26 Or. 428 | Or. | 1894
Opinion by
1. The plaintiff in his claim of lien gives an itemized statement of the several amounts due under the original contract, and the amounts claimed to be due for the alleged extra work, and also the payments made thereon, except one of two hundred dollars, and by deducting the sum of the credits from the sum of the charges, seven hundred and two dollars and twenty-five cents is found to be due; but in his claim he demands only five hundred and two dollars and twenty-five cents, and from said omission it is
2. The original contract provided that the defendant might make such alterations in the plans or specifications as he desired, and it was agreed that if any dispute arose respecting the true value of any alteration or work added or omitted, the same should be valued by two competent persons, one to be selected by each party, and if the persons so selected could not agree, they had authority to name an umpire, whose decision should be binding on all parties; and from this provision of the contract it is contended that no suit to foreclose said lien could be maintained until the plaintiff had attempted to ascertain the amount due in the manner therein provided. The plain
3. This brings us to a consideration of the claims of the respective parties. An examination of the evidence shows that plaintiff’s claim for cleaning the walls of said building, fifty dollars, should be disallowed. The specifications, which were made a part of the contract, require the plaintiff to “rub down all brickwork on street sides,” and while he used acids for that purpose we think the work comes within terms of the contract.
4. This is also true of the claim for changing four chimneys from common to pressed brick, twenty-eight dollars. "When the original contract was modified so as to require pressed brick for the walls of the building, it must necessarily have included the chimneys which are a part of these walls, and hence not extra. The plaintiff’s claim for building three extra pressed brick chimneys, seventy-five dollars, must be modified upon the testimony of his brother, who, when called as his witness, testified that the reasonable value of such work is only forty dollars. While there is quite a conflict of evidence, we think it shows that the other items of plaintiff’s claim are not embraced within the terms of the contract,- are reasonable, and should be allowed, thus making the amount due him
5. The contract required the plaintiff to keep the brickwork straight and plumb; and the evidence shows that he did not comply with this requirement. The walls are not what they should be, but the defects in that respect were probably caused by building the extra story without materially strengthening the foundation, for which plaintiff cannot be held responsible.
6. The defendant’s claim for insurance, interest on money advanced, damages for delay in completing the building, and for failure to put cement in the mortar cannot be allowed. True, the specifications call for the use of cement in the mortar, but the contract provided that the brick should be laid in common mortar.
7. The most difficult question in the case arises out of the defendant’s claim of sixteen hundred and sixty-seven dollars as damages alleged to have been sustained by reason of defective plastering. The specifications, among others, contain the following provisions: “Plaster all walls and partitions, and second, third, and fourth-story ceilings, one good, heavy coat of brown mortar, consisting of three barrels of clean, sharp sand to each one of fresh
8. The court awarded the plaintiff ten dollars as attorney’s fees, and required him to pay one half of the costs, and this he contends was an abuse of discretion. It seems to us, in view of the evidence as to the careless and negligent manner in which plaintiff did the plastering, that the decree in this respect was equitable. The decree of the court below will be here modified to correspond with this opinion. Modified.