{¶ 1} On December 1 and 8, 2001, the appellant, the city of Fairlawn, publicly advertised that it was accepting bids for a service-road project. The appellant lаter issued an addendum on December 10, 2001, to include planting pear trees as part of the project.
{¶ 2} On December 17, 2001, the bids were opened, and the apрellant’s law director notified the appellee, Cementech, Inc., that its bid had been rejected for failure to include the addendum in the bid. A few days later, the Fairlawn City Board of Audit and Review held a meeting in which it reviewed the submitted bids, as well as correspondence from the appellee regarding its bid and the bidding process. The bоard agreed to disqualify the appellee’s bid and recognize another bid as the lowest and most responsive.
{¶ 3} Appellee filed suit against the appellant and requested that the court enjoin the appellant from taking any action or awarding the contract to any other bidder. The trial court denied the apрellee’s request for injunctive relief, and the appellee did not appeal the denial. The trial court later granted the appellant’s motion for summаry judgment.
{¶ 5} On remand, the trial court ruled thаt the appellee could recover its cost of bid preparations, but nothing more, should it prevail on its claims for violations of the competitive-bidding process. In reaching this conclusion, the court reasoned that it was not in the public’s interest to allow a rejected bidder to recover lost profits, becausе the public had already paid for performance by the successful bidder (including its profits) and should not be required to pay profits a second time. The trial court furthеr found that the prospect of liability for bid preparations would serve as a reasonable and necessary deterrent to a municipality’s noncomplianee with competitive-bidding laws.
{¶ 6} A trial ensued, and a jury found in favor of the appellee and awarded it damages in the amount of the cost of its bid preparations. Following the verdict, the appellee appealed the trial court’s order limiting damages to the cost of bid preparations. The appellatе court reversed the trial court’s judgment that lost profits could not be recovered. The court determined that the project had been completed because injunctive relief had been denied and that if the appellee could not recover its lost profits, it was left with inadequate relief. Further, the appellаte court held that precluding recovery of lost profits would undermine the integrity of the competitive-bidding process because other relief would not adequately discourage government entities from violating bidding procedures.
{¶ 7} The appellate court recognized that its decision rejected the public-policy argument that other appellate courts had found persuasive. Specifically, the court held that the interest of protecting the integrity of the bidding process and ensuring that wronged parties receive meaningful relief outweighs the risk of taxpayers’ paying profits twice for the same project. However, the apрellate court also noted that the way to avoid awarding lost profits was by granting an injunction pending the outcome on the merits.
{¶ 8} The court of appeals determined that its judgment conflicted with the judgment of the Eighth District Court of Appeals in Cavanaugh Bldg. Corp. v. Cuyahoga Cty. Bd. of Commrs. (Jan. 27, 2000), 8th Dist. No. 75607,
{¶ 9} The intent of competitive bidding is to protect the taxpayer, prevent excessive costs and corrupt practices, and provide open and honest competition in bidding for public contracts. Danis Clarkco Landfill Co. v. Clark Cty. Solid Waste Mgt. Dist. (1995),
{¶ 10} Rather, a rejected bidder is limited to injunctive relief. An injunction is an extraordinary remedy in equity where there is no adequate remedy at law. Garono v. State (1988),
{¶ 11} It is clear that in the context of competitive bidding for public contracts, injunctive relief provides a remedy that prevents excessive costs and corrupt practices, as well as protects the integrity of the bidding process, the public, and the bidders. Moreover, the injunctivе process and the resulting delays serve as a sufficient deterrent to a municipality’s violation of competitive-bidding laws.
{¶ 12} In this case, the appellate cоurt justified its decision to award the appellee lost profits by finding that precluding damages would “allow government entities to go unpunished for ignoring Ohio and municipal laws.” Cementech, Inc.,
{¶ 13} Unfortunately, the appellee did not appeal the trial court’s denial of its motion for injunctive relief. Consequently, the propriety of the denial of the
{¶ 14} Therefore, we hold that when a municipality violates competitive-bidding laws in awarding a competitively bid project, the rejected bidder cannot recover its lost profits as damages.
{¶ 15} Accordingly, we reverse the judgment of the court of appeals.
Judgment reversed.
