History
  • No items yet
midpage
Century Marine Incorporated v. United States
153 F.3d 225
5th Cir.
1998
Check Treatment

*1 concurring: KING, specially Judge, Circuit v. Board Fremaux pending; appeal Comm’rs, 96-1225, 1997 WL No. by opinion in Although I am our troubled **3-4, at *8- LEXIS U.S. Dist. (5th Hosp., v. Memorial Martin 1997) (E.D.La. (applying Mar Mar. *10 Cir.1996), outcome I it controls the believe entering concluding hospital’s tin here, Judge and I therefore concur foreseeable). contract was into an exclusive panel. opinion Smith’s Florida, both court cases from In two district wrongly decid says were of which St. Luke’s broadly and

ed, Parker the courts construed anticompetitive a broad swath immunized Fla. Clin by hospitals. See Central conduct Bd., County Hosp. F.Supp. ic v. Citrus (M.D.Fla.), aff'd, Cir.1989) Hospital Dev. & (unpublished); Dist., Hosp. Corp. v. North Broward Serv. (S.D.Fla.1985). F.Supp. INCORPORATED, MARINE CENTURY

Plaintiff-Appellant, D. sum, appellees are that the we conclude America, STATES of UNITED exclusive immunity. The to Parker entitled Defendant-Appellee. reasonably fore-

nature of the contracts legislature. As to by the Louisiana seeable No. 97-20281. practices, alleged unlawful trade other while court that agree with the district we Appeals, Court of United States may engaged have “cutthroat” North Oaks Fifth Circuit. practices trying and “hardball” business Oaks, it is conduct patients Aug. lure to North 1998. reasonably result is a foreseeable statute. Louisiana

IV. if argues that even North Luke’s St. immunity, Quo to Parker is entitled Oaks not. private it is a actor—is rum—because 46:1055(B) disagree. La. Rev. We Stat. “may hospital districts service provides agreement with a special into services enter hospital manage including ... a any person, ad manage, operate, and ... ment firm hospitals, part hospital or minister a thereof, the commission under the control of dis hospital’s service the benefit of the agreement Because North Oaks’s

trict.” Quorum expressly authorized statute, Quorum operates and because agent the benefit hospital as an and for district, protected Quorum is the service immunity.5 North Oaks’s Parker AFFIRMED. Oaks’s, argument this failed to raise Quo- North Although in its brief St. Luke's hints court. independent before the district may economic interests rum have *2 compensation additional

its claims repair vessel Administration Maritime Transportation Department con- terminated (“MARAD”). MARAD *3 failing in Century’s default of tract because speci- the time within work complete to filed suit Century contract. fied have the seeking to the United against termi- ato converted default for termination convenience; Government’s for the nation the amount to addition payments and for the termi- under Century paid MARAD trial, dis- a bench After contract. nated Century’s demands rejected trict affirm. We prejudice. its suit dismissed trial contest the Century does appeal On contract that determination court’s Despité its for default. terminated properly it entitled Century argues bal- unpaid equal an amount recover contract of the price fixed full ance of unfinished of the completion of cost less the Century’s argu- the contract. work law established to well contrary ment Govern- Under regulations. federal contract fixed-price aof termination ment’s default, the Gov- contractor’s for contractor liable is not ernment Antici- work. or undelivered unperformed recovera- are not profits but unearned pated Government when by the contractor ble contractor’s for the contract terminates the Govern- of the convenience or for contention Century’s additional ment. also work is compensated be should rec- in the is warrant merit. There without Purcell, H. Papleacos, Wade A. Nicholas for lawin basis applicable ord and & Fussell, Wedge, Smotherman Shapiro, this claim rejection court’s Plaintiff-Appellant. GA, Atlanta, Martin, the merits. trial Justice, Dept, Myer, U.S. Glenn Peter Division, Washington, Branch-Civil Torts PROCEDURAL AND I. FACTUAL Defendant-Appellee. DC, for BACKGROUND Century and September contract into entered MARAD cargo renovation repair WASH BARKSDALE, MOUNT BENAVIDES S.S. tanks Before ballast the United Judges. DENNIS, INGTON, public vessel Circuit three Thereafter, issued States. Judge: DENNIS, in (“Mods”) Circuit modifications contract $1,050,000.000, value contract (“Centu- creased Marine, Inc. Century Appellant $8,521,910.000. amount total dismissal the district ry”), appeals When fell behind representative, schedule on the eer’s technical who testified 3, 1993, original May completion date of at trial. MARAD issued three additional Mods Based calculations on the Government’s completion Septem- extended the date until payment a final Mod MARAD made extensions, Despite ber these Cen- Century $409,023.56, com- representing tury fall continued to behind its work sched- pensation performed after the work all ule. When it became evident that progress payment before latest but complete timely, by could not the contract According to the was terminated for default. 8,1993, September letter dated MARAD ter- denying officer’s decision Centu- minated for default.1 At the time of ry’s administrative claims for additional com- termination, MARAD progress had made pensation, Century rep- payment this final *4 $5,903,135.50. payments Century to of On (1) payment progress for the made resented: 22, 1993, September the Government issued by Century prog- the time of its last between (“Mod 9”) Modification No. 0009 to con- payment ress termination of the contract and adjusted price tract that the contract (2) ($51,532.00); payment of of the balance work,

value of the unfinished and calculated retainage Century deducting owed to after progress payment Century the final to based ($285,539.06)3 procurement the excess cost of completed eventually on its work. MARAD (3) ; payment of funds withheld at the retained another contractor to finish Centu- legal depart- direction of the Government’s ry’s work.2 separate ment until a claim on another con- ($71,952.50). tract was settled

9,Mod admitted as a Government exhibit trial, percentage comple- July Century sets forth the of In a submitted “Re- item, adjusts quest Adjustment tion each Equitable of work the total For and For price by deducting contract the contract val- Conversion of a Termination For Default to a Century’s work, uncompleted Century’s ue of estimat- Termination For Convenience.” $1,260,861.00. Request Equitable Adjustment ed at In present- Mod For percentage completion part based the of in pay- ed administrative claim for additional Century’s percent completion figure on own ments of almost million under the con- $1.3 tract, provided progress payment Century’s in its allegations last re- based on quest prior MARAD' percentage submitted to one week MARAD had underestimated the termination, adjusted figure completion to for with this of finished work items in Mod during accomplished by Century work and that MARAD not was entitled to reproeurement final week of the terminated contract. The retain excess costs of from retainage in Mod 9 of the con- pay- Government’s estimate withheld from the final uncompleted Century Century’s Century tract value of work ment to thorough inspection wrongfully Century a also was based terminated. also assert- on. $21,254 videotaping per- of each item of unfinished work ed a claim for in extra work Volkmann, contracting pursuant Century’s offi- Request Richard formed For Regula required Acquisition ed contractor are still 1. Pursuant to the Federal tions, may, contracting repurchase the Government written notice officer shall the same ser- contractor, default to the terminate against vices the contractor’s account as soon as part fails to whole or in if the contractor in 49.402-6(a), practicable, § 48 C.F.R. and the specified perform in the services within the time any contractor is liable to the Government for any 48 C.F.R. contract or extension. the § acquiring excess costs incurred in services simi- 52.249.8(a)(1)(i). regulations which "Federal lar to those terminated for default. 48 C.F.R. authority upon grant are based 'have 49.402-2(e). § law, and, they applica if force effect ble, they deemed terms of the contract must be Acquisition Regulations, 3.Under the Federal therein, knowledge specifically out even if not set " "the officer shall use all retained charged the contractor.’ General of which is percentages progress payments previously O'Keefe, Eng'g Mach. Works v. & any progress made to the pay- contractor and (Fed.Cir.1993). completed ments due for work before the termi- liquidate Regulations, liability nation to Acquisition contractor's 2. Under the Federal § provided by Government.” the terminat- 48 C.F.R. 49.406. when the services to be dismissing judgment final rendered (RDOs). Finally, Delivery Orders the United against Century’s claims be default termination requested prejudice. for convenience. with termination to a converted con- 1994, the Government’s December In Mo- filed January On administrative a final issued officer tracting Findings Additional Make to Amend tion claims, denying decision made Fact, asserting that 48-page Century. This payments further had not claims on two case facie prima exhibits, supporting decision, attached (1) a States: by the United rebutted been allegation each in detail rebuts seven performed on work claim conclud- Adjustment, Equitable For Request (2) a $20,583; and in the amount RDOs Century’s “termination ing that due balance” “contract to a not entitled Century “is valid,” and that following resulting from $1,293,218.54 adjustment.” further computation: pursuant September $8,521,910.00 Amount Contract Modified 603, and § Act, U.S.C. Disputes Contract $6,492,159.46 Act, Deducts Admiralty Less-Payments U.S.C. Suits in the the United sued seq., et $714,187.00 performed Less-Work *5 Claims, transferred which of Federal Court $22,345.00 058 Item and credit of Texas.4 Less-Tow District Southern to the case the coun file a not to elected States United The $1,293,218.54 Due Balance Contract dam liquidated Century for against terclaim entered court 4, the district a con against 1997 March On recoverable are ages, which Motion Century’s denying 48 See default. order an terminated tractor 49.402-2(e). Fact. Findings of 49.402-7, 49.402-6(c), Additional Make or §§ Amend C.F.R. judge in to a Century appealed. tried were Century’s claims December presented REVIEW court, Century OF II. STANDARD district In the ad- in its claim the supporting no evidence of fact findings The district Equitable For Request level

ministrative “clearly errone the under reviewed be must to recover was entitled Adjustment 52(a). A P. R. Civ. Fed standard ous” the reprocurement costs excess the “clearly errone to be said fact finding of Century’s from had deducted Government evidence notwithstanding there when, ous” Contracting Of- K of the retainage. Exhibit upon exam reviewing it, court support the only evidence decision, was which ficer’s with the is left evidence entire of the ination reprocurement excess the Government’s mistake that a conviction firm and retainage withheld definite amount costs v. Co. Oil Justiss committed. trial been at has termination, withdrawn was 1057, F.3d Corp., 75 admissibility. Refining Kerr-McGee objected to Cir.1996) (citing (5th United 1062 is- 1997, court 3, district January On 364, Co., 333 Gypsum United lawof conclusions of fact findings sued (1948)). With 525, 92 L.Ed. 395, 68 S.Ct. claims, finding that Century’s rejecting reached legal conclusions respect termination States’ United so facts of the basis on trial court breach justified re novo a de found, will conduct this valid no contract, and that 1034, 1045 Lancaster, F.3d Reich view. con- adjustment an Cir.1995). (5th 1997, 3, the district January Also tract. Avon Corp. v. Steel Bethlehem Act, Circuit. Federal sub- Disputes Contract § 4. Under Inc., Shipyards, appeals of administra- dale jurisdiction ject matter contracts 1992). maritime con- Government involving maritime federal Cir. tive decisions Disputes Act. courts, governed rather Contract district the federal otherwise vests in tracts (now Court of Claims the Court of at 94. Id. than Appeals for Claims) the Court Federal CO INS o supplies perform tor fails to deliver the or to

III. DISCUSSION specified in the the services within the time appeal, does not contest the On § a ter contract. 48 C.F.R. 49.402-1. Under court’s determination that is not mination for the.Government the contract for properly terminated Centu- costs on undeliv liable for the contractor’s Century reurge its ry’s Nor does default. 49.402-2(a). In con ered work. 48 C.F.R. MARAD had level claim that administrative trast, fixed-price terminated retainage an excessive amount withheld Government, for the convenience of the Century. Century payment from the final compensate should the contractor settlement judgment argues only district court’s that the fairly actually and for the for the work done denying its claims for the “contract balance” preparations por terminated made for the clearly and extra work was erroneous and contract, including a reasonable tions of the (1) Century made must be reversed because: profit applicable to that work allowance for prima at trial for its contract facie case 49.201, §§ preparations. 48 C.F.R. claims; (2) MARAD balance and extra work consequen Anticipatory profits 49.202. Century’s proof failed to rebut on these damages not be allowed under ei tial shall (3) claims; the district court made no ex- ther a termination for convenience or a ter claims; press findings on each of these mination for default of a contract. (4) findings implied no such can be 49.201, 49.202, 49.402-2; §§ See C.F.R. implied finding supported by is not. Co., States, Mega. Constr. Inc. v. United evidence. (1993); Fed. Cl. G.L. Christian & States, Assocs. v. 160 Ct.Cl. A. “Contract Balance” Claim (1963), denied, cert. 375 U.S. Century contends that it made out a (1963). 444, 11 L.Ed.2d 314 84 S.Ct. recovery prima facie ease for of a “contract Consequently, as a contractor ter *6 $1,293,218.54 $768,- balance” of either or cannot, Century minated for as a undisputed 889.54. It is that the total law, “unpaid matter of recover the balance” contract, fixed-price including amount of the completion” of the contract less the “cost of modifications, $8^521,910.00, all and that the work under the contract. To allow of $6,492,159.46 paid MARAD for recovery permit would to do such completed prior Century’s work to termi viz., directly, indirectly what it could not do default, leaving unpaid balance nation for anticipated profits but unearned af recover $2,029,750.54 of under the contract at that ter the contract has been terminated because Century presented time. MARAD and con right of its A contractor’s to default. recover flicting expert technical evidence as to the anticipated profits only if for arises the ter completing estimated cost of the contract: by mination of the contract the Government $736,532.00 Century’s estimate was and wrongful and a is constitutes breach. G.L. $1,260,861.00. Consequently, MARAD’s was Christian, (citing 312 F.2d at 423 asserts, subtracting the esti Behan, 338, 346, 81, v. 110 4 S.Ct. completing mated cost of the work under the (1884); Spea 28 L.Ed. 168 United States v. balance, Century unpaid contract the from rin, 132, 138, 187, 248 U.S. 54 Ct.Cl. 39 S.Ct. viz., difference, $1,293,- entitled to the either 59, (1918); 63 L.Ed. 166 Broadbent Portable $768,889.54,depending 218.54 or on whether States, Laundry Corp. v. United 56 Ct.Cl. the or the MARAD estimate is used. (1921)). Any recovery profits by of .Century’s contractor on a contract terminated be argument lacks a sound basis in cause of its own default is limited to earned generally law. Termination default is for actually profit performed prior on work to exercise of the Government’s contractual Constr., Mega the termination. 29 Fed. Cl. right completely partially or terminate a at 475. contract because of-the contractor’s actual or

anticipated perform failure to its contractual Century’s B. Claim For Extra Work 49.401(a). obligations. The 48 C.F.R. right Century argues Government that the district has the to terminate legally findings if the contrac- court’s and conclusions are for default “extra performed which orders no ex- made the court insufficient court The fractures. repair weld work” work extra addressing its finding press “there that conclusion legal reached by also finding implied claim, and that adjustment equitable for an sup- valid basis is not no issue extra work court Century’s gen- rejecting contract.” by evidence. ported adjustment, which for eral 52(a) Rules Federal Rule claim, the dis- work the extra encompassed ac all “[i]n provides Procedure of Civil Century was impliedly found court trict ..., jury without upon the facts tried tions any other for compensation entitled not and specially facts find the shall the court work. extra there of law its conclusions separately state ” findings findings of fact of of 12-page articulation court’s district The The on .... sufficiently court to this law allows of law and conclusions fact and conclusions and bases factual legal and state adequately factual ascertain detailed decision, thereby providing a denial of court’s the district court’s for legal district bases appellate work, thereby pro- predicate sufficiently extra definite Century’s claim Dallas, F.2d City predicate for v. sufficiently Chandler definite viding review. 52(a) Cir.1992). “exacts (5th But Rule im- The court’s appellate review. proper tracing slavish claim is nor detail extra work punctilious neither denial plied evidence, witness particularly issue issue the claims fully supported Reli Corp. v. Navigation percentage Burma forth sets witness.” which Mod (5th orders; M/V, delivery ant for unfinished Seahorse completion Herzog, 2 decision, v. Cir.1996) Schlesinger pro- (quoting which contracting officer’s Cir.1993)); (5th also United see denial 135, 139 MARAD’s F.3d reasons vides detailed Inc., Assocs., work; Realty and the Northside claims Cir.1973) (“ (5th ‘Courts contracting offi- Volkmann, 5n. testimony F.2d or exegetics, parse testified indulge in who representative, need technical cer’s hy videotaped nuance each every fact and inspected personally declaim he Shrimp Co. King re- ”) he (quoting work pothesis.’ Century’s unfinished Gulf Cir.1969)). Wirtz, 90% of drafted searched Billy if the is satisfied the assistance rule The decision officer’s a clear reviewing testi- employee who give the findings Greer, another *7 the decision. basis understanding of the at trial. fied at 656. F.3d Navigation, 99 Burma argument reject doing, we so spe a to make judge fails a If a trial is decision contracting officer’s the that fact, re the particular a finding on used as cific cannot be therefore “pleading” and court the that may assume im- viewing court trial court’s evidentiary support its with finding consistent a made claim impliedly plied denial find implied Act, long as the holding so Disputes general Contract the work. Under In re the evidence. make supported ing required not contracting officers Corp., made, they Servs. Mortgage fact, but, if Texas findings of specific Cir.1985); v. Gilbert pro- 1068, 12 any subsequent 1075 n. in binding not be “shall (5th Cir.), 1389, However, 605(a). 1393 Sterrett, F.2d § 509 41 U.S.C. ceeding.” 373, 46 951, 96 S.Ct. denied, 423 U.S. Act Disputes cert. nothing in Contract the there (1975). contracting offi- 288 L.Ed.2d the use prohibits that in as evidence conclusions findings cer’s factual According to the Cupey proceeding.5 novo de subsequent a law, Century and conclusions findings States, Home, Inc. v. United Nursing Bajo delivery ten valid the compensated for been 609(a)(1), action the where Court), § that, U.S.C. 41 provides Disputes Act Contract 5. The claim, in accordance proceed de novo on a "shall a decision contracting renders officer 41 U.S.C. appropriate court.” directly on the bring rules may an action a contractor 609(a)(3). Federal Court of United in the Claims (formerly the United Claims (1996) (“[T]his contract and the unpaid balance of the court 36 Fed. Cl. completing the unfinished work under by a con cost of and law decided the facts reviews that a default- the contract. It is well settled to other evidence be tracting officer similar it[.]”). anticipated but v. cannot recover Accord Lathan Co. United ed contractor fore (1990) (“This judgment States, profits. Accordingly, court unearned 20 Cl.Ct. [contracting findings AFFIRMED. officer’s] court is may weigh the of the district would other evi conclusions as it States, dence.”). Wilner See BARKSDALE, HAWKINS RHESA (Fed.Cir.1994) (en banc) 1397, 1403-04 concurring: Judge, specially Circuit overruling pre-Contraets Dispute (expressly judgment being AF- I concur in the holding contracting offi that a precedent Act that, FIRMED, would do so on the basis but strong presump “constitutes cer’s decision findings of pursuant to the district court’s ... evidentiary admission albeit tion or an law, underly- and the fact and conclusions of rebuttal,” cautioning subject but (es- they ing upon which are based evidence “suggest[] that a contract opinion does pecially, modification No. 009 and the Gov- place in ... ing final decision has no officer’s contacting response written ernment officer’s Claims”). litigation in the Court of Federal adjustment), request finder-of-faet, Therefore, in its role as presented in this Marine’s claims contracting may give the offi district court fail, primary claim that it to include its weight, cer’s administrative determinations paid performed. which it was not for work Constr., Mega not deference. 29 Fed. Cl. claim, Concerning primary the refer- Corp. Camera v. Nation Universal Cf. concerning an- majority opinion Bd., 474, 493-94, ences al Labor Relations 340 U.S. profits (1951) ticipated but unearned seem wide (holding 95 L.Ed. 456 S.Ct. “lost-profit” mark. claim is not Such nonbiriding findings of an NLRB and, Marine; contrary by Century raised may be considered in a sub “trial examiner” approach majority, I would taken sequent appeal to establish whether an em implied that this is the indirect or not assume supported substan ployee’s removal was To Roudebush, position thrust of the asserted here. do evidence); tial Chandler view, results, majority my as the has done n. 48 L.Ed.2d S.Ct. reaching in this court outside the record— (1976) (holding prior administrative not, cannot, something we should indeed do. ulti findings can be used as evidence of the subsequent mate matters at issue in a de proceeding).

novo

Accordingly, we conclude that preclude Disputes Act does not Contract decision as use of the officer’s *8 of the ultimate matters at issue in a evidence proceeding, provided subsequent de novo given or a rebuttable that it is not deference In the Matter of: Charles presumption of correctness. ENGLAND, Debtor. IV. CONCLUSION PRITCHARD, Gregg Appellee, J. Having reviewed the record consid- Century’s arguments, ered all of conclude we commit

that the district court did not TRUSTEE, Appellant, finding fact in error of law or clear error of rejecting and in prejudice. As for claims with PALMER, P.C., Appellant. PALMER & argument, “contract balance” we conclude Wesley R. In the Matter of: there is no basis in law for a defaulted ENGLAND, Debtor. contractor to recover the difference between

Case Details

Case Name: Century Marine Incorporated v. United States
Court Name: Court of Appeals for the Fifth Circuit
Date Published: Oct 29, 1998
Citation: 153 F.3d 225
Docket Number: 97-20281
Court Abbreviation: 5th Cir.
AI-generated responses must be verified and are not legal advice.