“There can be no implied contract where there is an express contract between the parties in reference to the same subject matter.” 1 Plaintiffs Charlotte Motor Speedway, Inc. and Charlotte Motor Speedway, LLC (“Speedway”) argue that they are entitled to implied-in-law indemnification from Defendant Tindall Corporation (“Tindall”) because their liability is derivative to Tindall’s negligence. Because Speedway and Tindall executed an express indemnification provision that, by its terms, does not cover the losses for which Speedway seeks indemnification, we affirm the trial court’s order of dismissal.
In May 1995, Speedway contracted with Tindall to construct a pedestrian walkway from the Charlotte Motor Speedway to the parking area. The construction contract included an indemnification clause, stating:
[Tindall] shall indemnify and save harmless [Speedway], but only for claims for damages to property and personal injuries, including death, during the performance of the work herein and on the premises of [Speedway] and resulting directly and solely from negligence of [Tindall’s] employees while engaged in such work.
At some point after execution, the words “but only” were stricken from the clause.
Construction of the walkway was completed in October 1995. However, the walkway collapsed in May 2000 during the Winston Cup NASCAR race. Thereafter, 103 of the pedestrians on the walkway brought actions against Speedway and Tindall in various state and federal courts. All North Carolina state court actions were consolidated on 20 September 2001.
In August 2002, Speedway and Tindall executed an Interim Funding Agreement agreeing to establish a trust fund with Anti-Hydro — the manufacturer of a product Tindall used to construct the walkway — for the payment of settlements. Under that agreement, Speedway and Tindall again agreed not to sue each other until the pedestrian litigation was resolved, and that all claims existing between them would be preserved.
On 28 August 2002, the trial court in one of the pedestrian lawsuits ruled that Speedway was liable to the pedestrians “for the acts and omissions of the defendant Tindall Corporation” on a theory of nondelegable duty. That ruling was later adopted and applied to all pending pedestrian lawsuits. A jury verdict in Cindy A. Taylor, et al. v. Charlotte Motor Speedway, 01-CVS-12107, determined liability between Speedway and Tindall as follows: 1) Speedway was not negligent; 2) Tindall’s negligence injured the plaintiffs; and 3) Speedway breached its Encroachment Agreement (to construct the walkway in accordance with state standards) with the N.C. Department of Transportation; plaintiffs were third party beneficiaries of the Encroachment Agreement and were injured by Speedway’s breach.
The last of the pedestrian lawsuits pending in North Carolina courts concluded on 27 June 2007 with our Supreme Court’s denial of a petition for discretionary review. However, two pedestrian cases, neither of which named Speedway as a defendant, remained pending in South Carolina.
On 17 July 2007, Speedway brought the instant action seeking indemnification from Tindall on theories of implied and express indemnification. In turn, Tindall moved to dismiss Speedway’s complaint under N.C. R. Civ. P. 12(b)(6). From the trial court’s order granting Tindall’s motion to dismiss, Speedway appeals arguing that the trial court erred: (I) by considering matters - beyond the allegations of its complaint, thereby converting Tindall’s motion to dismiss into a motion for summary judgment; (II) because neither the statute of limitations nor the statute of repose bars Speedway’s claims; and (III) because, as a matter of law, Speedway is entitled to implied-in-law indemnity.
I.
First, Speedway argues that the trial court impermissibly considered matters beyond its pleadings, in effect ruling on the merits of the claims and converting Tindall’s motion to dismiss into a motion for summary judgment. Tindall answers that the plain language in the trial court’s order indicates that it considered nothing beyond the pleadings, and that Speedway urged the trial court to go beyond the pleadings.
“A motion to dismiss for failure to state a claim is ‘converted to a Rule 56 motion for summary judgment when matters outside the pleadings are presented to and not excluded by the court.’ ”
King v. Cape Fear Mem’l Hosp., Inc.,
At the hearing on Tindall's motion to dismiss, the trial court heard arguments regarding factual evidence, rulings, and jury instructions in at least one of the underlying pedestrian suits. The parties also made arguments regarding the Interim Funding Agreement. The trial court’s order, however, includes only the following relevant language:
IT APPEARING to the Court, having reviewed the pleadings and the briefs submitted by the parties, and having heard the oral argument by counsel for the parties at the December 5, 2007 hearing, that the Complaint fails to state a claim upon which relief can .be granted and that the Motion to Dismiss therefore should be allowed pursuant to Rule 12(b)(6) ....
Thus, the trial court’s order indicates that it dismissed the complaint under N.C. R. Civ. P. 12(b)(6), and notably, does not mention any of the evidentiary matter appropriately considered on a motion for summary judgment. Moreover, nothing in the record establishes that the trial court considered matters beyond the pleadings. Because the record does not indicate that the trial court converted the motion to dismiss into a summary judgment motion, we reject this assignment of error.
II.
Speedway next argues that the statutes of limitation and repose do not bar its claims, and alternatively, that Tindall should be equitably estopped from asserting those defenses because it agreed to waive them in the Tolling Agreement and Interim Funding Agreement (collectively “Agreements”). In response, Tindall argues that Speedway’s action is time-barred, and that Speedway lost the benefit of the Agreements when it breached them by filing this suit before all underlying pedestrian suits concluded.
The statute of limitations period for an indemnity contract is three years. N.C. Gen. Stat. § 1-52(1) (2008). The applicable statute of repose provides that “[n]o action to recover damages based upon or arising out of the defective or unsafe condition of an improvement to real property shall be brought more than six years from the later of the specific last act or omission of the defendant giving rise to the cause of action or substantial completion of the improvement.” N.C. Gen. Stat. § l-50(a)(5)a (2008).
In this case, Tindall alleges that the statute of limitations bars Speedway’s claim for indemnification of any monies paid prior to three years before it filed its complaint. Speedway filed the complaint in this case on 17 July 2007. However, Tindall’s argument ignores the operation of the Tolling Agreement, which expressly remained effective “through and including January 1, 2006.” Because Speedway filed suit less than two years after the. Tolling Agreement expired, we hold that the statute of limitations does not bar this action, and Tindall’s argument must fail.
Likewise, the statute of repose does not bar this action. The Walkway was substantially completed on 9 October 1995; the parties executed the “Tolling Agreement” on 28 September 2001, within six years from substantial completion of the walkway. Although the Tolling Agreement expired on 1 January 2006 (and this action was not filed until more than one year later), the parties executed the Interim Funding Agreement on 8 August 2002, in which they agreed that they would not sue each other until all pedestrian claims were resolved. 2 The pedestrian lawsuits were still pending when Speedway filed the complaint in this case on 17 July 2007; thus the Interim Funding Agreement operated to toll the statute of repose through the filing of Speedway’s complaint.
III.
In its next assignment of error, Speedway argues that its liability is merely derivative to Tindall’s negligent construction of the walkway, and thus it is entitled to implied-in-law indemnity from Tindall. In response, Tindall argues that the express indemnification provision in the parties’ construction agreement precludes Speedway’s implied-in-law indemnity theory.
An implied-in-law contract for indemnification is generally based upon the doctrine of primary-secondary liability.
Greene v. Charlotte Chem. Labs., Inc.,
Here, Speedway and Tindall executed an express indemnification provision which, by its terms, covered only injuries “occurring during the performance of [Tindall’s] work” on the walkway. Moreover, Speedway was found not to be a tortfeasor in the trial court. Speedway’s liability was adjudicated as purely contractual— it breached a nondelegable duty and the Encroachment Agreement with the NCDOT, of which the injured pedestrians were third-party beneficiaries.
Nonetheless, Speedway attempts to overcome the express indemnification provision and its pure contractual liability by citing
Northeast Solite Corp. v. Unicon Concrete, LLC,
In this case, on the other hand, an express indemnification provision exists which does not cover injuries occurring after the walkway was completed. Furthermore, Speedway seeks indemnity for Tindall’s tortious construction of the walkway, but Speedway was not adjudicated a tortfeasor. Therefore,
In sum, we affirm the dismissal of Speedway’s complaint.
Affirmed.
Notes
.
Greene v. Charlotte Chem. Labs., Inc.,
. Tindall argues, on appeal, that this Court should not consider the Interim Funding Agreement because it does not appear on the face of the pleadings. In its Memorandum of Law Supporting its Motion Dismiss before the trial court, however, Tindall quoted extensively from the Interim Funding Agreement, and argued that Speedway was not entitled to its benefit because of a breach. Therefore, Tindall may
not argue for the exclusion of the Interim Funding Agreement in this appeal because “arguments of counsel relating to a motion to dismiss are not considered matters outside the pleadings.”
King,
. Tindall concedes that Speedway was not a named party to any outstanding cases when it filed this action.
