Opinion
Chаrles J. Rounds Co. (hereafter employer) appeals from the judgment of the trial court, which dismissed a complaint, charging breach of a collective bargaining agreement, on the grounds that the dispute which was the subject of the suit was covered by an arbitration clause in the agreement.
Employer is a general contractor operating in the Los Angeles area as a member of the Southern California Chapter of the Associаted General Contractors of America (hereafter AGC). The AGC entered into a collective bargaining agreement with defendant unions in 1962, effective *891 July 1962 through June 1965. The agreement included a “no-strike” clause and detailed provisions for the arbitration of disputes.
The employer discharged a union member on June 28, 1963. On July 2, 3 and 5, the unions struck the employer at a job site where work was being done under contract for the Los Angeles County Flood Control District. During this period, the unions filed a grievance according to the • requirements of the collective bargaining agreement. The disposition of this grievance does not appear in the record.
The employer filed a complaint against the unions seeking compensatory damages for breach of the “no-strike” clause in the agreement. In their answer, the unions alleged, as an affirmative defense, that whether the strike was in violation of the agreement was an issue within the scope of the arbitration clause and that the employer’s failure to arbitrate according to the agreement’s procedures was a bar to an action for damages. The unions’ motion for summary judgment on the same grounds was denied by the trial court.
Subsequently, the unions made three separate attempts to force the employer into arbitration over the strike. In January 1965, the unions filed an application in the same court wherein the employer’s suit was filed, for a stay of proceedings pending arbitration. This application was denied. In April 1965 the unions again moved for summary judgment in the trial court, and the motion was denied. Finally, the unions brought suit in federal district court in 1968 to compel arbitration. After the employer answered, pleading laches and the statute of limitations, the unions voluntarily withdrew the action.
The cause came to trial finally in 1969. By stipulatiоn, the parties agreed to try the special defense first. The trial court found that the arbitration procedure set up by the agreement was intended to cover all disputes, including whether the work stoppage in question was a violation of the “no-strike” clause. The trial court ruled that the employer’s suit was barred because it had failed to adhere to the requirements of the arbitration provisions of the agreement.
On appeal, the employer contends that the dispute is not covered by the arbitration clause of the agreement and, alternatively, that the appropriate remedy was not dismissal but a stay of the proceedings pending arbitration.
First, it is necessary to determine whether this dispute was arbitrable. To do so, we must interpret the language of the agreement according to the federal substantive law set down by the federal courts pursuant to section 301 оf the Labor Management Relations Act (29 U.S.C. § 185(a)
*892
(1964).) The body of federal substantive law is applicable to the employer in the instant case, because he was involved in activities which affect interstate commerce.
(Teamsters Union
v.
Lucas Flour Co.
(1962)
Federal policy favors the settlement of labor-management disputes by grievance and arbitration mechanisms; this has been expressed by Congress in section 203(d) of the Labor Management Relations Act: “Final adjustment by a method agreed upon by the parties is declared to be the desirable method for settlement of grievance disputes arising over the application or interpretation of an existing collective-bargaining agreement. . . .” (29 U.S.C. § 173(d) (1964) quoted in
Butchers’ Union Local 229
v.
Cudahy Packing Co., supra,
In the
Cudahy Packing Co.
case, we stated that “the function of a court in deciding whether a dispute is subject to arbitration ‘is confined to ascertaining whether the party seeking arbitration
is making a claim which on its face is governed by the contract.’
(Italics added.)
(United Steelworkers of America
v.
American Mfg. Co.
(1960)
In article IV of the agreement, the parties contracted that “all grievances or disputes arising between them over the interpretation or application of the terms of this Agreement shall be settled by the procedure set forth in Article V. ...” A system of grievance and arbitration procedures was formulated in article V, which also provides: “All grievances, othеr than jurisdictional disputes, arising out of the interpretation or application of any of the terms or conditions of this agreement shall be submitted for determination and shall be determined by the procedure set forth in this Article, . . .”
The agreement in the instant case specified that both the employer and *893 the union were required to refer grievances or disputes to the Joint Adjustment Board composed of an equal number of representatives from both management and labor. Article V(C) of the agreement provided: “A Contractor shall refer a grievance or dispute to the Joint Adjustment Board through the appropriate employer Association. The Association shall then refer the grievance to the Joint Adjustment Board. . . .” If the board is unable to determine the matter, or if either party wishes to challenge a decision, the board is to select an impartial chairman from a Fedеral Mediation and Conciliation Service list.
These provisions clearly indicate that the parties intended to establish a system of dispute resolution, within which both the union and the employer could expect fair consideration of complaints which either might lodge against the other. The grievances which an employer might complain about are numerous. It is hard to believe that a strike would not be one of the things the employer would want tо be able to “grieve” about. At least, it is reasonable to believe that the parties would have specifically excluded a strike from coverage, given the obvious fact that the processing of other employer grievances is so clearly provided for. No such provisions appear in the instant agreement.
On the basis of broad arbitration provisions like those in the instant case,, the Supreme Court of the United States held, in
Drake Bakeries
v.
Bakery Workers
(1962)
Plaintiff relies upon
McCarroll
v.
L. A. County etc. Carpenters,
We conclude that it was the intention of the parties to include the instant strike within the coverage of the arbitration clause. The dispute should have been arbitrated.
We now turn to consider whether the relief granted was proper in this case—dismissal of the action—or whether a stay of judicial proceedings pending arbitration should have been granted.
Our courts for many years have held that, in the absence of waiver by the other party, an aggrieved party must seek to enforce his contractual right to arbitration before suing for breach of contract. “ ‘[Sjuch arbitration, or an unsuccessful attempt to secure the same,
is a condition precedent'
to the right to maintain an action for breach of the contract; . . .”
(Clogston
v.
Schiff-Lang Co., Inc.,
A more often-cited line of reasoning reaching the same result as
Clogston
was enunciated by the United States Supreme Court in
Transcontinental & Western Air
v.
Koppal
(1953)
The Court of Appeal in Cone reasoned as follows: “It is the general rule that a party to a collective bargaining contract which provides grievance and arbitration machinery for the settlement of disputes within the scope of such contract must exhaust these internal remedies before resorting to the courts in the absence of facts which would excuse him from pursuing such remedies. [Citations.] This rule, which is analogous to the rule requiring the exhaustion of administrative remedies as a condition precedent to resorting to the courts (2 Cal.Jur.2d 304, § 184), is based on a practical approach to the myriad problems, complaints and grievances that arise under a collective bargaining agreement. It makes possible the settlement of such matters by а simple, expeditious and inexpensive procedure, and by persons who, generally, are intimately familiar therewith. ...”
Several of our Courts of Appeal have adopted this reasoning, giving summary judgment to defendants or dismissing plaintiff’s cause of action where failure to pursue a contractual arbitration remedy is proved as an affirmative
*895
defense. In none of these cases, it may be added, did defendant
demand
arbitration, but rather raised failure of plaintiff to arbitrate as a
defense
to the cause of action. (See, e.g.,
Griggs
v.
Transocean Air Lines
(1960)
In each of the above-entitled cases, the fact situation was similar to the one at bar: Plaintiff had sued on the contract rather than arbitrate and had never sought to pursue its arbitration remedy. Moreover, each and every issue alleged in plaintiff’s cause of action could have been settled through arbitration procedures. Finally, defendant did not waive its right to arbitration, but consistently asserted failure to pursue arbitration as an affirmative defense.
An alternative remedy for failure to arbitrate has long been provided by statute. Former section 1284 of the Code of Civil Procedure provided: “If any suit or proceeding be brought upon any issue arising out of an agreement providing for the arbitration thereof, the court in which such suit or proceeding is pending, upon being satisfied that the issue involved in suсh suit or proceeding is referable to arbitration, shall stay the action until an arbitration has been had in accordance with the terms of the agreement; provided, that the applicant for the stay is not in default in proceeding with such arbitration.”
In
Clogston
v.
Schiff-Lang Co., Inc., supra,
Former section 1284 was utilized primarily where plaintiff’s suit involved some issues that were not covered by or susceptible to arbitration. In such cases the entire case would not be dismissed for failure to arbitrate. The defendant, therefore, sought a stay of the action pending arbitration of the arbitrable issue or issues. For example, in
Squire’s Dept. Store, Inc.
v.
Dudum
(1953)
*896
In
Homestead Sav. & Loan Assn.
v.
Superior Court
(1961)
A defendant could also elect to use section 1284 rather than assert failure to arbitrate as an affirmative defense. In
Tas-T-Nut Co.
v.
Continental Nut Co.
(1954)
We recognized defendant’s power to elect his remedy in this fashion in
Local 659, I.A.T.S.E.
v.
Color Corp. Amer.
(1956)
In December 1960, the California Law Revision Commission submitted to the Legislature a recommendation and study relating to arbitration. The commission’s recommendations are susсeptible to a number of interpretations. Given the prior statutory and case law discussed above, it would seem that the commission was most concerned. with cases in which only some of the issues raised are arbitrable. The commission’s recommendations in pertinent part were as follows: “A pending action should not be stayed because the matter in controversy is subject to arbitration unless the party seeking the stay has taken or is taking action to compel arbitration. Existing law provides for a stay of judicial proceedings merely upon a showing that the parties have agreed to arbitrate the matter involved. This permits the existence of an agreement to arbitrate to be used as the basis for a dilatory plea.” (Id., at p. G-7.)
The commission then expanded upon this thought at page G-39: “Section 1284 of the Code of Civil Procedure provides that if a suit is brought upon an issue referable to arbitration, the court shall stay the action until the issue is arbitrated, provided that the party who applies for the stay is not in default upon the agreement to arbitrate.
*897
“In 1935 the Supreme Court held, in
Clogston
v.
Schiff-Lang Co., Inc.
[
“When a party requests a stay in a civil action on the basis of an agreement to arbitrate, he is using that agreement to arbitrate as a defense. But, under existing law, there is no provision that compels a persоn to arbitrate even though the action is stayed; hence, it may be necessary for the party whose action is stayed to commence another proceeding in a court having jurisdiction to order arbitration in order to compel the arbitration to proceed. If a party is going to request a stay because there is an arbitration agreement, he should show his willingness to proceed with the arbitration as the means of settling the disputе. The best way for the defendant to demonstrate this willingness is to obtain an order to compel arbitration.
“Section 2(d) of the Uniform Arbitration Act handles this problem by providing that the stay of an action shall be granted ‘if an order for arbitration or an application therefor has been made under this section.’ Thus the initiation of a proceeding to compel arbitration under the agreement becomes a condition precedent for thе granting of a stay.
“It is recommended that this type of provision be included in the arbitration statute in order to state clearly the test that will be applied to determine the presence or absence of default.”
The commission’s mention of Clogston may have indicated an intent to overrule that case. On the other hand, it is quite possible that the commission feared Clogston’s application to situations in which stays, rather than dismissals, were appropriate, and sought to forestall such application.
However the Legislature interpreted the commission’s intent, it did enact the commission’s proposed legislation. Section 1281.4 of the Code of Civil Procedure in pertinent part provides: “If an application has been made to a court of competent jurisdiction ... for an order to arbitrate a controversy which is an issue involved in an action or proceeding pending before a court of this State and such аpplication is undetermined, the court in which such action or proceeding is pending shall, upon motion of a party to such action or proceeding, stay the action or proceeding until the application for an order to arbitrate is determined and, if arbi *898 tration of such controversy is ordered, until an arbitration is had in accordance with the order to arbitrate or until such earlier time as the court specifies. . . . [f] If the issue which is the controversy subject to arbitration is severable, the stay may be with respect to that issue only.” (Italics added.)
Since passage of section 1281.4, the case law has continued to reflect its dual origins. In
Don daRoza, Inc.
V.
Northern Cal. etc. Hod Carriers Union, supra,
Zak
v.
State Farm etc. Ins. Co.
(1965)
Similarly, in
Schwartz
v.
Leibel
(1967)
Finally, the same Court of Appeal that later sustained the dismissal of plaintiff’s suit in
Leon Handbag Co.
v.
Local 213, supra,
*899
The holding in
Ross
is not in issue here. What is instructive about
Ross
and the same court’s later decision in
Leon Handbag
is that in
Ross,
where proceedings were merely stayed, defendants
demanded
arbitration; in
Leon Handbag
a dismissal was sustained because defendants elected to assert plaintiffs’ failure to arbitrate as an affirmative defense only. In
Ross
the court recognized that “an agreement to arbitrate is an affirmative defense” (
The distinctions implicit in the decisions discussed above should be followed. Sрecifically, where the only issue litigated is covered by the arbitration clause, and where plaintiff has not first pursued or attempted to pursue his arbitration remedy, it should be held that (1) plaintiff has impliedly waived his right to arbitrate, such that defendant could elect tó submit the matter to the jurisdiction of the court; (2) defendant may also elect to demur or move for summary judgment on the ground that the plaintiff has failed to exhaust arbitration remedies; and (3) defendant may аlso elect to move for a stay of proceedings pending arbitration if defendant also moves to compel arbitration. Plaintiff may of course sue preliminarily to enforce its arbitration rights.
Where plaintiff has attempted to exhaust its arbitration remedy or raises issues not susceptible to arbitration or not covered by the arbitration agreement, defendant may not merely assert failure to arbitrate an issue as an affirmative defense; a stay rather than dismissal of the suit is then proper. Defendant must therefore demand arbitration if it seeks such a stay.
In the instant case plaintiff at no time attempted to pursue its arbitration remedy. The no-strike clause was contractually subject to arbitration. The relief sought, damages, is traditionally within an arbitrator’s power to award.
(Schwartz
v.
Leibel, supra,
Wright, C. J., McComb, J., Mosk, J., Burke, J., Sullivan, J., and Ford, J., * concurred.
Notes
The federal courts seem to have pursued a similar course. In
Drake Bakeries
v.
Baker Workers, supra,
Assigned by the Chairman of the Judicial Council.
