29 Ind. 614 | Ind. | 1868
The complaint was in three paragraphs. The first paragraph alleges a special contract, in writing, between the parties for the building of a house by the plaintiff, for the defendant, and furnishing the materials therefor, at a fixed price of $3,100. That at the instance of the defendant, the plans were greatly changed and enlarged, and the contract waived, and that work was done and materials furnished in building the house, upon the enlarged plan, to the amount of $4,000 more than was required by the original contract, &c. The second and third paragraphs are the common indebitatus and quantum valebant counts for work, labor, care, diligence and materials, done and furnished by the plaintiff for the defendant, in the erection of a house. The answer was in six paragraphs, three only of which are involved here; they are ■: 1. General denial. 2. Payment. 3. That the whole work was done and the materials furnished,
The giving of certain instructions to the jury is also
The sixteenth interrogatory was immaterial, so far as any answer to it could operate upon or control a general verdict. It must be considei’cd with reference to the seventeenth. Suppose the plaintiff did tell the defendant, at a certain time, that his extra work then amounted to only $350. Such an admission is not conclusive of the fact, but only evidence of it, and the jury might, nevertheless, have such evidence before them as would require them to find •that the extra work was greatly in excess of what the plaintiff' had stated it to have been ; indeed, that it was so much, that after deducting all payments made beyond the contract price, the balance would be the sum found by the general verdict. In that case, it could certainly be of no advantage to the defendant to ascertain whether or not extra work had been afterwards done. We think that neither the seventeenth nor eighteenth interrogatories should have been sent to the jury at all. But again: Inasmuch as the seventeenth question was answered in the negative, it is not within our power to perceive how any answer to the eighteenth could have controlled the general finding. No possible answer to it could have been in conflict with the latter. If it had been found that at the date named in the seventeenth, the extra work did, in fact, amount to only $350, .then a negative answer to the eighteenth would have been important, for the two answers together would have shown a limit beyond which the general verdict could not go. The twentieth interrogatory was also immaterial, and hence it ■was not error to refuse to require a specific answer to it.
The answers to the twenty-third and twenty-fourth interrogatories were sufficient. The answers were general, because the questions were general. If specific facts were .desired to be found, the questions should have been so framed that answers to them must have involved a finding as to those facts. These interrogatories did not call for answers any more particular than wei’e given.
We have omitted to consider, in its natural place, the question made upon the refusal to require a better answer to the ninth question sent to the jury. It is apparent that the answer given was not responsive to the question, and there was therefore no answer to that question. But no proper answer that could be framed could have been of any advantage to the appellant, for without an interrogatory and answer showing that the plaintiff had contracted to build a wood house, and there were none, any answer to the ninth interrogatory would have stood as a detached fact, and could not have directed the judgment, as against the general verdict. This interrogatory should not -have been put, unless others connecting it with the case had gone with it.
We perceive nothing in the answers to the interrogatories upon which the court below could have based a judgment contrary to the general verdict. True, some of the answers might possibly be construed as meaning that there was no contract, either express or implied, concerning the work, save that which was originally put in writing, the jury having found that there was no “ other made between the parties.” But such a construction would be unreasonable, and is not required by the language employed. It was not disputed on the trial, that some modifications of, and| changes and additions to the original plan of the building had been made at the appellant’s request. To this the appellant himself testified as a witness. The dispute was almost wholly concerning the extent and cost of these changes. Under such circumstances, it would be very unfair to
The judgment is affirmed, with three per cent, damages and costs.