Appellant Charles Boutwell appeals from the district court’s grant of summary judgment in favor of appellee Chevron U.S.A., Inc. Because the district court correctly determined that Boutwell was unable to prevail on any of the three pleaded grounds of recovery, we affirm.
*407 I.
In April of 1987, Chevron took bids to obtain the services of a construction contractor to perform a structural upgrade 1 on Chevron’s oil and gas production platform, the South Timbalier 151, located on the outer Continental Shelf, off the coast of Louisiana. C & B Fabricators, Inc. (hereinafter C & B) was awarded the contract. On May 18, 1987, Chevron and C & B entered into a written agreement which indicated that C & B was to provide all labor, equipment, materials, and supervision to upgrade the S.T. 151. The contract specifically stated that C & B would perform the work as “an independent contractor and not as an employee” of Chevron.
In order to accomplish the upgrade, C & B had to create various holes in the deck of the platform. For example, holes were created when portions of the grating were changed out, or when equipment had to be run through a platform deck. Whenever a hole was created, C & B required that its employees rope and chain off the hazard.
Boutwell was hired by C & B to work on the Chevron project. On June 18, 1987, after he had been working for about six days, Boutwell tripped and fell into an un-barricaded hole which C & B had created on the S.T. 151 platform. According to Boutwell, the hole was covered by a piece of plywood, but had not been roped or chained off. Boutwell filed suit against Chevron seeking to recover under theories of negligence and strict liability pursuant to Louisiana Civil Code, Articles 2315, 2317, and 2322. Rockwell Insurance Company intervened to recover workman’s compem sation benefits paid to Boutwell. The district court, pursuant to Chevron’s motion for summary judgment, dismissed the complaint. From this dismissal, Rockwell and Boutwell appeal. 2
II.
The district court correctly denied relief under Louisiana’s general negligence provision.
3
As a general rule, a principal is not liable for the negligent acts of his independent contractor.
Hawkins v. Evans Cooperage Co.,
Under the first exception, a principal may not avoid liability for injuries resulting from an ultrahazardous activity by hiring out work to an independent contractor. Louisiana case law 4 and recent decisions of this Court indicate that the activities involved in this case cannot properly be considered ultrahazardous. Neither party disputes this characterization. Rather, it is the second exception to the general rule of principal nonliability which forms the primary battleground in the case before us today.
Under the second exception, a principal incurs liability for the negligent acts of an independent contractor over which the principal exercises operational control or which it has expressly or impliedly authorized. 5 Boutwell argues that summary judgment was improper because the evidence *408 presented to the district court indicates that there is a genuine question of material fact as to Chevron’s retention of operational control.
This Court has noted the general rule regarding employer liability for the negligent acts of an independent contractor:
[T]he employer must have retained at least some degree of control over the manner in which the work is done. It is not enough that he has merely a general right to order the work stopped or resumed, to inspect its progress or to receive reports, to make suggestions or recommendations which need not necessarily be followed, or to prescribe alterations and deviations. Such a general right is usually reserved to employers, but it does not mean that the contractor is controlled as to his methods of work, or as to operative detail. There must be such a retention of right of supervision that the contractor is not entirely free to do the work in his own way. 6
Louisiana law recognizes, as a corollary to the above stated general principle, that the mere presence of a “company man” is not sufficient to constitute the retention of operational control. 7
“The fact that [the owner] periodically inspected the jobsite to be sure that work was being performed in accordance with the specifications does not constitute the exercise of operational control.” 8
The “company man” on the S.T. 151 project was Jim Melancon, Chevron’s construction engineer. Throughout the course of the project, Dean LeBlanc, C & B’s on-site supervisor, would generally discuss the work with Melancon. LeBlanc would then instruct the C & B workers as to how they should perform their work. 9
Boutwell, seeking to distinguish Ains-worth, argues that the evidence indicates that Chevron played a more active role in the day to day operations of C & B, 10 and the issue should properly go before a jury. After reviewing the evidence, we agree with the district court’s assessment.
Initially, we note that the contract between C & B and Chevron clearly indicated that C & B was to operate as an independent contractor. In
Hemphill v. State Farm Insurance Co.,
The summary judgment evidence, including the contractual provisions, does not support the imposition of liability against Chevron. All materials needed for the construction, with the exception of the actual grating, were provided by C & B. C & B also created the hole in question. 11 Further, C & B was solely responsible for advising their employees as to how to perform the necessary work including the rope-off procedure. The deposition of Le-Blanc stresses that C & B was fully responsible for barricading holes created in the course of their work:
Q: And Mr. Melancon, he did not tell your men how they should go about performing their work; did he?
A: Correct.
*409 Q: The way it worked, as I understand it, he would tell you generally what work needed to be done and then you would see to it that that work was done?
A: Correct....
Q: In terms of seeing to it that [roping off] was done, if there was a hole in the grating deck that was chained off, that was C & B’s job to see to it that that was done?
A: Correct.
Q: In other words, Jim Melancon wouldn’t come around and chain the holes or tell people to chain the holes?
A: Correct.
Deposition of LeBlanc, Record at 116, 117.
If a deficiency in the work became apparent, Melancon would inform LeBlanc; it was LeBlanc’s job to see that the problem was remedied. 12 In short, all of the evidence before the district court indicates that C & B acted in the capacity of a true independent contractor pursuant to the terms of the contractual arrangement. C & B was responsible for determining the methodology of the work to be accomplished, while Chevron stood guard over the finished product.
Absent operational control retained by Chevron, Chevron cannot be held liable for the negligent acts of its independent contractor. 13 The summary judgment evidence is not sufficient to raise a genuine question of fact as to the retention of operational control. Consequently, the district court did not err in granting summary judgment in favor of Chevron on this ground of recovery.
III.
Boutwell next argues that the district court erred in granting summary judgment in favor of Chevron pursuant to the strict liability count. Article 2317 holds a party strictly liable where the plaintiff establishes (1) that the property which caused the damage was in the custody of the defendant, (2) that the property was defective because it was a condition that created an unreasonable risk of harm to persons on the premises, and (3) that the defect in the property was the cause in fact of the resulting injury.
See, e.g., Stewart v. Sam Wallace Indus. Co.,
This Court has noted that “custody” in the context of Article 2317, means supervision and control.
Steele v. Helmerich & Payne Int’l Drilling Co.,
Boutwell cannot demonstrate that there was a defect creating an unreasonable risk of harm. As the court in
Stine v. Creel,
IV.
The district court did not err in granting summary judgment in favor of Chevron. The evidence before the district court indicated that there was no question of material fact as to the retention of control by Chevron. Similarly, Boutwell cannot prevail under Article 2317’s strict liability provision. The judgment of the district court is AFFIRMED.
Notes
. The structural upgrade involved changing out the structure’s grating decks, production piping, deckplate, and various other items of equipment.
. Initially, Boutwell argued on appeal that summary judgment was improper with respect to all three grounds of recovery. At oral argument, however, Boutwell conceded that he was not entitled to prevail on the basis of 2322. Article 2322 provides: "The owner of a building is answerable for the damage occasioned by its ruin, when this is caused by neglect to repair it, or when it is the result of a vice in its original construction." We agree with Boutwell’s assessment; accordingly, 2322 will not be discussed in the text of this opinion.
. Article 2315 provides, in pertinent part: “Every act of man that causes damage to another obliges him by whose fault it happened to repair it.”
.
Franklin v. Oilfield Heavy Haulers,
.
See, e.g., Ainsworth v. Shell Offshore, Inc.,
.
McCormack v. Noble Drilling Corp.,
.
Williams v. Gervais F. Favrot Co.,
.
Ainsworth,
. For example, LeBlanc specifically instructed Boutwell to employ the "rope off’ procedure whenever Boutwell created a hole in the course of his work. Boutwell Deposition, Record at 135.
. For example, in addition to the assertion that Melancon did more than merely oversee C & B’s progress, Boutwell argues that Chevron provided the tools to use during the structural upgrade. However, the evidence indicates that C & B provided all the necessary tools and equipment with the sole exception of the actual grating which was being replaced. Deposition of Forrest Calíais, Record at 148.
. LeBlanc Deposition, Record at 120.
. Melancon Affidavit, Record at 110-11.
. Rockwell argues, as an alternative ground on which to base Chevron’s liability, that Chevron authorized unsafe work practices. A similar situation was addressed in
Ainsworth,
. Boutwell Deposition, Record at 140-41.
