200 Pa. 230 | Pa. | 1901
Opinion by
Chandley Brothers & Company, the appellees, entered into a contract on July 11, 1898, with the borough of Cambridge Springs, “ to construct, build, equip and finish a complete system of water works on or before October first, A. D. 1898, in the borough of Cambridge Springs, Pa., in accordance with the specifications,” attached to and made part of the agreement. With the general plans and specifications submitted to bidders there were detailed specifications drawn under nine divisions, and bids could be made for each separately. The borough reserved the right to let the contract as a whole or by divisions. The whole of the work was given to the appellees. The several detailed specifications provided for different dates for furnishing materials and doing work ; but the whole work, as before stated, was to be completed by October 1, 1898. For failure to furnish machinery or complete work by the dates set forth in* the separate detailed statements, the contractors agreed to pay, * as confessed and liquidated damages, certain sums for every day’s delay—in one case $10.00, and in others $15.00 and $25.00 per day.
In paragraph twenty-eight of the general specifications and conditions of agreement, there is the following clause: “If the contractor fails to complete the work at the date specified, he shall forfeit to the board as confessed and liquidated damages, the amounts named in each of the detailed specifications for the different portions of the work.” By the term “board,” used in this paragraph, is meant the burgess and council of Cambridge Springs, Pa.
The contractors did not perform certain portions of their contract within the dates fixed, and, on the trial of the cause in the court below, the appellant asked that the different sums agreed upon as liquidated damages for the delay of the appellees be deducted from the sum claimed by them. Offers of the appellant in support of its alleged right to make these deductions were all overruled by the learned trial judge, apparently on the
Whatever powers the engineer had to settle disputes between the contracting parties are found in paragraph twenty-four of the general specifications and conditions of agreement, and nowhere else. That paragraph is as follows : “ Should any disagreement or difference arise as to the true meaning of the drawings or specification on any point, or concerning the character of the work, the decision of the engineer shall be final and conclusive and binding on all parties to the contract.” These words could not be plainer. They limit the final decision of the engineer to disagreements or differences arising as to the true meaning of the drawings or specification on any point, or concerning the character of the work. It is difficult to conceive how even the strained construction sometimes given by zealous counsel to written words could possibly extend these to the dispute before us. The claim of the borough of Cambridge Springs to deduct what the contractors agreed in each detailed specification should be deducted for delay, involves no “ true meaning of the drawings or specification on any point,” or “ the character of the work.” The claim means that the work was not done nor the materials furnished within the time agreed upon, and no question is raised concerning the character of the work; the contention simply is, that, in the face of the plain words of the contract, the contractors pay what they specifically agreed they would pay upon the happening of certain contingencies, which did happen. The very agreement of the parties, that the damages for delay should be considered liquidated, is conclusive on its face that that matter should not be referred to the engineer or any one else. In all cases where the decision of the
What we have said relates to the first eight assignments of error. The last four are not sustained. They do not seem to be pressed, and by them no error has been pointed out to us on the part of the court below. The only question involved is as to the power of the engineer to determine the claim of the borough for damages resulting from the contractor’s delay. This is frankly stated in appellant’s paper-book to be the only question raised, and we have so disposed of it. On the first eight assignments of error, the judgment of the court below is reversed and a venire facias de novo awarded.