149 N.E. 580 | Ill. | 1925
This is an appeal from a judgment of the county court of Christian county dismissing a proceeding brought by appellant under the law of eminent domain to acquire the right to damage the property of appellees by causing the same to be overflowed at various times during the year by reason of the construction and maintenance of a dam across the south fork of the Sangamon river, which flows adjacent to the property sought to be damaged.
Appellant is an Illinois corporation engaged in generating and selling electricity to various municipalities, corporations and private individuals in central Illinois, and in so doing is a public utility within the meaning of the Public Utilities act and subject to the authority of the Illinois Commerce Commission, and as such public utility the right of eminent domain is conferred upon it when necessary for the construction of any alterations, additions, extensions or improvements ordered or authorized by the Commerce Commission under the provisions of the act. (Smith's Stat. 1923, chap. 111 2/3, sec. 59.)
The Sangamon river is a stream over which commerce cannot be carried on in the customary modes in which such commerce is conducted by water, and is therefore not a *68
navigable stream and is not among the public waters of the State, nor can it be made navigable by mere legislation. (Hubbard v. Bell,
In 1913 the appellant acquired the title to a forty-acre tract of land on the same river further down the stream than the lands of appellees, and constructed thereon a generating station for the generation and distribution of electrical current by means of transmission wires, such station to furnish light and power to individuals and municipal corporations. To provide for a continuous supply of water for the operation of its plant appellant constructed a dam in the river about four and a half feet high, and later added thirty inches more to its height by a superstructure, making the top of the dam about two and a half feet below the top of the banks of the stream. Certain riparian owners, among whom were some of appellees, claimed that the obstruction to the flow of the water by the dam caused the stream to overflow oftener, the overflow to reach parts of their lands which had not previously been subject to overflow, and caused the water to stand longer on their lands than it had previously done, thereby seriously damaging their lands for cultivation, and brought suit for a mandatory injunction to require appellant to remove the dam and obstructions to the natural flow of the water. A decree was entered in the circuit court granting the relief claimed, which decree was affirmed by the Appellate Court, and thereafter by this court in Deterding v. Central Illinois Service Co.
It is contended by appellees that in the former suit it was held, in effect, that the Commerce Commission had no jurisdiction to enter the above order. This is a misconception of our former holding. That question was not involved in the former suit, and the holding there was, that under the circumstances of the case the questions involved in that suit were proper questions for the court and not for the Commerce Commission.
It is contended by appellees that the judgment in the former suit ordering the removal of the dam is res judicata in this suit as to the right of appellant to maintain the dam. The general truth of the proposition that where a fact necessarily involved in the litigation has been decided in a suit and again becomes a matter in issue by the same parties in a subsequent suit the former judgment is conclusive as to such matter, is well established. (Buerger v. Buerger,
It is contended by appellees that if the Public Utilities act be so construed as to give to appellant the right of eminent domain the act must be held to be unconstitutional, as authorizing the taking of private property for private use and as embracing more than one subject. An act having a single, general subject indicated in the title may contain any number of provisions, no matter how diverse they may be, so long as they are not inconsistent with or foreign to the general subject, and may be considered in furtherance of such subject by providing for the method and means of carrying out the general object. (People v. McBride,
It is contended by appellees that the petition filed in the county court did not sufficiently describe the land sought to be taken. By this proceeding no lands were sought to be taken. The petition alleged that appellees' tracts of land had certain easements appurtenant thereto relative to the flow of water in and over the land of appellant, which said easements would be interfered with by the installation of the dam, and that it was necessary that petitioner acquire such easements as would be interfered with by the maintenance and construction of the dam. The petition contained a legal description of the land on which the dam is located and of the lands of the respective land owners and of the elevation of the dam. Upon hearing of the motion appellant filed a plan of the concrete dam, a profile of the river showing elevations of the banks and bed and a topographical survey of the lands of appellees. We are of the opinion that the provisions of the statute were sufficiently complied with in this respect by appellant.
Many other contentions are made by appellees, but as they are all answered by the views herein expressed and by the authorities cited in this opinion they will not be discussed in detail.
Upon the record in this case appellant clearly had a right to maintain its condemnation suit, and the court erred in dismissing it.
The judgment of the county court is reversed and the cause remanded to the county court of Christian county, with directions to overrule appellees' motion to dismiss the petition.
Reversed and remanded, with directions. *72