This is a case involving the construction of a fire station in Tucson, Arizona. John R. Kulseth Associates, Ltd. (Kulseth) entered into a contract with the City of Tucson (Tucson) dated October 27, 1980, to furnish architectural services for the design of a structure known as Fire Station 7. On January 27, 1982, Chaney Building Co., Inc. (Chaney) entered into a contract with Tucson to build Fire Station 7. The contract contained a provision which required Chaney to complete the building within 245 days, but this provision was later extended 45 days by a contract change order. However, Chaney did not complete the building within the agreed upon time frame and as of February 28,1983, the building was 97% complete according to Tucson’s estimate for payment.
On April 28, 1983, Chaney received a letter from Tucson notifying Chaney that the building contract between the two parties was terminated as of May 5, 1983. The letter read in part, “[Tucson] will no longer accept your firm’s unending delay in completing the work in the above-mentioned project”. Tucson hired another contractor to complete the project using retention money withheld from Chaney’s contract. Tucson claimed certain work on the building was done improperly by Chaney, but the main factor relied upon by Tucson in the termination of the contract was the delay in the completion of the project.
Chaney filed suit against Tucson alleging breach of contract. Chaney claimed that it had performed its obligations under the contract and was owed $142,554.81 by Tucson. Chaney subsequently filed an amended complaint, again seeking relief against Tucson for breach of contract and against Kulseth for negligence. Chaney alleged that Kulseth negligently prepared the plans and specifications for the building and “as a result of errors in the plans and specifications [Chaney] incurred additional costs beyond the contract bid price”. Shortly before trial, Chaney, Tucson and Kulseth executed a stipulation for the dismissal of Kulseth from the action with prejudice. The record on review gives no indication of the underlying reasons for the stipulation.
A jury trial proceeded between Chaney and Tucson. Chaney’s first witness was its president, Earl Chaney, who offered testimony regarding problems with the plans and specifications. This subject was a designated topic in the parties’ pretrial statement. Three days into trial Tucson objected to testimony regarding the adequacy of the plans and moved for a mistrial. The motion was supported by Arizona case law on the subject of collateral estoppel. Tucson argued that since Kulseth had been dismissed with prejudice and the claim against Kulseth was for negligent preparation of the plans, it was error for Chaney to introduce evidence of defects in the plans. Tucson further argued that the dismissal of Kulseth operated as an adjudication on the merits “of the fact that there was no negligence” in the design plans. The trial *573 court overruled the objection and denied the motion for mistrial.
The trial continued with testimony from both sides introduced on the issue of whether the delays were attributable to Chaney or the plans. The instructions given to the jury made it clear that the claim asserted against Tucson was for breach of contract and a verdict was returned in favor of Chaney in the amount of $67,790.07.
The court of appeals reversed based on the trial court’s alleged error in refusing to grant Tucson’s motion for mistrial. We disagree with the appeals court opinion and vacate
Chaney Building Co. v. City of Tucson,
The issue before this Court is whether Kulseth’s valid dismissal with prejudice can be given collateral estoppel effect to bar litigation on the breach of contract claim between Chaney and Tucson. We hold it can not.
Under the doctrine of
res judicata,
a judgment “on the merits” in a prior suit involving the same parties or their privies bars a second suit based on the same cause of action.
Lawlor v. National Screen Service Corp.,
When an issue is properly raised by the pleadings or otherwise, and is submitted for determination, and is determined, the issue is actually litigated. Restatement (Second) of Judgments § 27 comment d. However, in the case of a judgment entered by confession, consent or default, none of the issues is actually litigated.
Id.,
comment e. A judgment entered by stipulation is called a consent judgment,
Cochise Hotels v. Douglas Hotel Operating Co.,
Tucson could have possibly raised the doctrine of collateral estoppel had there been any litigation of issues between Chaney and Kulseth.
Standage Ventures, Inc. v. State,
We would agree with the appeals court result if Tucson’s liability were solely derivative from that of Kulseth. In that situation a dismissal of Kulseth would prohibit an action against Tucson. If this were a case of
respondeat superior
and the only party left in the suit were the
*574
master, we would agree with Tucson’s position because an act of a servant done in the course of his employment is legally the act of the master.
Driscoll v. Harmon,
In the current action Tucson was sued for wrongful termination and breach of contract; Kulseth for negligence. We do not believe this was a case where Tucson’s liability was simply derivative from any liability of Kulseth.
Cf. Industrial Park Corp. v. U.S.I.F. Palo Verde Corp., supra
(multiple corporate defendants were so closely related to principal corporate defendant that their liability was derivative of that of principal);
Torres v. Kennecott Copper Corporation, supra
(master-servant relationship). Clearly the law allowed Chaney to assert a cause of action against Kulseth for negligence.
Donnelly Const. Co. v. Oberg/Hunt/Gilleland,
In
Donnelly,
we recognized that design professionals, such as architects, have a duty to use ordinary skill, care and diligence in rendering their professional services and must use their skill, care and diligence to provide sufficient and adequate plans.
A principle in construction law is that the owner (Tucson) impliedly warrants the adequacy of the plans and specifications supplied by the owner which he requires the contractor to follow. Thomas C. Horne,
Arizona Construction Law,
§ 107, at 39 (State Bar of Arizona 1978); The American Bar Association,
Construction Contract Claims,
117-118 (1978); The American Bar Association,
Seven Steps to Resolving Construction Contract Claims,
3.17; 6 Corbin,
Contracts,
§ 1338, at p. 349. A contractor is also not liable for damages which are the direct result of defective plans and specifications furnished by the owner.
Kubby v. Crescent Steel,
The evidence objected to by Tucson was used by Chaney to demonstrate that it was unable to perform in a timely manner in accordance with the contract due to inadequate plans. When Tucson terminated its contract, Chaney claimed it had substantially performed and the delays in completing the project were beyond its control. Chaney was entitled to seek the balance due under the contract on a breach of contract theory. The jury, as the finder of fact, decided that the delays were excusable on Chaney’s part and that Tucson did breach its contract with Chaney. We will not disturb this result. The opinion of the court of appeals is vacated and the judgment of the trial court affirmed.
