*181 OPINION
Pursuant to Federal Rule of Civil Procedure 56, both parties move for summary judgment on all counts of plaintiffs second amended complaint. For the reasons discussed below, plaintiffs motion (Document # 17) is GRANTED in part and DENIED in part and defendant’s motion (Document # 20-2) is GRANTED in part and DENIED in part.
BACKGROUND
Plaintiff, Célico Partnership, d/b/a Bell Atlantic Mobile, Inc. (“Célico”), 1 which is a personal wireless service provider, has been authorized by the Federal Communications Commission to provide cellular telephone service to the “Hartford, Connecticut New England County Metropolitan Area,” including the Town of Farmington. Célico' commenced this action after defendant, Town Plan and Zoning Commission of the Town of Farmington (“Commission”), denied its application for a special permit to reconstruct a church steeple and install a cellular telecommunications facility within the steeple.
In an attempt to fill existing gaps in the coverage of its personal wireless services along Routes 4 and 177 in the Unionville section of Farmington, Célico searched the area for an appropriate site on which to place a cellular telecommunications facility. Subsequently, Célico entered into a lease agreement with the First Church of Christ of Farmington, Inc. (“Church”), located at Two School Street, Unionville, Connecticut. In the 1950’s, the Church had removed the original steeple due to safety concerns. As part of the current lease agreement, Célico, proposed reconstructing the steeple, to a height of approximately 135 feet, and installing six cellular telecommunications antennas inside the steeple. Célico would also place cellular telephone equipment in a 300 square-foot room in the church basement.
Before installing its communications facility on the Church, Célico was required to obtain a special permit from the Commission pursuant to Article 2, Section 3 of Farming-ton’s Zoning Regulations because the Church is in an R-12 residential zoning district. Accordingly, Célico submitted an application for a special permit and site plan approval to the Commission on June 20,1997. The Commission held a public hearing on July 28,1997 to consider Cellco’s application, and voted to deny the application at a Commission meeting held on September 8, 1997. On September 10, 1997, the Commission notified Célico in a letter that its application had been denied. Célico then commenced this action on October 8,1997.
Célico now moves for summary judgment claiming that the Commission’s denial of its application for a special permit violated the Telecommunications Act of 1996, Pub.L. No. 104-104, § 704(a), 1996 U.S.C.C.A.N. (110 Stat. 61) 10 (“Act” or “Telecommunications Act”) (Counts One-Three). Célico further alleges that the Commission’s denial was arbitrary and capricious under Connecticut state law (Count Four). Finally, Célico argues that it was deprived of its federally guaranteed rights as protected by 42 U.S.C. § 1983 (Count Five).
DISCUSSION
A court may grant summary judgment only if it determines that there is no genuine issue of material fact based on a review of the pleadings, depositions, answers to interrogatories, admissions on file, and affidavits. Fed.R.Civ.P. 56(c). The moving party bears the burden of demonstrating the absence of a genuine issue of material fact.
Adickes v. S.H. Kress & Co.,
I. TELECOMMUNICATIONS ACT
Congress passed the Telecommunications Act in an effort to increase competition in the telecommunications industry by placing certain limitations on local zoning boards’ regulation of the placement, construction, and modification of personal wireless service facilities. 47 U.S.C. § 332(c)(7)(B);
see, e.g., Smart SMR of New York, Inc. v. Borough of Fair Lawn Bd. of Adjustment,
Célico asserts that the Commission’s denial of its petition for a special case permit violated several provisions of the Telecommunications Act. Specifically, Célico contends that the Commission’s denial: (a) was not supported by substantial evidence contained in a written record (Count One); (b) prohibited or had the effect of prohibiting the provision of Cellco’s personal wireless services (Count Two); and (c) unreasonably discriminated against Célico in favor of providers of functionally equivalent services (Count Three).
A. Substantial Evidence in a Written Record
Count One of the second amended complaint alleges violation of the Telecommunications Act for the Commission’s failure to set forth its reasons for the denial of Cellco’s application in a written decision supported by substantial evidence contained in a written record. 47 U.S.C. § 332(c)(7)(B)(iii). According to the substantial evidence standard, which is the traditional means of reviewing agency actions, this Court must consider whether the Commission’s written decision is supported by “ ‘such relevant evidence as a reasonable mind might accept as adequate to support a conclusion.’ ”
BellSouth Mobility Inc. v. Gwinnett County,
In a letter dated September 10, 1997, the Commission informed Célico that its application had been denied. Return of Record, Item I. In its entirety, the letter provides:
At a meeting of the Town Plan and Zoning Commission on September 8, 1997 it was voted to deny Bell Atlantic NYNEX Mobile, Inc. special permit to locate communication facility within reconstructed church steeple at 2 School Street. Members found that the height and scale of the proposed steeple would not be in character with the neighborhood. Members noted that the proposed steeple was significantly taller than the church’s former steeple.
Id. (emphasis added). This letter constitutes the Commission’s written decision to which we apply the substantial evidence standard.
After reviewing the written record, this Court finds that the Commission’s con-elusion — that the proposed steeple would be out of character with the surrounding neighborhood due to its height — is not supported by substantial evidence. At a public hearing *183 held on duly 28, 1997, Cellco’s regulatory manager, Sandy Carter, presented evidence on the issue of whether the proposed steeple’s height would conform to the neighborhood’s character. See Return of Record, Item F, at 1, 8, 12-13. Cellco’s application for a special permit and site plan approval dated June 20, 1997 contained similar statements. See Return of Record; Item A. Carter explained that the Church removed the original steeple, which was approximately 100 feet tall, in the 1950’s because it was damaged and structurally unsafe. Return of Record, Item F, at 2. She stated that Célico proposed reconstructing the steeple to a height of 135 feet and installing a cellular telecommunications facility within the steeple. She noted that Célico would place six antennas at the 100 foot level of the steeple and would add an additional 35 feet to complete the spire’s taper. Id at 1-3. When describing the height of other buildings in the Church’s neighborhood near the intersection of Routes 4 and 167, Carter stated, “there are a number of commercial and retail uses at this intersection and the neighborhood at various heights and elevations. We feel that the church will blend in with the other uses and building [sic] ... and it will be in harmony and conformance with other uses in the area.” Id at'3. At this point in the hearing, Carter reviewed picture's of the proposed site with the Commission and noted that the “heights of the buildings that are near the church vary as well as the hilly areas, the trees, the cemetery and then across the street being a firehouse and other town owned facilities.” Id She then directed the Commission to observe “the various heights and the various buffers and tree lines and elevations that are in this general area.” Id at 4.
After Carter concluded her presentation, the Commission’s members asked several questions on the proposed steeple’s height. Member Brenneman asked about the height of the original steeple in comparison to that of the proposed steeple. Douglas Roberts, an architect who was hired by Célico to design the proposed steeple, confirmed that the proposed steeple would be 35 feet taller than the original steeple. Member Banta noted that this additional 35 feet would be purely aesthetic and would complete the spire. Id at 6. Alternate Member Wads-worth asked about the height of surrounding structures, including adjacent buildings and the firehouse. Carter replied that Célico had not taken measurements, but instead had relied on photographs to determine how the proposed steeple’s height would blend in with the heights of nearby structures and the various elevations in the area leading from the Church site up a hill to a local cemetery. Id at 8. There was no evidence presented at the hearing to refute Cellco’s position that the proposed steeple’s height would enhance the area near the Church.
In addition to the July 28 public hearing transcript and Cellco’s application, Farming-ton’s Zoning Regulations provide evidence on the standards and regulations relevant to special permit applications for telecommunications facilities. Pursuant to Article II, Section 3(B)(1), churches and communication facilities are uses allowed only by special permit in an R-12 zone. Farmington Zoning Regulations, Return of Record, Item K, at 20. Accordingly, Célico applied for a special permit and followed the procedures set forth in Article IV, Section 12(C). Id at 110-11. While structures in an R-12 zone are generally subject to maximum height regulations set forth in Article III, Section 6, Cellco’s proposed use — the reconstruction of a church steeple — falls within an exception set forth in the definitions section of the Zoning Regulations. According to the definition of “BUILDING, HEIGHT OF,” “[cjhimneys, spires, masts, elevator penthouses, tanks and similar projections shall not be included in the height provided that any such projections shall not have an aggregate area greater than 25 percent of the roof area.” Id Article I, Section 9, at 5-6. Célico provided evidence that the aggregate area of the proposed spire was approximately 2% of the Church’s roof area. Roberts Aff. ¶ 5, Pl.’s Mem. in Supp. of Mot. for Summ. J., Attachment B. Defendant does not dispute that Célico met this specific requirement.
Instead,- defendant argues.that its denial was based on general criteria it was entitled to consider "pursuant to Article. IV, Section 12(B), including how a proposed use would be *184 in general harmony with the character of the surrounding neighborhood. See Farmington Zoning Regulations, Return of Record, Item K, at 109. Thus, in its written decision dated September 10, 1997 denying Cellco’s application, the Commission stated that its members found that the proposed steeple’s height would be out of character with the neighborhood. Return of Record, Item I.
Contrary to the Commission’s bald assertions, the September 10 decision fails the substantial evidence test. First, as discussed above, the written record does not contain any substantial evidence to support the Commission’s conclusion. The only evidence established by the Commission during the July 28 public hearing was in the form of questions by its members. For example, Member Wadsworth questioned whether Célico had “done a drawing that shows how [the proposed steeple] would look in relation to the neighborhood, with other structures or topography.” Return of Record, Item F, at 9. Despite Cellco’s negative reply, the Commission never asked Célico to provide something similar to an elevation drawing or rendering. Moreover, the collective questions posed by the Commission’s individual members do not indicate what the Commission’s general stance was on whether the proposed steeple’s height would conform to the neighborhood. There is no other substantial evidence supporting the Commission’s decision. Instead, when viewing the written record as a whole, this Court finds that the only evidence on this issue is opposed to the Commission’s conclusion.
Second, even if the Commission was entitled to rely on its knowledge of local conditions, it was required to specify, these considerations in its written decision in order to satisfy the substantial evidence standard. The substantial evidence standard “requires governing bodies to produce a written decision, detailing the reasons for the decision and the evidence that led to the decision .... ”
Virginia Metronet, Inc. v. Board of Supervisors of James City County,
Consequently, this Court finds that the Commission violated 47 U.S.C. § 332(e)(7)(B)(iii) because its decision denying Cellco’s application for a special permit was not supported by substantial evidence contained in a written record and did not provide reasons or evidence to support its conclusion. Thus, we grant Cellco’s summary judgment motion and we deny the Commission’s summary judgment motion on Count One.
B. Prohibiting or Having the Effect of Prohibiting the Provision of Personal Wireless Services
In Count Two of the second amended complaint, Célico argues that the Commission violated section 332(c)(7)(B)(i)(II) because the denial of its application had the effect of prohibiting Célico from providing personal wireless services in the Unionville section of Farmington. A zoning commission, however, does not violate the Telecommunications Act solely because it denied a personal wireless service provider’s application for a special permit, even though it had granted a permit in favor of the provider’s competitor.
Smart SMR,
In this case, Célico does no more than allege that the Commission denied its application. 2 A zoning commission’s single decision to deny an application for a special permit, even if it results in a provider’s inability to provide cellular service in a particular area, is not prohibitive within the meaning of the Telecommunications Act. Because there is no evidence that the Commission has a general bias against granting special permits for telecommunications facilities which are similar to that proposed by Célico, this Court finds that the Commission’s denial did not prohibit or have the effect of prohibiting the provision of personal wireless services. Thus, on Count Two of the second amended complaint, we deny Cellco’s summary judgment motion and grant the Commission’s summary judgment motion.
C. Unreasonable Discrimination Among Providers of Functionally Equivalent Services
In Count Three of the second amended complaint, Célico claims that the Commission violated section 332(c)(7)(B)(i)(I) by unreasonably discriminating among providers of functionally equivalent services. Célico asserts that the Commission approved a special permit for SNET Mobility, Inc., which is a provider of functionally equivalent services and which maintains an existing communications facility in or near the Unionville section of Farmington.
As an initial matter, in order for a zoning commission to have unreasonably discriminated among providers of functionally equivalent services, there must be evidence that the commission treated the providers differently. Thus, an applicant must have been subjected to unequal treatment. While unequal treatment is generally established when a commission grants a competitor’s application and denies a plaintiffs application, this is not exactly the situation here. Célico contends only that the Commission discriminated against it in favor of SNET Mobility. Yet, there is evidence that the Commission recently granted plaintiff, under the company name Bell Atlantic NYNEX Mobile, an application to install a telecommunications facility on a water tower in Farmington. Return of Record, Item H, at 2. Notice of the Commission’s approval for this second application was published in the Hartford Courant on September 10, 1997, along with notice that the Commission had denied the application at issue in this ease. Return of Record, Item J. Based on the Commission’s approval of one of Celleo’s applications and denial of the other, and the lack of any other evidence to support Cellco’s claim of unequal treatment, this Court finds that plaintiff did not receive any unequal treatment. Indeed, the Commission’s approval of the water tower application demonstrates that the Commission did not discriminate against Célico on its second application solely in favor of other providers. Consequently, we do not need to inquire into the reasonableness of the Commission’s decision to deny Cellco’s application in this ease.
See Virginia Beach,
II. CONNECTICUT STATE LAW
Count Four of the second amended complaint alleges that the Commission’s denial of Cellco’s application for a special permit was arbitrary and capricious under Connecticut law. Defendant urges this Court to grant' summary judgment in its favor because it contends that Célico did not timely appeal the Commission’s decision on state-law grounds. Section 8 — 8(b), C.G.S.A., provides that any person aggrieved by a zoning board’s decision may appeal to superior court within fifteen days from the publication of the notice of the decision.
This Court has supplemental jurisdiction over plaintiffs state-law claim because it is so related to plaintiffs federal claim under the Telecommunications Act that they form part of the same case or controversy. 28 U.S.C. § 1367(a).
For claims brought under the Telecommunications Act, plaintiffs must commence an action in any court of competent jurisdiction within thirty days of a zoning commission’s adverse decision. 47 U.S.C. § 332(c)(7)(B)(v). This provision explicitly states that this time-period applies to “any final action or failure to act by a State or local government or any instrumentality thereof that is inconsistent with this subpara-graph.” Id. (emphasis added). By the plain language of section 332(c)(7)(B)(v), the thirty-day time-period applies only to plaintiffs Telecommunications Act claim and not to its state-law claim. Accordingly, this Court must apply the time limitation of C.G.S.A. § 8-8(b) to Count Four.
Here, notice of the Commission’s decision was published in the Hartford Courant on September 10,1997. Return of Record, Item J. Plaintiff did not commence this action until October 8, 1997, which is more than the statutory fifteen-day period. Thus, Cellco’s claim under Connecticut state law is time-barred.
See Bridgeport Bowl-O-Rama, Inc. v. Zoning Bd. of Appeals of Bridgeport,
III. SECTION 1983
Finally, in Count Five of the second amended complaint, plaintiff alleges that it was deprived of its federally guaranteed rights in violation of 42 U.S.C. § 1983. In
Smart SMR,
this Court held that a plaintiff could assert a claim under section 1983 based on a zoning commission’s, violation of the Telecommunications Act.
In
Town of Easton,
the court granted the plaintiff summary judgment on its section 1983 claim after finding that the zoning board of appeals had acted under the color of state law and violated the plaintiffs rights under the Act.
IV. REMEDIES
Due to the Commission’s failure to base its decision on substantial evidence in the written record, this Court concludes that the Commission must issue Célico a special permit to reconstruct a church steeple, install six antennas within the steeple, and place cellular telephone equipment in a 300 square-foot room in the church basement. We do not find that remand would be appropriate in this case because it would only create further delay.
See Virginia Metronet,
We also deny plaintiffs request for punitive damages for the Commission’s violation of 42 U.S.C. § 1983 because the Supreme Court has held that municipalities are immune from punitive damage awards in section 1983 cases.
City of Newport v. Fact Concerts, Inc.,
CONCLUSION
For the foregoing reasons, plaintiffs summary judgment motion (Document # 17) is GRANTED on Counts One (Telecommunications Act) and Five (section 1983). We also DENY plaintiffs summary judgment motion' on Counts Two, Three (Telecommunications Act), and Four (Connecticut state law). On the Commission’s cross-motion (Document # 20-2), we GRANT summary judgment on Counts Two, Three, and Four, and we DENY summary judgment on Counts One and Five. ■
An injunction is hereby entered ordering the Commission to grant Cellco’s application for a special permit and site plan approval within twenty (20) days from the date of this opinion. Because Célico established that the Commission violated section 332(c)(7)(B)(iii) of the Telecommunications Act, the Clerk of the Court is directed to enter judgment in Cellco’s favor.
SO ORDERED.
Notes
. According to plaintiff, when it submitted its application for a special permit, it did so under the company name "Célico Partnership d/b/a Bell Atlantic NYNEX Mobile, Inc.” Subsequently, Bell Atlantic Corporation and NYNEX Corporation completed the merger of their respective telecommunications interests, and the mobile entity is now known as "Bell Atlantic Mobile, Inc.”
. We note that in an earlier case involving the Commission and a different plaintiff, the Town of Farmington had enacted a moratorium which prevented personal wireless service providers from applying for special permits until April 1998. We struck down the moratorium in
Sprint Spectrum L.P. v. Town of Farmington,
Civ. No. 3:97-863,
