Chapman & Cole v. Itel Container International B.V.Chapman & Cole v. Itel Container International B.V.
This аction arose over the commercial lease of a container yard. Chapman & Cole (Chapman), the landlord, brought this suit seeking recovery for failure to pay rent and failure to maintain the premises properly against Itel Container International B.V. (Itel), the tenant. Itel counterclaimed alleging that Chapman had failed to design and construct the container yard adequately and alleging a RICO violation by Chapman and one of its employees, Mr. Norman Ehrentraut.
Itel appeals the final judgment award of $562,573.62, plus costs and expenses and attorneys fees in favor of Chapman in the case-in-chief, the breach of contract claim. Itel and Urquhart & Hassel, Itel’s counsel for the case-in-chief, appeal the sanctions imposed against them under
We deny Itel’s and its counsels' appeals and also Chapman’s appeals, affirming in its entirety the district court judgment.
I. FACTS AND PRIOR PROCEEDINGS
Itel is in the business of owning, leasing, storing, and moving large aluminum and steel containers all over the world.
Coldwell Banker enlisted Chapman to purchase property for the site, develop it pursuant to plans and specifications approved by both Chapman and Itel, and lease the property back to Itel for a term of ten years. Itel at the end of the lease
Chapman purchased the property, and the yard was built through the use of subcontrаctors. Chapman referred Itel to Mr. Robert Treat, a “dirt/surface subcontractor,” and to Mr. John Montgomery, an architect. Itel representatives met with Treat and Montgomery on numerous occasions to plan, develop, and design the facility.
During the planning stage, Itel advised Chapman and the subcontractor Treat that the maximum weight to be utilized on the yard would be 30,000 pounds.
In June of 1980, Coldwell Banker, as the agent of Itel, prepared a standard industrial/commercial lease and lease addendum that were signed by Itel аs the lessee and Chapman as the lessor. The lease was later amended to state it would begin on February 1, 1981 and end on January 31, 1991. The lease and the addendum are the only written agreements between the parties. They were the subject of a joint stipulation by the parties when they were admitted into evidence at trial.
Upon completion of the site in early January 1981, Itel took possession. At the grand opening of the facility in March 1981, Itel declared to the public that it had “designed the greatest facility that this type operation could possibly have.”
Itel hired an independent contractor to operate the plant on its behalf. After analyzing the flexible surface material of the plant, the independent contractor informed Itel that the surface could not withstand the weight of the forklifts Itel planned to use. Itel instructed the contractor to use the forklifts as planned anyway.
During the first month of operation, failures in the surface were already appearing. Upon request by Itel, Chapman, through its subcontractors, made the necessary repairs to the surface. Upon discovering the weights of the forklifts being used on the facility however, Chapman, as well as the subcontractors, refused to make any further repairs after May 15, 1981.
Itel ceased to pay rent on July 1, 1981, remaining on the yard until October 1, 1981. In the face of the contract obligations under the lease and despite substantial damage obviously occurring to the yard, Itel did not make repairs or maintain the yard.
After Itel vacated the property, Chapman undertook repairs. During the renovation, Chapman leased half of the property to Container Maintenance Service (CMS). After renovation, CMS occupied the entire space until 1985 when it went into bankruptcy. The property was then relet to another contractor who also became insolvent and was never able to make any rent
On November 22, 1982, Chapman sued Itel in the United States District Court for breach of the lease. Chapman claimed that Itel’s alleged use of overweight forklifts, its failure to stack containers properly, and its careless maintenance of the yard negligently damaged the yard’s surface and appurtenances in breach of the lease contract.
Itel answered and counterclaimed for breach of an alleged turn-key lease, breach of warranty, negligence, and violation of the Deceptive Trade Practices-Consumer Protection Act (“DTPA”), Tеx.Bus. & Com. Code Ann. 17.41, et seq. Itel alleged that Chapman failed to complete the facility adequately to support Itel’s normal operations; thus, Itel was constructively evicted by these deficiences.
Two years into the case, Itel amended the counterclaim, alleging violation of the Racketeer Influenced and Corrupt Organizations Act (“RICO”),
Itel contended in the counterclaim that Ehrentraut had received “kickbacks” by a Mr. Ed Novotny of Dantex Erectors, one of the subcontractors on the project, to “turn his head” during the construction of thе surface of the facility by Treat, another subcontractor. While it is clear Ehrentraut did receive at least five checks from Dan-tex Erectors during the time period in question, the evidence established that these checks were paid to Ehrentraut for other legitimate business transactions completely unrelated to the matter at hand.
After a trial which lasted seven days, the district court entered its findings of fact and conclusions of law. The court awarded Chapman $562,573.72 in actual damages, pre- and post-judgment interest, $13,412.06 in costs and expenses, and $180,000 in attorneys’ fees. No future damages were awarded. The court also dismissed Itel’s counterclaim with prejudice. Final Judgment issued on August 10, 1987.
The court characterized this case as a “straightforward action for breach of contract,” in finding that Chapman had constructed the yard in accordance with the specifications рrepared by Itel. It concluded that it was through Itel’s failure to maintain the property that damage occurred to the property.
After trial and after a “show cause” hearing, the district court imposed sanctions against Itel and its attorneys. On July 22, 1987, the Court ordered Itel and Urquhart & Hassell to pay appellees $20,-000 in sanctions, allocating $15,000 to Chapman and $5,000 to Ehrentraut. The court found that Itel and its attorneys had violated
II. BREACH OF CONTRACT CLAIM
A. Standard of Review
Our review of the facts is limited by the clearly erroneous rule set out in
As to the lease itself, the district court found the contract clear and unambiguous. Because of the absence of factual issues, our interpretation of the contract is not limited to the clearly erroneous rule. Carpenters Amended & Restated Health Ben. Fund v. Holleman Constr. Co.,
B. The “Turn-key” Provision
On appeal, Itel argues that the district court’s finding that this case involves a straight-forward breach of contract claim misapprehended the “turn-key” nature of the contract. Itel supports this argument by pointing out the trial court in its written opinion never addressed specifically the typewritten lease addendum that expressly required Chapman to construct the Itel facility on a “turn-key condition upon occupancy” basis so that Itel “would have the capacity to immediately commence [its] normal operations.”
A “turn-key” contract has a certain well-defined meaning in law and in fact. A “turn-key job is defined as ‘a job or contract in which the contractor agrees to complete the work of the building and installation to the point of readiness for operation or occupancy.’ ” Hawaiian Independent Refinery, Inc. v. United States,
While Chapman admits its obligation to build a facility capable of Itel’s intended use, this admission, along with the use of the term “turn-key” in the contract, did not create a “turn-key” situation. The district court correctly looked to the entire written agreement to ascertain the meaning of the contract and did not err in disregarding the industry usage of the term “turn-key.” See Chapman v. Orange Rice Milling Co.,
First, Itel agreed in Section 6.3 of the lease to accept the premises “in their condition existing as of the date of the execution hereof ...,” and “acknowledge^] that neither Lessor nor Lessor’s agents ha[d] made any representation or warranty as to the suitability of the Premises for the conduct of Lessee’s business.” Itel also agreed under Section 8.7 that Chapman:
shall not be liable for injury to Lessee’s business or any loss of income therefrom or for damages to the goods, wares, merchandise or other property of Lessee ... whether the said damage or injury results from conditions arising upon the Premises or upon other portions of the building of which the Premises are a part....
If Itel had wished to make Chapman liable under a turn-key contract, it would not have prepared and executed an instrument expressly relieving Chapman of liability to Itel and expressly disclaiming warranty as to the suitability of the premises to Itel’s business. As the court in Glassman pointed out:
Ordinarily the industry understanding of the term [turn-key] would be control-ling_ However, in the instant contract the term was expressly defined as requiring compliance with the tenant’s lease requirements and bearing all costs, therefore controlling over the industry usage.
In Hawaiian Independent Refinery, supra, a case similar in its fact to the case before us, the court chose to look past the label “turn-key” to conclude that the owner’s active participation in the “makeup of the contract plans and specifications” and the disclaimer of liability on the part of the contractor demonstrated that the parties’ agreement was not a turn-key contract.
Choosing not to apply the common industry meaning of “turn-key,” the district court found the contract a lease agreement without deeming any of the contract provisions inconsistent. The court held that Chapman presented Itel with a facility that conformed to the specifications that both parties had agreed could handle Itel’s normal business operations. It was correct, therefore, for the court to find that the destruction of the property resulted from Itel’s misrepresentations of what constituted “normal business operations” coupled with the misuse by Itel of the property. In sum, Itel breached the contract.
We agree with the application of the law of contract by the district court. But the result is the same even if “turn-key” in the common usage had been the general intent of the parties. Contracting parties retain the right to “allocat[e] the risks among themselves as they see fit” in the “turnkey” situation. See Martin v. Vector Co.,
C. Liability of Itel Under Contract Law
Itel argues that the' district court misperceived the relationship between Chapman and Itel even if the court correctly found the contract not to be the usual turn-key construction contract. Itel claims that as the general contractor, Chapman was responsible for design deficiencies. See Emerald Forest Utility Dist. v. Simonsen Constr. Co.,
... if the contractor is bound to build according to plans and specifications prepared by the owner, the contractor will not be responsible for the consequеnces of defects in the plans and specifications. This responsibility of the owner is not overcome by the usual clauses requiring builders to visit the site, to check the plans, and to inform themselves of the requirements of the work, as is shown by Christie v. United States, 237 U.S. 234 ,35 Sup.Ct. 565 ,59 L.Ed. 933 ; ... where it was held that the contractor should be relieved, if he was misled by erroneous statements in the specifications.
Id. (some citations omitted). Chapman carried out the construction according to the plans prepared by Itel and mutually approved. Chapman cannot be held responsible for defects in those plans.
Chapman did not breach the contract. Rather, Itel breached it by failing to pay rent, by failing to make repairs as it had contracted to do, and by vacating the premises. The district court correctly awarded damages to Chapman for Itel’s breach of the contract.
III. ALLEGED IMPROPER RELIANCE BY THE DISTRICT COURT ON EXTRAJUDICIAL KNOWLEDGE OF THE UNDERLYING FACTS
Itel claims the trial court rеlied upon personal knowledge of matters outside the trial record, which allegedly circumvented the administration of justice.
While it is clear the judge made several comments throughout the trial which implied knowledge of the construction industry, Itel fails to show any improper reliance on that knowledge by the trial judge or any prejudice to its case by any possible improper reliance. Price Bros. Co. v. Philadelphia Gear Corp.,
Though the trial judge must be neutral, he should not be a passive spectator ... He may, when in his sound discretion he deems it advisable, comment on the evidence, question witnesses, elicit facts not yet adduced or clarify those previously presented, ...
Itel fails to show where the district judge moved beyond his proper role or how Itel was prejudiced. As the finder of fact, a judge must rely upon his or her experience and common sense. No more was involved here.
IY. THE IMPOSITION OF SANCTIONS AGAINST ITEL
A.
The correct standard for reviewing a courts’ imposition of sanctions under
Itel clearly had ample opportunity to present its position. Itel received notice as early as ten months before trial that sanctions might be imposed when Chapman filed a motion to impose sanctions. Itel also was repeatedly warned throughout the trial of the possibility of sanctions. After trial, Itel was again warned when both Chapman and Ehrentraut renewed their motions for imposition of sanctions. Finally, after a show cause hearing where Itel was allowed to put on evidence, the judge decided to award sanctions.
This Court en banc recently discussed an attorney’s obligations under
1) that the attorney has conducted a reasonable inquiry into the facts which support the document;
2) that the attorney has conducted a reasonable inquiry into the law such that the document embodies existing legal principles or a good faith argument ‘for the extension, modification, or reversal of existing law;’ and
3) that the motion is not interposed for purposes of delay, harassment, or increasing costs of litigation.
Id. at 873-74. Also, an attorney’s subjective “good faith” does not protect him from
The district court found that the RICO action was based at best upon the subjec-five belief of Itel’s attorney without enough concrete evidence to bring the cause of action, and at worst, on the improper purposes of causing delay and increasing expenses to Chapman. The district court thus had as a basis for sanctions either the first or the third affirmative duty set out in Thomas.
Itel undertook to support its RICO claim that Ehrentraut received “kickbacks” to “turn his head” during the construction of the flexible surface by initially proffering: 1) copies of five cancelled checks from No-votny and Dantex Erectors to Ehrentraut; 2) statements made by John Montgomery during a taped telephone conversation with Hassell; 3) the fact that Ehrentraut occasionally did work for Novotny as an independent contractor and was a partner in a company with Novotny; 4) the fact that Chapman confronted Ehrentraut about his involvement with Novotny; and 5) the fact that if either Novotny or Ehrentraut admitted to this scheme, they would subject themselves to possible criminal charges.
The district court found the only possiblе “solid” evidence at the time of the initial filing was the taped conversation between Montgomery and Hassell and the five can-celled checks. The court correctly concluded that neither amounted to proper grounds for bringing a RICO cause of action. The court heard the tape in camera after it was brought to the court’s attention at the show cause hearing. The court ruled that it contained only rumors.
Itel and its counsel now try to argue that they were precluded at trial from discussing the RICO issue since the suit against Ehrentraut was never tried; thus, they argue they were never given the opportunity to prove their claim. They were given numerous opportunities to do so during cross-examination, however, and they had fair warning that sanctions might be imposed if additional evidence in support of their claim was not forthcoming. At a pretrial conference, the trial court warned Itel of the weakness of the RICO claim. Itel responded that there was plenty of evidence, but when the court asked Itel to produce that evidence within 60 days, none was provided. Itel also failed at the show cause hearing to supply any additional information on the objective reasonableness of its plеading.
Finally, it should be noted that an attorney’s responsibility to conduct a reasonable prefiling investigation is particularly important in RICO claims:
Given the resulting proliferation of civil RICO claims and the potential for frivolous suits in search of treble damages, greater responsibility will be placed on the bar to inquire into the factual and legal bases of potential claims or defenses prior to bringing such suit or risk sanctions for failing to do so.
Black & Magenheim, Using the RICO Act in Civil Cases, 22 Hou. Law. 20, 24-25 (Oct.1984). See also Fahrenz v. Meadow Farm Partnership,
B. Rules 26 and 37, Sanctions
The district court found that in connection with the RICO claim, Itel’s attorneys also abused the discovery process. The district court stated its awareness of the superior resources of Itel. It then found evidence of an attempt to innundate Chapman with unnecessary discovery requests to raise the cost of the litigation to a point that Chapman would be forced to “give up without a fight” because of the expense.
Under 26(g), Urquhart & Hassell was under a duty similar to the duty under
The duty to make a ‘reasonable inquiry’ is satisfied if the investigation undertaken by the attorney and the conclusions drawn therefrom are reasonable under the circumstances. It is an objective standard similar to the one imposed by Rule 11 ... Ultimately what is reasonable is a matter for the court to decide on the totality of the circumstances.
The failure to inform opposing counsel of the tape also warranted sanction. The failure amounted to an incomplete response to an interrogatory question.
Itel and its counsel claim that they were not under a duty to reveal the tape since it constitutes work product. For two reasons this contention cannot prevail. First, the clandestine taping of a telephone conversation implicitly waives the protection of the work product doctrine because it violates the American Bar Associations’s Model Rules of Professional Conduct. See Parrott v. Wilson,
C. The Amount Awarded
The district court imposed sanctions in the amount of $20,000 on Itel and its attorneys under
First, the district court correctly determined an “appropriate” sanction under
[wjhether sanctions are viewed as a form of cost-shifting, compensating opposing parties injured by the vexatious or frivolous litigation forbidden byRule 11 , or as a form of punishment imposed on those who violate the rule, the imposition of sanctions pursuant toRule 11 is meant to deter attorneys from violating the rule.
Id. at 877 (quoting Donaldson v. Clark,
Itel and its counsel argue that even if monetary sanctions are appropriate under
Even if
V. CLAIM FOR FUTURE RENT
The district court properly denied Chapman’s claim for future rent for the unexpired term of the Itel lease, the period covering May 1, 1987, through January 31, 1991. The district court held that Chapman failed to offset against the value of the alleged future unpaid rent either the fair market value of the unexpired term of the lease or the amount of payments to be received by Chapman from subsequent tenants. Chapman’s failure preсluded under Texas law recovery of any amount for future rent. The court reached this decision by finding that Chapman chose to treat Itel’s abandonment as an anticipatory breach under common law. This finding was not clearly erroneous.
In its petition, Chapman sued for “loss of rents.” At trial, Chapman relied solely on the testimony of Howard Chapman to establish the amount of lost future rent. Chapman initially calculated these future damages based on the total amount due under the lease from July 1, 1981, to January 31,1991. From that amount, Chapman subtracted the actual rents that had been received from subsequent tenants and discounted that sum to its present value. During cross-examination, Chapman admitted that the figure as calculated did not take into account the reasonable cash market value of the unexpired lease or the rental amounts to be received by subsequent tenants.
Chapman argues that it was electing recovery of damages under Section 13(a) of the contract and not Section 13(c) as the trial court held. Chapman argues that it was entitled to do that under Section 16.11 of the contract. It asserts that while Section 13(c) “incorporated” the common law for breach by the tenant, Section 13(a) displaced and superseded the ordinary common law measures of damages. Under Section 13(a), the contract language suggests that the burden of proof on the future cash market value of the property was on Itel. Thus, Chapman argues that it did not have to reduce future rent by any amount and that it was up to Itel to produce reduction evidence. The district court, however, correctly held that under Crabtree, the burden of proof was on Chapman to prove the amount of future losses.
Further, even if Chapman were right in its assertion, Chapman still cannot prevail. Itel correctly relied on the unrefuted valuation of the unexpired term as derived from the admitted evidence of the CMS lease and subsequеnt leases on the property
VI. THE APPROPRIATE POST-JUDGMENT INTEREST RATE
Chapman argues that when jurisdiction is based on diversity of citizenship, the rate applied post-judgment should be determined by the applicable state law, which would be Texas lаw in this case. Under Texas law, the appropriate rate would be the contract rate of 10% per annum. Tex.Rev.Civ.Stat.Ann. art. 5069-1.-05, § 1(1) (Vernon 1985). We must reject this contention, however, and uphold the district court’s application of
Chapman’s argument that Texas law should still govern since this is a diversity case is based upon cases decided before
Since the statutory amendment, however, the great majority of the circuit courts have held that the amended
VII. CONCLUSION
We affirm the district court’s judgment in full. The district court correctly decided that the contract was not a “turn-key” construction contract but rather a commercial lease. The court correctly assessed damages against Itel for breach of that contract when it vacated the premises, failed to make proper repairs, and failed to pay rent.
As to the sanctions awarded, the court correctly imposed sanctions under Fed.R. Civ.P.
As to the request for sanctions for this appeal under Fed.R.App.P. Rule 38, we are not persuaded that the imposition of sanctions is warranted. Therefore, we deny the appellees’ motion for further sanctions under this rule.
Finally, the court correctly denied future rent as part of the damage award and properly awarded post-judgment interest by calculating it in accordance with the amended
AFFIRMED.
Notes
. Itel is the fourth largest container company in the world. Itel utilizes various container yards in the United States, including yards in Chicago, Detroit, Houston, Los Angeles, Memphis, Oakland, Portland, and Seattle.
. Itel contends that it is understood in the container business that 30,000 pounds refers to the lift capacity and not the gross weight as Chapman assumed. Itel further contends that even if 30,000 pounds referred to the gross weight, the surface still would not have been able to withstand the weight.
. The relevant sections of the lease can be found in the district court opinion, Chapman & Cole v. Itel Container International,
.Itel initially advised Chapman that a "top” forklift would be utilized in the yard to preclude damage to the flexible surface that would be caused by the tynes of a “bottom" forklift. However, Itel only had the "bottom” forklifts on hand upon the opening of the plant so that they had to be used. These forklifts weighed approximately 48,000 pounds and could exert as much as 80,000 pounds of weight on any given location. This weight was 214% greater than the maximum 30,000 pound weight for which the container yard had been designed.
.
Findings of fact, whether based on oral or documentary evidence, shall not be set aside unless clearly erroneous, and due regard shall be given to the opportunity of the trial court to judge of the credibility of the witnesses.
. While the court never mentions the term "turn-key” in its opinion, it is clear that the court was aware of the provision because of the many references by the court to the addendum. We must conclude that the court chose to disregard the general industry usage meaning of the term in its conclusions.
. Itel tries to distinguish Hawaiian Independent Refinery on the basis that Itel did not own the property. The reasons for holding the owner liable in Hawaiian Independent Refinery, however, are applicable to Itel. Itel clearly had the upper hand in bargaining, had the right to purchase the property at the end of the lease, and initiated and conducted the arrangements between the parties.
. Itel also argues that Chapman breached the implied warranty of suitability that was recently recognized by the Texas Supreme Court in Davidow v. Inwood North Professional Group Phase I,
.
. The district court also held Itel violated
. The judge found Montgomery had no personal knowledge of the truth of the allegations. Hassell herself admitted that she did not ask Montgomery about the names, dates, places, or circumstances underlying the rumors that he had heard. Hassell thus failed to explore readily available avenues of inquiry and on that basis alone could be sanctioned for filing a factually frivolous appeal. See Calloway v. Marvel Entertainment Group,
. Urquhart & Hassell again failed to follow reasonable avenues of exploration. Had it bothered to investigate before filing the suit, it would have learned Ehrentraut legitimately worked for Novotny as an independent contractor "after hours” for legitimate pay.
.
Every request for discovery or rеsponse or objection thereto made by a party represented by an attorney shall be signed by at least one attorney.... The signature of the attorney or party constitutes a certification that he has read the request, response, or objection, and that to the best of his knowledge, information, and belief formed after a reasonable inquiry it is: ... 2) not interposed for any improper purpose, such as to harass or to cause unnecessary delay or needless increase in the cost of litigation; and 3) not unreasonable or unduly burdensome or expensive, given the needs of the case, the discovery already had in the case, the amount in controversy, and the importance of the issues at stake in the litigation. ...
.The district court found numerous other violations as well. The judge found other internal reports of Itel that were improperly withheld, evidenсe of attempted intimidation of witnesses, and requests for documents that were also unduly burdensome on non-party witnesses.
. The question asked in the Chapman’s fifth set of interrogatories was worded as follows:
Interrogatory No. 4:
Please state with specificity and particularity all of the documents, records, memoranda, written indicia and/or any other evidence, whether or not written which indicate or support the allegation that Mr. Norman Ehren-traut ‘knowingly solicited and accepted benefits and payments from subcontractors involved in constructing the Itel facility on the agreement or understanding that the benefits and payments would influence the conduct of third party defendant in relation to the affairs of his employer.’
Itel’s answer was:
Answer:
Copies of cancelled checks evidencing payments from EJ. Novotny and Dantex Erectors are attached hereto.
. Additionally, the failure to disclose the existenсe of the tape was actionable under 26(g) because it prolonged needlessly the litigation of this claim.
. The district court did not make specific findings as to the imposition of the
If the sanctions imposed are substantial in amount, type, or effect, appellate review of such awards will be inherently more rigorous; such sanctions must be quantifiable with some precision. Therefore, justification for theRule 11 decision in the record must correspond to the amount, type, and effect of the sanction applied.... We therefore reject a rule that would impose upon district courts the onerous and often time-consuming burden of making specific findings and conclusions in allRule 11 cases. In doing so, it should be clearly understood that when the basis and justification for aRule 11 decision is not readily discernable on the rеcord, an adequate explanation by the trial court for the decision will be necessary.
Thomas,
Also, as the Fourth Circuit stated in Fahrenz, it is important to note thatRule 11 speaks in terms of an ‘appropriate sanction.’ What constitutes reasonable expenses within the context ofRule 11 must be considered in relation with the Rule’s goals of deterrence, punishment, and compensation. In this respect, "reasonable” does not necessarily mean actual expenses and attorney's fees. InsteadRule 11 leaves the determination of the "appropriate sanction” to the sound discretion of the trial court....
850 F.2dat211. While Fahrentz addresses the specific situation of expenses as a sanction, the same reasoning applies where the court imposes sanctions that are nоt tied to expenses. Here, the sanction imposed is reasonable in light of the expenses involved in the litigation.
. The district court found alternatively: 1) If Chapman intended to reduce the amount of future rent by subsequent tenants’ rent, which was its contention in its Reply to Defendant’s Response to Plaintiffs Motion for Final Judgment, there would be no recovery since the amount realized on subsequent leases exceeded the amount due under the Itel lease. On the other hand, (2) if the court treated Chapman as not realizing anything on the additional leases, Chapman’s damages for future losses would be the present value of the unexpired term less the fair market value of the term. Again, Chapman recovers nothing because it failed to put on any expert evidence to support its claim. Under either approach, the district court held Chapman failed to meet the burden of proving the amount of damages for future losses on the unexpired term of the lease. 665 F.Supp. at
.The district court laid out the fact scenario:
... the facts are clear that Chapman and Cole initially chose to treat Itel’s conduct as an anticipatory breach of contract, repossess the property and lease it to a new tenant, Container Maintenance Service, Inc_ Under the terms of the industrial lease with CMS, CMS was to pay Chapman and Cole rent at the reduced rate of $6,000 per month while repairs were being made to the container yard. Once the repairs were completed, CMS would then pay the agreed upon monthly rental of $16,500 for the duration of the ten-year lease. In addition, under the terms of the triple-net-lease, CMS was also responsible for the payment of taxes and insurance.... The facts indicate, however, that this did not occur.
. CMS terminated the lease after going into bankruptcy. After retaking possession, Chapman relet it again. It appears this tenant is still on the property, but that the tenant still has not made any rent payments.
. Section 16.11 of the contract makes the remedies under the contract cumulative. The trial court, however, had reason for holding Chapman to an election since in its April 29, 1987 motion, Chapman specifically argued it was entitled to recover "the contractual rental reduced by the amount to be received from the new tenants, as set forth in Crabtree ...,
. Prior to October 1, 1982,
. This Court had expressly reserved this issue since the enactment of amended