Ceen v. William Cramp & Sons Ship & Engine Building Co.

249 Pa. 415 | Pa. | 1915

Opinion by

Mr. Justice Mestrezat,

This is an action of trespass brought by an employee to recover damages for an injury which he alleges was caused by the negligence of his employer. There was a verdict for the plaintiff, but the court entered judgment for the defendant non obstante veredicto on the ground that the evidence failed to show any negligence on the part of the defendant which caused the plaintiff’s injuries.

The plaintiff was employed by the defendant as a painter, and at,the time of the accident was engaged with a fellow-workman in painting the ceiling and the side of the hold of a ship in course of construction by the defendant. There was a skeleton scaffold, fifteen to eighteen feet high, which was used by the painters in performing the service. Loose boards were laid on the top of the scaffold and placed in position by the workmen as they had occasion to use them. There was a stick of timber or log, variously known as a stiffener, ribbon or strongback, seven or eight inches square and more than twenty feet in length, which was bolted to the side of the ship to hold the bulkhead in place. On the day of the accident and while the plaintiff and his fellow-workman were engaged at their work in the hold, they laid a plank from the platform to the ribbon, over which the plaintiff passed, and as he stepped on the ribbon it fell, precipitating him to the floor and causing the injuries for which he seeks to recover damages in this action.

The cause of action averred in the statement is that the defendant negligently and carelessly erected and constructed the scaffold and negligently and carelessly permitted to be furnished and used defective and insufficient material in the construction of the scaffold which caused it to break and fall resulting in the injury to the plaintiff. There is no evidence whatever in the *417case to sustain the averments of the statement except that the ribbon fell and caused the plaintiff’s injuries. This was insufficient to sustain the plaintiff’s case. There was no proof that the ribbon or the scaffolding was negligently or carelessly erected, or that the material of which it was constructed was defective or insufficient. The ribbon seems to have been securely fastened to the side of the hold, and there is no evidence to show that it became loose, of that it was defective in the method of construction, of that the material was rotten or defective and was not of the best quality. There is nothing in the case to show that the accident occurred by reason of the failure of the defendant to properly inspect and keep in repair the ribbon or the scaffold, or that it failed in the performance of any othef duty in the construction or placing of the ribbon which resulted in it falling and causing the plaintiff’s injuries. The plaintiff is, therefore, compelled to rely solely upon the happening of the accident to sustain this action against his employer which is not sufficient to warrant a recovery under the facts of this case: Price v. Lehigh Val. R. R. Co., 202 Pa. 176; Montgomery v. Rowe, 239 Pa. 321, and Brynelson v. Turner-Porman Concrete Steel Company, 239 Pa. 346.

The judgment is affirmed.