191 A.D. 365 | N.Y. App. Div. | 1920
The complaint demands judgment for $76,701.65 and interest from February 27,1914. The verdict directed was for $47,500. There are a number of items going to make up the amount of plaintiff’s claim, which were necessarily the subject of separate consideration and decision by the court. As. the verdict is much less than the amount demanded, it is impossible to determine which of the claims were allowed and which disallowed by the court, for there were no findings and no opinion. This information is buried in the general verdict, rendered by the court under a stipulation which made him the judge of both fact and law. Neither do we get the light that is usually afforded in a jury trial by the charge of the court. I think, therefore, that if we find a sufficient basis for the verdict in any of the claims, the judgment should be affirmed. I cannot agree with appellant’s counsel that the verdict “ embraces ’ within itself all the claims, reduced in amount.” I think rather the presumption must be indulged that the verdict directed by the court under such a stipulation is founded on those claims that we find supported by evidence sufficient to justify a finding in their favor. Any other course would lead to the conclusion that if a single unimportant claim is not established, the whole judgment, although abundantly supported by other well-established claims, must fall.
The amount of about $19,000 was unpaid on the purchase price. The contract required that the work should be fully completed and certified to by the architect and the president
The contract gave to the contractor the option of sheathing from the grade levels to the bottoms of the excavation, or of pitching back the banks at such an angle that the adjoining material could not under any condition fall into the excavation and sheathing from two feet above the base of the banks to the bottoms of the excavation, provided that the tops of the banks should in no case come within five feet of the property fine. The contractor chose the method of pitching back the banks. He was, therefore, required to see that the tops of the banks did not come within five feet of the property line, to sheath from two feet above the base of the banks to the bottoms of the excavation, and to keep the material from falling into the * excavation. During the progress of the work there were slides into the excavation, and on September 24,1912, a slide occurred which extended beyond the curb line of Flatbush avenue. The contract contained a provision that all. shoring, bracing, cribbing and the like, necessary or required, should be done in the most substantial manner, to protect adjoining property. The architect required the plaintiff, instead of using the method of pitching back the banks, to construct a system of trussing, sheathing and shoring. The plaintiff protested against this change of method, but yielded and did the work accordingly.
The doctrine that where the architect, representing the owner, requires the contractor to do work on a plausible but
The architect, against the protest of plaintiff, required him to pour the concrete continuously in a monolith, both in some of the foundation slabs and in the walls. The walls were to be forty feet high. The architect required him to pour twenty-seven feet continuously, then ten feet continuously, and then
The claim for the increased expense of pouring as a mono.lith seems, therefore, to fall within the doctrine of the Borough Const. Co. Case (supra). A finding for the plaintiff on this claim is warranted by the evidence and rules of law applicable thereto, and we must' assume that the court so found.
The evidence on the items of damage, already considered, warranted the verdict directed, and there is no necessity for prolonging the opinion by a discussion of the other items.
The judgment and order should be affirmed, with costs.
Present—Rich, Putnam, Blackmar, Kelly and Jaycox, JJ.
Judgment and order unanimously affirmed, with costs.