60 Mo. 370 | Mo. | 1875
delivered the opinion of the court.
This was an action to recover possession of some lumber alleged to belong to the plaintiffs.
The plaintiffs were lumber dealers in Muscatine, Iowa, and . sold to one Ely a lot of lumber for $3,600, for which Ely paid itr cash $1,500 and was charged with the remaining $2,100. Ely was a carpenter and builder, and purchased the lumber to- be used in building a school house at Cameron, for the construction of which he was the contractor, Under a written contract with the defendant, the Board of Education. The lumber was forwarded to Ely, and by him hauled from the B. B. depot and placed on a lot belonging to the School Board, where tire school house was to be built. It does not appear •how much of the lumber was used in the building, from the ' month of May, when the contract was made and the building commenced, until the month of December, 1872, when tlie controversy upon which this action is based arose.
There is very little, if any, discrepancy in the testimony, except upon one point, which relates to a verbal contract between two of the board of trustees and Ely.
There was a written contract between the Board of Trustees and Ely for the building of the school house, which was to cost about $21,000. This contract is in the record. By this contract, which was dated May, 4, 1872, Ely was to build the school house and appurtenances described in it, and furnish all the materials and perform all the work according to certain plans referred to in the contract and under the supervision of an arehiteet named. The house was to be completed on the 1st of November, 1872. Charges were to be allowed by the architect, etc. The board was to pay Ely $20,789 in instalments as the work progressed, reserving ten per cent., etc., from the amount of the work done and materials delivered on the ground or in the building. These instalments were to be paid on certificate of the architect, etc. it was further provided, that for the materials used or to be used in 6aid building, ¡upon Ely’s filing his bond for $20,000, said bond being approved by the Board, the sifms required for said materials should be paid upon the written order of the architect, and when approved by order of the Board, should be paid to Ely.
This contract was duly executed, signed by the president of the Board and Ely; and on the same day Ely executed his bond for $20,000, as required by7 this contract. So far the facts were undisputed.
This statement is denied by Ely; but as the finding was for the defendant, it may be assumed to be correct.
It further appears beyond dispute, that the lumber bought, by Ely was put on the lot owned by defendant, where the building was to be erected, and was used by Ely as needed in the building.
In October, 1872, one of the plaintiffs came to Cameron to get the balance due the firm from Ely. He was informed by the treasurer of the verbal agreement which has been stated, and that Ely had been paid upon the estimates certified by the architect. At the suggestion of this member of the firm, a re-examination was made, and a mistake of $366 was discovered in favor of Ely, and the amount was paid to plaintiffs.
There is no dispute that the lumber when sent down from Iowa was put on the school lot where the building was to be erected, and remained there until this suit was brought. Upon this state of facts, the court declared the law to be as follows : •
1. That from the evidence it appears that the lumber in question was purchased by A. J. Ely for the purpose of erecting a public school building for defendant, in the town of Cameron, and was placed by him on the ground of defendant, and was inspected and received by a superintendent em*375 ployed by defendant, and estimates were made by said superintendent in said Ely’s'favor, which included said lumber and the freight thereon, and that said estimates were paid by defendants to said Ely, and that plaintiffs had notice of these facts before they purchased the lumber of said Ely ; therefore the finding and judgment must be for defendants.
2. If it appears from the evidence, that at the special instance and request of plaintiffs, defendant’s superintendent made a second estimate of said lumber, and that by said second estimate it was found that there was still due and unpaid a certain sum of money in addition to the amount found due upon the .first estimate, and that the amount found due and unpaid was paid by defendant to plaintiffs, and at their request, the finding and judgment of the court must then be for the defendant.
3. If it appears that subsequent to the signing of the written contract the defendant furnished Ely $3,000, with which to purchase lumber, before he was entitled to any money under said contract, and in consideration thereof said Ely agreed that all lumber purchased by him should be the property of defendant when delivered on defendant’s ground, and that plaintiffs had notice of these facts before they purchased said lumber of said Ely, the finding and judgment of the-court must be for defendant.
4. ' If it appears that the purchase of the lumber by plaintiffs of Ely, was conditioned upon the recovery of the debt against him from the defendant, and that plaintiffs did not give said Ely credit for the amount of said debt, the finding and judgment must he for defendant.
And upon these declarations of law, the court, to whom the ease was referred without a jury, fonnd for defendant..
Several instructions were asked by the plaintiffs, all of which were refused. These instructions, in substance, asserted that Ely was not an agent of the defendant, and there*, fore that the lumber bought, by him, as contractor, was his property, and the sale to the plaintiffs conveyed the property.
“ Where the contract is executory for the sale of articles not in existence,'bnt to be made or manufactured, no property passes to the orderer, until the thing is completely finished, and is either delivered to him, or is appropriated to 1ns benefit, set apart for him, and is accepted by him. Nor does it make any difference that the price is advanced, or that the contract contains a specification of the dimensions and other particulars of the thing to be made, and fixes the preeise mode and time of payment by months and days; since the agreement is considered as a bargain for an entire thing, and not for unfinished parts of it. So also, in such case, the maker would not ordinarily be bound to deliver to the purchaser the particular thing upon which he is engaged and intends for such purchaser, or which the purchaser supposes to be intended for him; but he may, if he pleases, dispose of it to some other person, and furnish another article corresponding to the specification or the contract. Bnt where the contract provides that the article shall be built under the superintendence of a person appointed by the orderer, the manufacturer could not compel the orderer to accept a thing'not constructed under the direction and approved of by the superintendent ; and therefore he eonld not sell to any other person than the orderer an article, the building of which had been so superintended, since, if he could, he would thereby be enabled to burden the orderer with the expense of employing a person again to superintend the building of another vessel. The faet, therefore, that a superintendent is appointed, is considered as an appropriation of the materials approved by him and used in the construction of the thing, and an appropriation of the thing so far as it is constructed.’5 (Sto. Sales, § 233.)
In New York and in Massachusetts the principle announced in Woods vs. Russell, that the appointment of a superintendent, and the agreement to advance money to the manufacturer as the building progressed, would thereby, (contrary to the general rule of law) invest the property in the orderer, is repudiated. (Andrews vs. Durant, 1 Kern., 35 ; Williams vs. Jackman, 16 Gray, 514; Briggs vs. “A Light Boat,” 7 Allen, 287.) In these cases it was held that the general rule of law was well settled, that under a contract for building á ship or making any other chattel, not in existence at the time of the contract, no property vests in the purchaser during, the progress of the work, nor until the ship or other chattel is finished and delivered. At the same time it was conceded that there were exceptions to this rule, growing out of express stipulations in the contract between the orderer and the builder, by which the building, as.it progressed, might vest in the purchaser from time to time. But théy denied that an agreement to pay the purchase money in instalments, as the work progressed, or a stipulation for the employment of a superintendent by the purchaser or orderer would operate to change the general rule of law, and vest the title in the orderer to so much of the chattel as was built.
The question, as these American courts declare, depends on the intent, to be inferred from an interpretation of the contract. If the intent of the parties to the contract is to invest the property in the purchaser during the progress of the work and before its completion, the courts will give effect
These principles relate to chattels, and have been chiefly applied in eases of ship building; but are equally applicable to builders of houses, so far as the materials for the building-are concerned, with the exception that when the materials are once put in the building and thereby become a fixture, the owner of the land, who employs the contractor, of course owns the building on it, or so much of it. as is completed.
Adopting then the modification of the English rule, as laid down in Woods v. Russell, made by the courts in New York and Massachusetts, in accordance with well settled principles, and conceding that a special contract may change the general rule of law, and transfer'to the orderer property in the materials tó be put into the building by the contractor, it is evident that in the case now before the court, the main question decisive of the merits of the ease is, whether, under the contract between the contractor and the School Board, the lumber in question was transferred to the Board, so soon as bought by Ely and placed on the lot where the school house was to be built.
The testimony in this ease, on this point, has been copied. If the contract executed by the Board and Ely bad embraced such a provision as is proved by the testimony of one of the members, the case would be clear. But the written contract in evidence madé no such provision. On the contrary, the contractor, Ely, was to furnish materials, and the board might advance to him money to buy them, on the certificate of the architect. To secure the board against misappropriation or other failure of the contractor, a bond in $20,000 was required of the contractor. The contract was duly signed according tó law, and the bond was accepted according to law.
At the same meeting of the Board at which the contract was executed, it appears that Ely applied for an advance of $3,000, to enable him to buy lumber. This advance was made, biit upon the condition that the lumber so bought
The 13th section of the Act, concerning schools, Art. 2 provides that, “all regulations, orders, resolutions and other acts of said Board may be proven in all courts and places, either by a sworn copy thereof, or a copy certified by the president and secretary, and authenticated by the seal of the Board.”
But there are, no doubt, other modes of proving the action of the Board. In this case their action is established by a written contract. The question is whether a parol contract made by one or two of the members could alter the written contract, on the same day it was executed, or whether the whole Board could do so, without a record of such resolution.
There is no doubt that written contracts may be altered by subsequent parol agreements, in relation to the time of performance or in regard to matters about which the written contract makes no provision. Butin this case the written contract makes ample provision for advancement of money to Ely for materials ; and, for security for such advances, requires his bond for $20,000. The parol contract requires an additional security of a transfer of the materials to defendant. The two contracts were inconsistent. They were made on the same day and cannot be reconciled. By the written contract any amount might have been advanced by the Board, for materials, if the architect so certified. The amount, of $3,000 was advanced by the Board to enable-the contractor to buy lumber, on the condition that the lumber bought and delivered should belong to the Board. This would make the contractor a mere agent or servant of the Board, so far as materials to the value of $3,000 are concerned, and would give to the Board the property in such materials, so soon as they were delivered on the lot where the house ■ was to be erected. By the written .contract, the contractor was bound to furnish materials, and such materials were
It might be questioned if the School Board had any authority, under tiie law, to invest $3,000 in lumber, and risk the chances of its being used in a building which they bad authority to have built. But, conceding that they had the power to do this, the contract should have been in the form, and authenticated in the mode, required by the general and special law. The loose conversation between members of the Board and the contractor, after a formal execution of a written contaact between the Board and the contractor, cannot •be allowed to vary the written contract. It would be unsafe to both parties to allow such parol variations; and the well settled rules of law do not permit such proofs. The third instruction, therefore, given by the court for the defendant, was erroneous, and this instruction was upon a point on which the merits of the ease mainly depend.
The first instruction seems to be based on the law applicable to chattels, as declared in the case of Woods vs. Bussell, and followed by the compilers of elementary treatises in this country. It, however, goes a step beyond, in assuming tlmt' the materials on the ground, designed to go into the building
The lumber-bought of the plaintiffs in this case, it seems, cost $600 more than the money advanced by the defendant. It does not appear whether all the lumber was needed for the school building or not. By the terms of the contract, the building was to have been completed in November, 1872, and it was on the 28th of December, 1872, that the plaintiffs, or
The second instruction given by the court was based on a sripposed estoppel, produced by the act of one of the plaintiffs, in receiving some $300 from the treasurer, in October, which was, on a re-examination of the accounts between Ely and the Board, found to be due to Ely. We are unable to see any ground for such an application of the doctrine of estoppel. The plaintiffs were creditors of Ely, and not unwilling-to collect the debt, or so much of it as could be obtained from Ely or from the defendant who employed him. Their reception of $300 dollars from the treasurer, which upon reexamination of Ely’s account was found to be due him, was no admissiou in regard to the property now in dispute; in fact, had no connexion whatever with it. The same observation will apply to the fourth instruction, which directs a verdict for defendant, because the plaintiffs never entered a credit on Ely’s account, when they took the bill of sale he gave them for the lumber; in other words, because they did not know whether their title under this sale would he valid or not.
They filed a mechanic’s lien on the building, which was also a matter of law about the efficacy of which they might be mistaken.
The merits of the case, it is obvious, depend on the propriety of the. 3d instruction, which lias been already examined and passed on. It may be added to what has been said on this instruction, that under our statute concerning fraudulent conveyances (Wagn. Stat., 281, § 10) a doubt might be entertained in regard to the power of Ely to transfer the title of this lumber to the Board, so as to preclude bis creditors, by the verbal agreement testified to, without any visible change in the possession, unless Ely is to be regarded, so far as this transaction is concerned, as a mere agent or servant of the board.
It is clear from the contract formally entered into between the board and himself, that lie occupied no such position, but
The judgment must be reversed and the'cause remanded ;