OPINION
This matter comes before the court on the application of CEMS, Inc. for attorney fees under the Equal Access to Justice Act (EAJA), 28 U.S.C. § 2412 (2000). Plaintiff alleges that it is entitled to an award of attorney fees and expenses under EAJA. More specifically, plaintiff argues that (1) the contracting officer assigned to this case at the Department of Transportation Federal Highway Administration (FHA), Western Federal Lands Highway Division “surrendered his or her authority to make decisions” during the administration of the contract; (2) that the contracting officer also “surrendered to others adjudication of claims submitted by CEMS;” and (3) that the government was not substantially justified in proceeding to trial on those claims on which CEMS ultimately prevailed. Plaintiff also alleges that the government should have recognized the “core failings of [the agency contracting officer] to administer the project or determine the claims... [and] should have earlier and more actively sought a global solution, but instead it compelled CEMS to adjudicate its claims at a cost that was overwhelming.” Plaintiff seeks $221,701.56 in EAJA attorney fees. After careful consideration of the record before the court and the applicable law, the court finds that the defendant is liable to the plaintiff for $57,058.64 in EAJA fees.
FINDINGS OF FACT
The facts of this case were fully detailed in this court’s lengthy November 3, 2003 opinion, CEMS, Inc. v. United States,
As a result of disputes which arose during performance of the contract, plaintiff filed multiple claims with the contracting officer. The plaintiff then filed several separate appeals before the Department of Transportation Board of Contract Appeals (DOTBCA). During the pendency of the plaintiff’s appeals before the DOTBCA, the plaintiff submitted another, comprehensive claim to the agency contracting officer, including numerous separate claims, some of which included separate pay items for changes, delays, and other allegations of acts or omissions by FHA, for which plaintiff requested an equitable adjustment under the terms of the contract. Following the denial of a number of plaintiff’s claims and separate bid items by the contracting officer, CEMS filed its complaint in this court. The plaintiff subsequently filed a motion to consolidate the DOTBCA appeals with this case, which the court granted.
On June 27, 2000, pursuant to a government motion to dismiss, this court dismissed a number of the claims filed with this court. On the first day of trial, the parties settled a number of additional claims and separate bid items. A large number of claims and individ
Plaintiffs EAJA application was filed in this court seeking attorney fees and expenses for work performed. Plaintiffs itemized statement indicates that it seeks fees and other expenses incurred from June 8,1999 to July 20, 2004.
DISCUSSION
I. EAJA Requirements
The EAJA provides that a judgment for costs “may be awarded to the prevailing party in any civil action brought by or against the United States____” 28 U.S.C. § 2412(a)(1). Section 2412(d)(1)(B) of the EAJA provides:
A party seeking an award of fees and other expenses shall, within thirty days of final judgment in the action, submit to the court an application for fees and other expenses which shows that the party is a prevailing party and is eligible to receive an award under this subsection, and the amount sought, including an itemized statement from any attorney or expert witness representing or appearing on behalf of the party stating the actual time expended and the rate at which fees and other expenses were computed. The party shall also allege that the position of the United States was not substantially justified.
28 U.S.C. § 2412(d)(1)(B). “The purpose of the EAJA is to ‘eliminate legal expenses as a barrier to challenges of unreasonable government action.’ ” Cmty. Heating & Plumbing Co. v. Garrett,
Thus, eligibility for an award of attorney fees and expenses in a civil action requires (1) that the claimant be a prevailing party; (2) that the government’s position viewed over the entire course of the dispute was not substantially justified; (3) that no special circumstances make an award unjust; and (4) that pursuant to section 2412(d)(1)(B), any fee application be submitted to the court within thirty days of final judgment in the action and be supported by an itemized statement. See 28 U.S.C. § 2412(d)(1)(A),(B); Comm’r, I.N.S. v. Jean,
II. Entitlement
Defendant concedes that plaintiff was the prevailing party in this action and is otherwise EAJA-eligible. However, because EAJA “was not intended to be an automatic fee-shifting device” in any given lawsuit where the applicant prevails against the government, the government may successfully assert a substantial justification defense to prevent recovery under EAJA. See Luciano Pisoni Fabbrica Accessori Instrumenti Musicali v. United States,
While the Supreme Court has cautioned that an evaluation of an EAJA application should not evolve into a “second major litigation,” Hensley v. Eckerhart,
During the course of a civil action, the government may take a number of positions, including positions on the merits, positions on pre-trial, trial and post-trial matters, and on appeal. Prior to 1990 many Circuit Courts of Appeal, including the United States Court of Appeals for the Federal Circuit, allowed cases to be segmented during the substantial justification determination in order to award fees for a significant portion of the litigation in which the government’s position was not substantially justified. See Ellis v. United States,
Subsequent to the Federal Circuit’s decision in Ellis, the United States Supreme Court decided Commissioner, I.N.S. v. Jean,
Following the Supreme Court’s ruling in Jean, the United States Court of Appeals for the Federal Circuit directed trial courts to “look at the entirety of the government’s conduct and make a judgment call whether the government’s overall position had a reasonable basis in both law and fact,” including “the entirety of the conduct of the government. .. including action or inaction by the agency____” Chiu v. United States,
Several courts have found that the language in Jean does not require every argument made by the government to be substantially justified. See Marcus v. Shalala,
The United States Court of Appeals for the Eleventh Circuit, in contrast, held in United States v. Jones, that the United States cannot escape responsibility for paying EAJA fees unless all its claims were substantially justified. The Eleventh Circuit affirmed the District Court’s conclusion that: “[t]he United States may be required to pay EAJA fees to a prevailing party for the work on any claim that was not substantially justified.” United States v. Jones,
An Alabama District Court followed Jones, stating that Jones “stand[s] for the proposition that, in order for the defendants’ overall position to be substantially justified, their opposition to each of the plaintiffs’ claims must have been substantially justified.” Nat’l Fed’n. of Republican Assemblies v. United States,
In the case currently before the court, in which the plaintiff presented over one hundred claims stemming from the same factual core, requiring the government to be substantially justified in every single defense would lead to endless litigation over fees. See Comm’r, I.N.S. v. Jean,
This court, therefore, approaches the plaintiffs entitlement to EAJA fees by reviewing the government’s overall position, without requiring that each and every government position be substantially justified. For a defendant to prevail when a ease involves numerous claims that are factually and legally intertwined, the “position of the United States” should be viewed based on the totality of the circumstances of the entire claim, including balancing the government’s various positions against their impact on the entire civil litigation.
A. Contract Administration
First, plaintiff argues that the agency behavior which gave rise to the underlying contract claims was the result of arbitrary and capricious behavior by the contracting officer as a result of his “surrendering to others administration of the contract.” In support of this allegation, the plaintiff cites to this court’s previous finding in the trial opinion that the contracting officer “delegated broad discretion in supervising this contract, which project engineer Chew exercised daily.” CEMS, Inc. v. United States,
B. Contracting Officer’s Final Decision
CEMS further contends that the government’s position at the administrative level was not substantially justified because the contracting officer “surrendered to others adjudication of claims submitted by CEMS,” and that their subordinates abused that authority. The plaintiff also alleges that the contracting officer “denied claims in which even government error or changes were acknowledged.” To support its claim that the contracting officer acted unreasonably, CEMS first notes that the contracting officer hired a former contracting officer, Frank Baldwin, to assist in evaluating the plaintiffs claims, and that the contracting officer relied entirely on his analysis. The plaintiff points out that at trial “[i]ncredibly, Baldwin was not even called by FHA to testify.”
Although a contracting officer may obtain the advice of others, the contracting officer still must “put his own mind to the problems and render his own decisions____” Pacific Architects & Eng’rs, Inc. v. United States,
The contracting officer’s testimony during trial indicates a pattern of releasing authority to subordinates and remaining remarkably detached from the decision-making process. The contracting officer appeared to have relied almost exclusively on Mr. Baldwin’s determinations and, although he testified that
Q. [Plaintiffs attorney] All right. Did you review in detail the backup data or the purported backup data for the Final Contractor’s [sic] Officer’s Decision, or is that something you relied on Mr. Baldwin to do?
A. [Contracting officer] There was a great amount of reliance on Mr. Baldwin. Q. All right. Do you think you looked at any of the stuff?
A. I looked at it early on, rather cursorily-
Q. All right.
A. But taken [sic] how much volume there was and what basically there was during the claim analysis, I relied on Mr. Baldwin.
The contracting officer further testified that he did not know whether Mr. Baldwin had conducted a critical path analysis, or had interviewed pertinent witnesses in the course of preparing the contracting officer’s final decision. In addition, he was unaware that CEMS had submitted substantial, notarized bid information, thereby discrediting Mr. Baldwin’s rejection, in the draft contracting officer’s final decision, of a claim on the ground that CEMS had not provided its bid information. Moreover, it is apparent from the contracting officer’s testimony that he and his subordinates relied almost entirely on government sources in making determinations for the COFD, and gave little, if any, consideration to evidence submitted by CEMS. See Marshall Associated Contractors, Inc. & Columbia Excavating, Inc., 2001-1 B.C.A. (CCH) ¶ 31,248, at 154,259,
Finally, the contracting officer even denied claims in which government error or changes were acknowledged. For example, in the contracting officer’s final decision, the contracting officer noted that, regarding Claim F29, the “PE [the government’s project engineer] was in error in the manner of payment,” but nevertheless denied CEMS additional compensation, finding that the claim had “no merit.”
Thus, the pattern of detachment of the contracting officer from the claim adjudication decision making process reflected in the record in this case demonstrates that the contracting officer released his responsibility to such a degree that his actions, or inac-tions, were unreasonable. Although a contracting officer may review claims using in-house assistance, he must still understand and be persuaded by the determinations made in his contracting officer’s final decision. See Impresa Construzioni Geom. Do-menico Garufi v. United States,
In making a determination as to whether the government’s litigation position was substantially justified, this court reviews below the claims upon which the plaintiff prevailed. The remaining claims were either acknowledged by the government and paid at the administrative level, settled, or were tried and the government prevailed.
1. Claim A2
Claim A2 concerned whether the government breached its implied duty to cooperate due to plaintiffs allegation that delay occurred as a result of excessive supervision or control of the finishes of the subgrade and aggregate base course. Plaintiff based its theory of recovery on two alternate theories. Plaintiff first asserted that the government misinterpreted the contract when the government required acceptance of subgrade finishes in accordance with the tolerances set forth in subparagraph 204.13 of the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP 96). In response to this theory, the government argued that, as a matter of contract interpretation, plaintiff was incorrect, and that the government did not require plaintiff to perform beyond the contract specifications. In its trial opinion, this court rejected plaintiffs first theory regarding subpara-graph 204.13, and found that plaintiff failed to establish that the government required finishing in excess of the requirements specified in that section of the contract.
On its second theory, however, the plaintiff prevailed. Plaintiff asserted that the government rejected subgrade and aggregate finishes which were within contract tolerances. In response to plaintiffs second theory, the government argued that plaintiff failed to provide any evidence proving that the government sought to enforce tolerances beyond the contract specifications and that where the government changed grades, plaintiff was compensated. Regarding plaintiffs second theory, this court ruled in favor of the plaintiff, finding that the government failed to rebut plaintiff’s second claim that the government breached the implied duty of cooperation when it used improper measuring tools and changed the grades to which plaintiff was required to finish surfaces. CEMS, Inc. v. United States,
The government contends that its defense to Claim A2 was, nevertheless, substantially justified because this court’s ruling was based on a determination of witness credibility. In support of this contention, the government cites to Manno v. United States,
Also critical to the court’s decision in favor of the plaintiff was the fact that the government failed to make an affirmative argument to support its defense of Claim A2. Indeed, in its post-trial brief the government based its entire defense on the insufficiency of plaintiffs evidence. Thus, once this court determined that plaintiff had met its burden of proving that the government breached the implied duty of cooperation by using improper measuring tools and changing grades, the plaintiff prevailed on that issue. Id. As a result, the government has failed to meet its burden of demonstrating that its defense to Claim A2 was substantially justified.
2. Claim All and A14 pay item 21101
These claims concerned whether CEMS performed additional roadway obliteration on the bicycle path project which was not included in the contract estimated pay item of
The government contends that its interpretation of the contract was reasonable because the provisions for roadway excavation only provided exclusions for the building of structures and subexcavation. Because asphalt is a “material,” the government argued that it was governed by subsection 204.02(l)(a) of the contract and that it was reasonable for the defendant to conclude that the asphalt removal would be treated as roadway excavation. CEMS, however, asserts that this interpretation was not reasonable because the court ruled against the government, “[biased on the evidence presented at trial, and a plain reading of the contract documents ____” CEMS, Inc. v. United States,
To bolster its argument, CEMS cites Gutz v. United States,
Unlike Gutz, the court in the present case did not find that the contract language was clear and unambiguous on its face. To the contrary, interpretation of the contract with CEMS implicated complicated legal and factual issues and was anything but clear and unambiguous. This court’s ruling, therefore, was based not only on a reading of the contract, but also on evidence presented at trial. As a result, this court concludes that the government’s positions on Claims All and A14 pay item 21101, although ultimately incorrect, were substantially justified.
3. Claims D5, D8, H6, F18, and A14
The remaining claims were for excessively wet material at Station 6 + 258 to Station 6 + 810 (D5), additional mobilization costs (D8), change in location of concrete barriers (H6), saw cutting concrete (F18), and the roadway excavation and minor hot asphalt concrete pay items under Claim A14. Concerning these items, the government made no attempt to provide a defense, explanation, or substantiation for its prelitigation or litigation position. The standard for reviewing whether the government’s litigation position was substantially justified requires the defendant to demonstrate that the government acted reasonably during the dispute. See Baldi Bros. Constructors v. United States,
D. Government’s Overall Position
The final issue presented is whether the government’s overall position was substantially justified, given the government’s success in defending against a significant number of plaintiffs claims. The government was not substantially justified with respect to
The agency’s conduct would not necessarily result in an award of EAJA fees, if the government’s later litigation position was substantially justified to a degree that cured this initial conduct. See Baldi Bros. Constructors v. United States,
III. Amount of Damages
A. Apportionment
Although the United States Supreme Court has suggested that when making a determination of whether the government’s position was substantially justified, trial and appellate courts should consider the case as a whole, the Court has retained the option of adjusting EAJA fees downward to account for the varying degrees of success achieved by the petitioner during various phases of litigation or on specific issues during litigation. See Hensley v. Eckerhart,
In determining whether a plaintiff achieved excellent results, in the words of the Hensley case, it is not dispositive that the plaintiff in the present case prevailed on only 9 of the 30 claims and individual bid items actually litigated, and received only somewhat less than 24 percent of the damages
The United States Court of Appeals for the Federal Circuit has adopted a mechanism for trial courts to award attorney fees on a pro rata basis. See Cmty. Heating & Plumbing Co. v. Garrett,
Although the plaintiffs billing records are sufficient to avoid a denial or reduction of EAJA awards based on deficiencies in the plaintiffs records, the records in this case do not segregate the amount of time plaintiff actually spent on the issues on which the plaintiff prevailed. Thus, this court must determine the appropriate reduction based on its determination of what would be reasonable in light of the plaintiffs more limited success. In making this determination, the United States Supreme Court in Hensley v. Eckerhart found that EAJA awards should not be reduced according to a mathematical ratio that compares the number of issues upon which the plaintiff actually prevailed with the total number of issues in the ease. Hensley v. Eckerhart,
Notwithstanding these restrictions on fee calculations, the Supreme Court has stated that trial courts have significant discretion in awarding attorney fees because of their “superior understanding of the litigation and the desirability of avoiding frequent appellate review of what essentially are factual matters.” Comm’r I.N.S. v. Jean,
This court, therefore, bases its determination on having worked with the parties through the pre-trial, trial, and post-trial proceedings, including having reviewed the parties’ pleadings and pre-trial status re
After review of plaintiffs EAJA application, as well as the issues before the court, the court finds that the issues on which the government was not substantially justified accounted for approximately one quarter of the parties’ efforts, reflected, in part, in the apparent relative relationship in this case of efforts to claims. This court, therefore, reduces the EAJA award to 25 percent of the amount of EAJA fees claimed by the plaintiff.
In addition, plaintiff requests compensation of $454.75 for work its attorneys performed prior to issuance of the contracting officer’s final decision. Those fees, however, are not recoverable through an EAJA application. Levernier Constr., Inc. v. United States,
B. Cost of Living Adjustment
EAJA establishes a statutory cap of $125.00 per hour, but allows for adjustments above the statutory cap, if “the court determines that an increase in the cost of living ... justifies a higher fee.” 28 U.S.C. § 2412(d)(2)(A)(ii). Defendant has raised no objection to a cost of living increase by not addressing it in their response to plaintiffs EAJA application. An increase in the rate of attorney fees to account for cost of living adjustments (COLAs) may be awarded at the discretion of the court. See KMS Fusion v. United States,
This court finds that a COLA award is justified in the present case. The plaintiff requested a COLA to its attorney fees paid from 1999 through 2004 based on the consumer price index. Id. at 734 (taking judicial
After performing the appropriate computations, this court finds that the hourly rate should be enhanced to $133.75 for 1999, $138.25 for 2000, $142.18 for 2001, $144.42 for 2002, $147.71 for 2003, and $151.65 for 2004.
CONCLUSION
For the foregoing reasons, the court finds that the plaintiff is entitled to EAJA attorney fees. Based on the above computations, the Clerk of the Court shall enter JUDGMENT awarding the plaintiff EAJA fees in the amount of $57,058.64.
IT IS SO ORDERED.
Notes
. In Roanoke River Basin Association, the court also concluded that although Jean does not direct that the court look "only at the government’s macrocosmic position,” it plainly does direct "a more broadly focused analysis that would reject the view that any unreasonable position taken by the government in the course of litigation automatically opens the door to an EAJA award.” Roanoke River Basin Ass'n v. Hudson,
. This court notes that at least one court has found, based on the language in Hensley v. Ecker-hart, 461 U.S. 424,
. Plaintiff in the case currently under review requests fees for 454.7 hours of work performed by paralegals. Generally, courts have found that fees for work performed by paralegals are only recoverable to the extent they reflect tasks traditionally performed by an attorney and for which the attorney would customarily charge the client. See, e.g., Hyatt v. Barnhart,
. This court notes that, theoretically, the COLA could be calculated separately for each month that services were performed. However, although the hours expended varied from year to year, they appear, nevertheless, to have been distributed approximately evenly throughout each year, justifying use of the average CPI-U for each year.
. Despite this court’s best efforts, it could not duplicate the COLA adjusted fees provided by plaintiff. This court, therefore, calculated the enhanced rate using its own formula as follows:
1999: $125 x 166.6/155.7= $133.75 2000: $125 x 172.2/155.7= $138.25 2001: $125 x 177.1/155.7= $142.18 2002: $125 x 179.9/155.7= $144.42 2003: $125 x 184.0/155.7= $147.71 2004: $125 x 188.9/155.7= $151.65
. This amount includes $55,484.50 in appropriate paralegal fees, following review by the court, which are not subject to a COLA. See Levemier Constr. v. United States,
Year 1999: 2000 2001 2002 2003 2004 Hours 14.4 315.8 188.5 435.4 232.3 32.9 Rate $133.75 $138.25 $142.18 $144.42 $147.71 $151.65 Total Attorney Fees (COLA): Award $ 1,926.00 $ 43,659.35 $ 26,800.93 $ 62,880.47 $ 34,313.03 $ 4,989.29 $174,569.07
Therefore, $174,569.07 plus $55,484.50 equals $230,053.57.
