delivered the opinion of the court:
This case is before the court on defendant’s motion to dismiss on the ground that plaintiff has failed to bring itself within the provisions of Public Law 657, 79th Congress, 2d Session, 60 Stat. 902, (herein referred to as the Lucas Act), as amended by Public Law 773, 80th Congress, 2d Session, 62 Stat. 869, under which act the petition was filed.
In Centaur Construction Company, Inc., v. United States (No. 46242), 107 C. Cls. 498, plaintiff sued to recover from the United States upon the same contract involved in the instant case. On January 6,1947, plaintiff’s petition in that case was dismissed on the ground that its claims, which had in part been allowed by the contracting officer acting under the supposed authority of the First War Powers Act,
Plaintiff’s contract with the United States fixed intermediate completion dates for specific portions of the work, and this suit involves claims for the remission of liquidated damages and alleged extra costs on various portions of the contract. Of these claims only the one for the remission of liquidated damages for four days’ delay from October 21 to October 25,1940, falls within the time limits set by the Lucas Act.
That where work, supplies, or services have been furnished between September 16,1940, and August 14,1945, under a contract * * * for any department or agency of the Government * * * such departments and
agencies are hereby authorized, * * * to consider, adjust, and settle equitable claims of contractors, * * * for losses (not including diminution of anticipated profits) incurred between September 16, 1940, and August 14, 1945, without fault or negligence on their part in the performance of such contracts * * *.
Sec. 2. (a) In arriving at a fair and equitable settlement of claims under this Act, the respective departments and agencies shall not allow any amount in excess of the amount of the net loss (less the amount of any relief granted subsequent to the establishment of such loss) on all contracts and subcontracts held by the claimant under which work, supplies, or services were furnished for the Government between September 16,1940, and August 14,1945, * * *.
Sec. 3. Claims for losses shall not be considered unless filed with the department or agency concerned within six months after the date of approval of this Act, and shall be limited to losses with respect to which a written request for relief was filed with such department or agency on or before August 14, 1945, * * *.
Plaintiff’s failure to allege or establish that it incurred a net loss on the performance of its contract or contracts is, we believe, fatal to the maintenance of its action under the Lucas Act, as amended. Section 6 of that act, which grants
We have not discussed the other issues presented in-plaintiff’s brief in this case.because they do not bear upon the question of whether plaintiff has stated a claim under the Lucas Act.
The defendant’s motion is sustained and the petition is dismissed.
55 Stat. 839.