OPINION OF THE COURT
The question presented to us is whether a federal court in a Pennsylvania diversity action should decline to exercise jurisdiction because of the contractual provisions limiting the forum in which relief can be sought.
Plaintiff, Central Contracting Company, a Pennsylvania corporation, was employed as a painting subcontractor on the North View Heights Housing
Defendant moved to dismiss the action under Rule 12(b) (6) on the ground that the complaint failed to state a claim upon which relief could be granted. Its motion also relied upon the provisions in the subcontract that it should be construed pursuant to the laws of the State of New York and that any action brought pursuant to it should be limited to the courts of New York County, New York. Defendant further moved for a stay of the proceedings pending arbitration, in reliance on the provisions of the contract for the arbitration of disputes, which was to be held within the City of New York subject only to the jurisdiction of the Supreme Court of the State of New York and the appellate courts of that state.
The court below granted the motion to dismiss on the ground that the contractual stipulation limiting jurisdiction to the courts of New York County was valid and reasonable. This action made it unnecessary for it to decide the motion 'to stay pending arbitration. Central Contracting Co. v. Maryland Casualty Co.,
Section 45 of the plaintiff’s subcontract with the general contractors provides that the contract shall be construed under the laws of the State of New York and contains the subcontractor’s agreement to limit actions thereunder to the courts of the County of New York. It provides: “The rights of the parties shall be construed pursuant to the Laws of the State of New York. The Subcontractor agrees that it will not commence any action, whether in law or in equity, against the Contractor or its sureties on bonds, if any, because of any matter whatsoever arising out of the alleged breach or performance of this subcontract agreement, in any Courts other than those in the County of New York, State of New York, and the Subcontractor expressly waives any and all rights the said Subcontractor might have by reason of the aforesaid bond provisions, if any, or by reason of any other cause whatsoever, to bring said action in any other court. The rights herein given the Contractor shall also be deemed for the direct benefit of the aforesaid sureties, if any, with the same force and effect as if they were parties hereto.”
Additional light is shed upon this section by the provisions of the contract relating to arbitration. Section 54 provides that with certain exceptions all disputes arising out of the agreement shall be submitted to arbitration. Section 55 provides for the manner in which arbitration shall be carried out. After
The validity of Section 45 of the subcontractor’s contract recently was reviewed by the Supreme Court of Pennsylvania in the action by this plaintiff against the general contractors. The court there reviewed the earlier Pennsylvania decisions and announced the modern rule which is to prevail in Pennsylvania. “The modern and correct rule is that, while private parties may not by contract prevent a court from asserting its jurisdiction or change the rules of venue, nevertheless, a court in which venue is proper and which has jurisdiction should decline to proceed with the cause when the parties have freely agreed that litigation shall be conducted in another forum and where such agreement is not unreasonable at the time of litigation.” Central Contracting Co. v. C. E. Youngdahl & Co., Inc.,
We need not consider whether in this diversity case we are bound to apply the Pennsylvania rule, for both federal and state courts have increasingly in recent years recognized the same principle which the Supreme Court of Pennsylvania has now adopted.
The Pennsylvania rule, therefore, represents the correct principle, and we accept it and apply it here. This brings us to the question whether the provision that the action must be brought only in the courts of New York County is unreasonable.
On the face of it there is no unreasonableness in the provision. Two of the three general contractors were New York corporations. The provision is tied in with the requirement that the rights of the parties should be construed pursuant to the laws of the State of New York and that disputes should be arbitrated in the City of New York subject to the judicial supervision and review of the Supreme Court of New York and the appellate courts of that state. Judge Marsh in the court below noted that the forum in New York is only 400 miles from plaintiff’s home office and that this would hardly impose an unreasonable burden upon it. Affidavits by the parties present some fragmentary information on the subject but they are not enough to rise to the dignity of substantial evidence of unreasbnableness. Under Pennsylvania law the burden is on the plaintiff to prove the unreasonableness of the provision. Central Contracting Co. v. C. E. Youngdahl & Co., Inc., supra at 134,
We are mindful that cases may be imagined in which the requirement of a contract limiting resort to a single forum may be the instrument of injustice. But such a provision does not oust the jurisdiction of the courts; in effect it merely constitutes a stipulation in which the parties join in asking the court to give effect to their agreement by declining to exercise its jurisdiction. There will always be open to either party the opportunity to present whatever evidence will move a court in the particular circumstances not to decline to exercise its undoubted jurisdiction. No such showing has been made in the present case.
Finally, plaintiff claims that it is not bound by the provisions of Section 45 of the contract. This it asserts on the ground that its president signed the contract without reading it after he was given only a few minutes to read it and
The Pennsylvania courts in Gianni v. R. Russell & Co., Inc.,
Plaintiff therefore is bound by the provisions of its contract, which it has failed to show are unreasonable, or inoperative because of any representation. The effect of the provision, of course, is not to foreclose a consideration of the merits of plaintiff’s case; on the contrary plaintiff will have an appropriate forum for its claim, either in arbitration or in a judicial proceeding.
The judgment of the district court therefore will be affirmed.
Notes
. Defendant was surety on a performance bond and a labor and materialmen’s bond along with two other sureties, each of whose limit of liability is in different amounts but all of whom agreed to be jointly and severally liable with each other and with the principal.
. The claim consists of $15,980.68 as the balance due under the original contract and two categories of claims for additional work consisting of $46,262.39 and $1,162.-80.
. The adoption of this modern view by the Pennsylvania Supreme Court was foreshadowed in its earlier decision in Nippon Ki-Ito Kaisha, Ltd. v. Ewing-Thomas Corp.,
. In the status in which plaintiff’s suit reached it the Pennsylvania Supreme Court did not decide whether Section 45 was reasonable. The court reversed because the lower court had held that the action had been improperly commenced by foreign attachment against a public housing authority and remanded the case for further proceedings, which would include a consideration of this question.
. Wm. H. Muller & Co., Inc. v. Swedish American Line Ltd. & T. S. S. Co., Ltd.,
Earlier cases such as Mittenthal v. Mascagni,
. See also Montgomery v. Levy,
. Amend v. Hurley,
