chem One Plaintiffs; (2) plaintiff Shandong Industrial, Inc.; 5 (3) plaintiff St. Paul Travelers; and (4) plaintiff Atlantic Coast Yacht Sales, Inc. (collectively, the “Cargo Interests”), each filed complaints against, inter alia, (1) the Rickmers Genoa and the M/V Sun Cross vessel; (2) the Rickmers Interests; (3) the ESM Group and ESMT; and (4) defendant Pudong Trans USA. The foregoing actions were *634 joined for consideration in the District Court.
On February 17, 2006, the ESM Group filed (1) counterclaims and cross-claims against the Rickmers Interests for failing properly to handle and carry the ESM Group Cargo and for breaching their duty of care and thereby allegedly causing the destruction of that cargo; (2) cross-claims against Pudong Trans USA for breaching its duty of care as the common carrier of the cargo; and (8) counterclaims against the Chem One Plaintiffs for failing to warn the parties about the “dangerous” nature of unspecified chemicals contained in the Chem One Plaintiffs' cargo onboard the Rickmers vessel. See Counterclaims and Cross-Claims of ESM Group Inc., Chem One, Ltd. v. M/V Rickmers Genoa et al., No. 05-cv-4261 (LAP) (S.D.N.Y. Feb. 17, 2006), ECF No. 19.
On April 25, 2006, the Rickmers Interests filed an amended third-party complaint against (1) the ESM Group and ESMT; (2) Pudong Trans USA; and (3) U.S. Shipping. 6 In that complaint, the Rickmers Interests alleged, inter alia, that the ESM Parties had failed to provide any warning as to the dangerous nature of the ESM Group Cargo.
On November 22, 2006, ESMT counterclaimed against the Chem One Plaintiffs to recover for the loss of the ESM Group Cargo onboard the Rickmers Genoa. In the counterclaims, ESMT also sought contribution or indemnity from the Chem One Plaintiffs to the extent that ESMT might be hable for any judgment against it.
See generally In re M/V Rickmers Genoa Litig.,
Nos. 05-civ4261 (LAP); 05-civ-6226 (LAP); 05-civ-8841 (LAP); 05-civ-9472 (LAP),
In a separate filing, also on November 22, 2006, ESMT alleged cross-claims against (1) defendants-third-party plaintiffs Rickmers Interests for contribution, indemnity, and/or recoupment “for all or part of any liability or judgment against [ESMT], and/or any related payment by [ESMT] in relation to claims arising from the Casualty”; and (2) defendant-third-party defendant Pudong Trans USA, as NVOCC, for contribution, indemnity, and/or recoupment from “for all or part of any liability or judgment against [ESMT], and/or any related payment by ESM Group in relation to the claims arising from the Casualty.” Cross-Claims of ESM Tianjin Against the Rickmers Interests and Pudong Trans USA, Chem One, Ltd. v. M/V Rickmers Genoa et al., No. 05-cv-4261 (LAP) (S.D.N.Y Nov. 22, 2006), ECF No. 63.
A year later, in November 2007, the ESM Group moved for summary judg
*635
ment, seeking to dismiss all of the claims asserted against it by the Rickmers Interests and the Chem One Plaintiffs. The claims against the ESM Group were predicated on theories of: (1) common law negligence (general negligence and failure to warn); (2) common law strict liability; (B) COGSA; (4) breach of contract; and (5) agency and veil piercing. In an Order dated March 31, 2009, the District Court granted the motion in part and denied the motion in part.
In re M/V Rickmers Genoa Litig.,
The District Court permitted the claims against ESM Group to proceed to the extent that the ESM Group might be liable for the acts of ESMT. Id. at 73. Specifically, the court found, with respect to the claims predicated on theories of federal maritime common law of agency and veil piercing, that the evidence was “sufficient to create a triable issue as to whether veil piercing is warranted,” id. at 76, i.e., whether “ESM Group and ESMT were sufficiently related to hold each liable for the other’s torts, contracts, and statutory obligations,” id. at 73. The court found that the “evidence tend[ed] to show that ESMT was transacting ESM Group’s business rather than its own business. Taking this evidence as a whole, it is sufficient to create a triable issue as to whether veil piercing is warranted in this case.” Id. at 76.
On April 16, 2010, the ESM Parties collectively moved for summary judgment to dismiss all the remaining claims alleged against them. On November 4, 2010, the District Court granted the ESM Parties’ motion for summary judgment and dismissed all remaining claims alleged against them by the Rickmers Interests and Cargo Interests. The court started its analysis with the four claims alleged by third-party plaintiffs Rickmers Interests. First, the court rejected the strict liability claims, alleged pursuant to § 4(6) of COGSA, 46 U.S.C. § 30701 Note § 4(6) (2006), against the ESM Parties because the Rickmers Interests “either actually or constructively knew that the SS-89 cargo had certain dangerous propensities and nevertheless exposed the cargo to the condition that activates those dangerous propensities.”
See In re M/V Rickmers Genoa Litig.,
Third, as to the Rickmers Interests’ claim that ESMT breached both (1) a bill of lading issued by Rickmers to Pudong Trans USA and (2) a bill of lading issued by Pudong Trans USA to ESMT, the court dismissed the breach of contract claim because (1) ESMT was generally “not bound by the Rickmers-Pudong bill of lading ... [as] Pudong Trans [USA] was the shipper and Rickmers was the carrier,” id., and (2) the Rickmers Interests had “no standing to enforce” the Pudong-ESMT bill of lading, to which the Rickmers Interests were non-parties, id. at 392. Fourth, the court rejected the Rickmers Interests’ claim of detrimental reliance based on a February 22, 2005, letter of indemnity drafted by ESMT, because the court found that the Rickmers Interests were unable to establish that they had relied to their detriment on any “letter[ ] of indemnity when [they] accepted the SS-89” on the Rickmers Genoa. Id. at 393.
The District Court next addressed the strict liability and negligent-failure-to-warn claims alleged by the Cargo Interests against the ESM Parties, including ESMT, and ultimately dismissed those claims. Id. at 393-95. The court determined that these claims should be dismissed because the evidence revealed that the Cargo Interests knew or should have known of the hazardous nature and dangerous propensities of the ESM Group Cargo and that this knowledge or constructive knowledge therefore barred the claims. See Id. at 386-91, 395. Finally, because the District Court dismissed all claims against ESMT, the court dismissed the remaining causes of action that had sought to hold ESM Group accountable for ESMT’s actions and that the court had originally allowed to proceed in its March 31, 2009 Order. Id. at 393 n. 12. The court directed that “[t]he remaining parties sh[ould] confer and inform the [c]ourt by [mid-November 2010] how they propose to proceed.” Id. at 395.
On December 3, 2010, the Rickmers Interests filed timely notices of appeal from the District Court’s interlocutory November 4, 2010, Order, resulting in the opening of docket numbers 10-4934-cv, 10-4938-cv, and 10^4961-cv in this Court. On December 6, 2010, the Chem One Plaintiffs filed a timely notice of appeal from both the District Court’s November 4, 2010, and March 31, 2009, decisions, 7 resulting in the opening of docket number 10-4965-cv in this Court. Following the District Court’s November 4, 2010, Order, the Rickmers Interests, by endorsed letter dated November 17, 2010, “on behalf of all the parties,” informed the court that the loss-of-cargo claims asserted against them by the Chem One Plaintiffs, Atlantic Coast Yacht Sales, and ESM Group remained to be adjudicated.
As to the remaining claims for loss of cargo asserted against them, the Rickmers Interests, on February 18, 2011, moved for partial summary judgment with respect to the interpretation of the terms in their bill of lading concerning the issue of the limitation of liability of a carrier engaged to transport goods. The Rickmers Interests contended that under their bill of lading and COGSA, a package limit of $500 per *637 package should be applied to any claim for damage or loss of cargo transported pursuant to the Rickmers Interests’ bill of lading between Pudong Trans USA and the Rickmers Interests. See generally COGSA § 4(5), 46 U.S.C. § 30701 Note. Sec. 4(5) (“Neither the carrier nor the ship shall in any event be or become liable for any loss or damage to or in connection with the transportation of goods in an amount exceeding $500 per package....”).
On March 4, 2011, the ESM Group filed a memorandum of law in opposition to the Rickmers Interests’ February 18, 2011, motion for partial summary judgment and in support of ESM Group’s cross-motion for summary judgment as to its counterclaims and cross-claims against the Rickmers Interests. In its opposition and cross-motion for partial summary judgment, the ESM Group opposed the Rickmers Interests’ motion seeking to limit the Rickmers Interests’ liability to $500 per package and sought to pursue their claims in full. The ESM Group argued that under the plain language of the Rickmers Interests’ bill of lading, German law should be applied, and, therefore, with regard to ESM Group’s counterclaims and cross-claims against the Rickmers Interests, that the ESM Group should be entitled to recover its actual loss of the ESM Group Cargo and that it was not limited to the $500 per package cap under COGSA.
By Order, dated May 26, 2011, the District Court granted ESM Group’s cross-motion for summary judgment and denied the Rickmers Interests’ motion for partial summary judgment, thereby allowing the ESM Group to proceed with their counterclaims and cross-claims against the Rickmers Interests.
In re M/V Rickmers Genoa Litig.,
Docket Nos. 05-civ-4261 (LAP); 05-civ-6226 (LAP); 05-civ-8841 (LAP); 05-civ-9472 (LAP),
On June 9, 2011, the Rickmers Interests moved the District Court for reconsideration of its May 26, 2011, Order, and the ESM Group opposed that motion by filing a Memorandum of Law in support of that opposition on June 23, 2011. On July 8, 2011, the District Court denied the Rickmers Interests’ motion for reconsideration, finding that they “rehash[ed] the arguments made in the summary judgment papers.” Order Denying Motion for Reconsideration, In re M/V Rickmers Genoa Litig., No. 05-CV-4261 (S.D.N.Y. July 8, 2011), ECF No. 222. The court also denied the Rickmers Interests’ request for certification of an interlocutory appeal from the May 26, 2011, Order. Id.
III. Proceedings in this Court
By motion dated January 4, 2011, the ESM Parties moved to dismiss all appeals in this Court for lack of jurisdiction on the grounds that the appealed-from orders are non-final and this Court lacks jurisdiction under the admiralty interlocutory provision set forth in 28 U.S.C. § 1292(a)(3) because claims remain in the District Court. In their motion, the ESM Parties also moved this Court to consolidate the *638 appeals in the event that their motion to dismiss is denied. The ESM Parties argue that Section 1292(a)(3) should be construed to require that all of the rights and liabilities of all parties must be adjudicated by the District Court to provide this Court with appellate jurisdiction over these interlocutory appeals. The Rickmers Interests and the Chem One Plaintiffs oppose the ESM Parties’ motion to dismiss, contending that in this case, we have interlocutory jurisdiction under Section 1292(a)(3) because the District Court has resolved all claims against the ESM Parties. Rickmers Interests and the Chem One Plaintiffs do not oppose consolidation of the present appeals.
ANALYSIS
I. Interlocutory Admiralty Jurisdiction
“As a general rule, we lack jurisdiction to hear an appeal ‘unless the decision is, or is embodied in, an order or judgment that is “final” within the meaning of 28 U.S.C. § 1291.’ ”
Swede v. Rochester Carpenters Pension Fund,
“The Section 1292(a)(3) exception to the final judgment rule has its origins in the once common admiralty practice of referring the determination of damages to a master or commissioner after resolving the issue of liability.”
Becker,
It is undisputed that the present appeals arose under the District Court’s
*639
admiralty jurisdiction and that the orders from which the parties have appealed are interlocutory in nature.
See Wingerter,
In
Thypin Steel,
we noted and seemingly rejected the Eleventh Circuit’s conclusion in
Bradford Marine, Inc. v. M/V Sea Falcon,
Notwithstanding the foregoing, interpretation of the scope of Section 1292(a)(3) was not necessary in
Thypin Steel
because in that case, we ultimately held that there was no appellate jurisdiction under Section 1292(a)(3) over a cross-appeal seeking interlocutory review of a district court’s dismissal of one defendant for lack of
personal jurisdiction,
reasoning that the dismissal “only affected how and where [the defendant’s rights would be determined
*640
but did not conclusively resolve the parties’ substantive rights or liabilities or the merits of the underlying controversy.”
Thypin Steel,
Accordingly, we reject the contention of the ESM Parties that language in
Thypin Steel
somehow limits Section 1292(a)(3) to interlocutory appeals only from orders that dispose of all of the rights and liabilities asserted among all of the parties.
Thypin Steel’s
discussion of the scope of Section 1292(a)(3) was dictum. It was not necessary in that case to suggest that Section 1292(a)(3) might be limited to dispositions of all the rights and all of the liabilities asserted among all the parties when the cross-appeal at issue in
Thypin Steel
did not fully resolve the liabilities of even a single party.
See Alsol v. Mukasey,
In our view
Thypin
Steel’s dictum is at odds with the plain language of Section 1292(a)(3), which “does not say that
all
rights and liabilities of [all] the parties must be decided before an appeal can be taken,”
Deering v. Nat’l Maint. & Repair, Inc.,
The fact that the ESM Parties have their own counterclaims and cross-claims pending in the District Court does not affect whether we may exercise appellate jurisdiction under Section 1292(a)(3). In
Becker v. Poling Transportation Co.,
we held that we had jurisdiction under Section 1292(a)(3) over an appeal from a magistrate judge’s determination that the jury had found a purchaser vicariously liable for injuries sustained by two seamen, even though the purchaser’s cross-claim for contribution against a third-party defendant remained pending, “because its liability to [the seamen] ... ha[d] been determined and [was] unaffected by the cross-claim or the indemnification clause in [a] ... settlement.”
In this case, the District Court’s adjudication of liability as to the ESM Parties was resolved in the court’s decisions of March 31, 2009, and November 4, 2010, in which the court dismissed all direct and third-party claims against the ESM Par
*642
ties. Those determinations are “unaffected by” any remaining counterclaims or cross-claims that the ESM Parties have alleged.
See Becker,
The ESM Parties’ contention that an interlocutory appeal “would likely result in disruptive appellate review” simply has no basis in the record or fact. The parties cannot dispute that “there is nothing left to litigate at the District Court level with respect to the claims ... against ESM Group and ESM Tianjin.” Thus, given that the District Court has determined conclusively all of the claims against the ESM Parties, and that decision is unaffected by any remaining claims, we properly may exercise appellate jurisdiction over the present appeals under Section 1292(a)(3). Delaying appeal merely because a “final judgment” as to all of the claims against all of the parties has not been issued would defeat the interlocutory nature of Section 1292(a)(3) and effectively render the statute a nullity in the modern era of litigation in which admiralty suits frequently involve multiple parties and claims.
II. Consolidation
“When the parties have filed separate timely notices of appeal, the appeals may be joined or consolidated by” this Court. Fed. R.App. P. 3(b)(2). We have explained that, “[i]n assessing whether consolidation is appropriate in given circumstances,” a court “should consider both equity and judicial economy.”
Devlin v. Transp. Commc’ns Int’l Union,
III. Conclusion
Upon due consideration, it is hereby ORDERED that the motion to dismiss is DENIED,
Becker,
Notes
. The Chem One Plaintiffs include the following entities: Chem One Ltd., Commercial Metals Company, A.H.A. International Co., IKE Trading Co., Ltd., Hunter Douglas Metals Inc., National Oilwell L.P., Texas Wyoming Drilling, Inc., Graphite Electrodes Sales Company Inc., The Babcok & Wilcox Company, WestcoSystems, Inc., Toray Engineering Co., Ltd., The Crispin Company, Itochu Building Products Co., Inc., Bluelinx Corporation, Kurt Orban Partners LLC, BSTC Group Inc., Foster Wheeler North America Corp., Wego Chemical & Mineral Corp., Suewon Poongryuk Machinery Co. Ltd., General Electric Company, and Wintersun Group (USA).
. On December 31, 2005, ESM Group became the corporate successor in interest of ESM II Inc. and ESM II L.P., both of which ceased to exist upon their merger into ESM Group.
. C.I.F., or "Cost, Insurance, and Freight,” is a "commonly used international commercial term meaning ‘that the seller delivers when the goods pass the ship’s rail in the port of shipment. The seller must pay the costs and freight necessary to bring the goods to the named port of destination!; however,] the risk of loss of or damage to the goods, as well as any additional costs due to events occurring after the time of delivery, are transferred from the seller to the buyer.’ ”
In re M/V Rickmers Genoa Litig.,
. A bill of lading is generally "[a] document acknowledging the receipt of goods by a carrier or by the shipper’s agent and the contract *633 for the transportation of those goods; a document that indicates the receipt of goods for shipment and that is issued by a person engaged in the business of transporting or forwarding goods.” Black’s Law Dictionary, at 188 (9th ed. 2009).
. In the case of Shandong Industrial, Inc. v. M/V Rickmers Genoa, et at, No. 05-cv-6226 (LAP), a Stipulation and Order of Dismissal was entered April 29, 2010, pursuant to a settlement agreement between the parties, discontinuing the case in its entirety, including all counterclaims, with prejudice and without costs to any party. Stipulation and Order of Dismissal, Shandong Industrial, Inc. v. M/V Rickmers Genoa, et at, No. 05-cv-6226 (LAP) (S.D.N.Y. April 29, 2010), EOF No. 96.
. By Stipulation and Order, dated May 22, 2009, and signed by the District Court June 3, 2009, any and all claims, cross-claims, and counterclaims "by and between U.S. Shipping and the undersigned parties” were dismissed without prejudice and without costs. Stipulation and Order to Dismiss U.S. Shipping Without Prejudice, Chem One, Ltd. v. M/V Rickmers Genoa et al., No. 05-cv-4261 (LAP) (S.D.N.Y. June 4, 2009), ECF No. 141.
. Because the last day to file a notice of appeal fell on a Saturday, the last day to file was extended until Monday, December 6, 2010. See Fed. R.App. P. 26(a)(1)(C) and (3).
. 28 U.S.C. § 1292(a)(3) provides in relevant part:
(a) Except as provided in subsections (c) and (d) of this section, the courts of appeals shall have jurisdiction of appeals from ... (3) Interlocutory decrees of such district courts or the judges thereof determining the rights and liabilities of the parties to admiralty cases in which appeals from final decrees are allowed.
. None of the other admiralty cases cited by the ESM Parties involving dismissals of appeals by this Court help their argument. Unlike the cases at bar, in which the District Court has adjudicated the merits of all liability claims against the ESM Parties, those admiralty cases involved attempted appeals from: the denial of a motion to dismiss,
see Blue Water Yacht Club Ass’n v. N.H. Ins. Co.,
. The Ninth Circuit has taken a particularly expansive approach with respect to Section 1292(a)(3), holding that a determination as to a party’s actual liability is not required before an appeal can be taken.
See Wallis v. Princess Cruises, Inc.,
