Lead Opinion
The issue here is whether plaintiff, the disappointed lowest bidder on a public contract, had a valid business expectancy for the purpose of sustaining a claim of tortious interference with a business expectancy. The trial court held that plaintiff did not have such an expectancy, but a divided Court of Appeals panel held that a genuine issue of material fact exists in this regard. Because we agree with the trial court and the Court of Appeals dissent that plaintiff did not have a valid business expectancy, we reverse the judgment of the Court of Appeals and reinstate the trial court’s order granting defendant’s motion for summary disposition.
I. FACTS AND HISTORY
Davison Community Schools, a public school district, entered into a contract with defendant for architectural services with regard to a construction project. As part of the contract, defendant agreed to assist the school district
The trial court granted defendant’s motion for summary disposition, concluding that plaintiff did not have a valid business expectancy. In a split decision, the Court of Appeals reversed, holding that a genuine issue of material fact existed in this regard. Cedroni Assoc, Inc v Tomblinson, Harburn Assoc, Architects & Planners, Inc,
address whether the Court of Appeals erred when it determined that there are genuine issues of material fact as to (1) whether the plaintiff, a disappointed low bidder on a public contract, had a valid business expectancy and (2) whether the defendant architectural firm’s communications, made pursuant to an agreement with the contracting*45 school district, amounted to intentional and improper conduct sufficient to sustain a claim of tortious interference with a business expectancy. [Cedroni Assoc, Inc v Tomblinson, Harburn Assoc, Architects & Planners, Inc,489 Mich 953 , 953-954 (2011).][2 ]
II. STANDARD OF REVIEW
We review de novo a trial court’s decision on a motion for summary disposition. Driver v Naini,
III. ANALYSIS
The elements of tortious interference with a business relationship or expectancy are “ ‘the existence of a valid business relationship or expectancy, knowledge of the relationship or expectancy on the part of the defendant, an intentional interference by the defendant inducing or causing a breach or termination of the relationship or expectancy, and resultant damage to the plaintiff.’ ” Dalley v Dykema Gossett PLLC,
Given that a contractor that submits the lowest bid cannot bring a cause of action against the municipality when its bid is rejected, even when the municipality has adopted a charter provision that requires it to accept the “lowest responsible bidder,” it is difficult to fathom how plaintiffs submission of the lowest bid could have created a valid business expectancy in light of the highly discretionary process of awarding governmental con
We are the apparent low bidders on the Additions and Renovations at Hill and Siple Elementary. I look forward to working with the Davison Schools on this project and I expect you will be more than pleased with my company’s performance and professionalism, if awarded. [Emphasis added.]
The Court of Appeals recognized that “the submission of the lowest bid, in and of itself, was inadequate to sustain plaintiffs suit” and “reject[ed] any rule per se that would allow litigation to proceed simply on the basis of proof of the lowest bid” because submission of the lowest bid does not, by itself, create a valid business expectancy. Cedroni,
“Lowest responsible bidder” is defined in the policy as a “responsible contractor,” and “responsible contrac
In Mago Constr Co v Anderson, Eckstein & Westrick, Inc, unpublished opinion per curiam of the Court of Appeals, issued November 8,1996 (Docket No. 183479), a case involving facts similar to the instant case, the Court of Appeals affirmed the trial court’s order granting the defendant’s motion for summary disposition. The defendant was a corporation of professional consulting engineers and the plaintiff was the disappointed lowest bidder. The plaintiff sued the defendant for, among other things, tortious interference with a business expectancy. The Court of Appeals explained, “Where the ultimate decision to enter into a business relationship is a highly discretionary decision reposed within the structure of a governmental entity, it be
the award of the contract was a highly discretionary governmental activity in which “too many factors [were] in play to be able to reasonably infer that. .. plaintiff would have obtained the desired [contract].” Moreover, the bidding instructions clearly informed plaintiff that the lowest bidder was not guaranteed to receive the water main improvement contract. [Id. (citation omitted; first alteration in the original).]
Although Mago is an unpublished and therefore nonbinding opinion of the Court of Appeals,
In the instant case, although the school district’s fiscal management policy provided that the contract would be awarded to the “lowest responsible bidder,” the school district itself retained the right to choose the “lowest responsible bidder.” The policy provided a non-exhaustive list of factors for the school district to consider, including its architect’s input. Therefore, just as in Mago, “the award of the contract was a highly discretionary governmental activity in which ‘too many factors [were] in play to be able to reasonably infer that. . . plaintiff [by virtue alone of being the lowest bidder] would have obtained the desired [contract].’ ” Id. (citation omitted; first alteration in the original). In addition, “the bidding instructions clearly informed plaintiff that the lowest bidder was not guaranteed to
We agree with the Court of Appeals dissent that the school district’s fiscal management policy did not afford plaintiff a valid business expectancy. The school district determined that plaintiff was not a “responsible contractor” in this specific circumstance, and it is not our
“ ‘The exercise of discretion to accept or reject bids [involving public contracts] will only be controlled by the courts when necessary to prevent fraud, injustice or the violation of a trust.’” Leavy,
rv CONCLUSION
For these reasons, we reverse the judgment of the Court of Appeals and reinstate the trial court’s order granting defendant’s motion for summary disposition. As the trial court and the Court of Appeals dissent concluded, plaintiff had no valid business expectancy for the purposes of sustaining a claim of tortious interference with a business expectancy.
Notes
According to defendant, its decision to recommend US Construction rather than plaintiff was predicated on the fact that the references supplied by plaintiff gave negative feedback and US Construction had provided construction services for other projects designed by defendant for the school district and had performed the work adequately. According to plaintiff, on the other hand, defendant’s decision to recommend US Construction rather than plaintiff was based on defendant’s desire “to punish [plaintiff] for what occurred on the Holly Academy project wherein [defendant] was ultimately replaced by another architect.”
Because we conclude that plaintiff did not have a valid business expectancy, it is unnecessary for us to address the second issue.
The dissent argues that our decision to apply the “disappointed-bidder rule” to private entities is “contrary to the purpose of the disappointed-bidder rule: to protect taxpayers.” Post at 63. However, if this case had anything at all to do with protecting taxpayers, plaintiff “should have proceeded by injunction to prevent the doing of the work under the [US Construction] contract” instead of “l[ying] by, and, after
The dissent, on the other hand, concludes that “once a qualified bidder has submitted a conforming bid and knows that it has provided the lowest bid, there might he a genuine issue of material fact regarding whether the bidder’s expectation reasonably elevated from a ‘mere hope’ to a ‘realistic expectation’ that it would be awarded the project. . . Post at 59. This conclusion is simply incompatible with both MCL 380.1267(6), which expressly states that the school board “may reject any or all bids,” and the documents presented to plaintiff, which equally clearly state that “the lowest dollar cost bidder may not always receive award of the bid.”
MCR 7.215(C)(1) (“An unpublished opinion is not precedentially binding under the rule of stare decisis.”).
The Court of Appeals majority relied, as does the dissent in this Court, on Joba Constr Co, Inc v Burns & Roe, Inc,
The dissent states that “plaintiff presented evidence that defendant’s opinion and recommendation regarding plaintiffs qualifications might have been improperly influenced by misplaced or unsupported animosity toward plaintiff related to problems between plaintiff and defendant on a previous project.” Post at 59. However, the only “evidence” that plaintiff has presented to support its allegation that defendant “improperly influenced” the school district are plaintiffs own statements.
Plaintiff argues that an architect should not be immune from liability for making false statements about a low bidder. Similarly, the dissent argues that this Court should “not protect a private entity that dishonestly influences the governmental entity.” Post at 65. However, we do not hold that an architect is “immune from liability” for making false statements about a low bidder. Instead, we simply hold that when the ultimate decision to enter into a business relationship is a highly discretionary decision reposed by law within a public entity, a disappointed low bidder does not have a valid business expectancy for the purpose of sustaining a claim of tortious interference with a business expectancy.
Dissenting Opinion
(dissenting). The issue presented in this case is whether plaintiff has produced sufficient evidence to create a genuine issue of material fact regarding whether defendant tortiously interfered with plaintiffs valid business expectancy. I respectfully dissent from the majority’s decision to disregard Joba Constr Co, Inc v Burns & Roe Inc,
I. FACTS AND PROCEDURAL HISTORY
In 2003, Davison Community Schools decided to renovate two elementary schools and contracted with defendant for architectural and engineering services. Under the contract, defendant was to assist the school district during the competitive bidding process “by reviewing and evaluating bid applications, investigating competing contractors and their references, expressing opinions and views on contractor competence and workmanship, and making recommendations regarding which contractor should be awarded the project.” Cedroni Assoc, Inc v Tomblinson, Harburn Assoc, Architects & Planners, Inc,
The school district advertised for bids. With respect to the bidding process, the school district’s fiscal management policy (FMP) provided that the school district reserved the right to reject any or all bids. The FMP also stated that “[b]ids shall be awarded in compliance with the applicable bidding obligations imposed by law to the ‘lowest responsible bidder.’ ” The FMP defined “lowest responsible bidder” as
[t]he Responsible Contractor that has submitted a fully complete and responsive bid that provides the lowest net dollar cost for all labor and materials required for the complete performance of the work of the Construction Project let for bid. Such bid must satisfy the requirements of all applicable local, state, and federal laws, this Policy, any administrative rules associated with this Policy developed by the Superintendent at the Board’s direction, and bid documents used to solicit bids, and any other guidelines and specifications required for the Construction Project.*56 Because a bidder with the net lowest dollar cost bid may not be a Responsible Contractor, the lowest dollar cost bidder may not always receive award of the bid.
The FMP defines the “Responsible Contractor” as
[a] contractor determined by the Board to be sufficiently qualified to satisfactorily perform the Construction Project, in accordance with all applicable contractual and legal requirements. The Board’s determination shall be based upon: (1) an overall review of the Responsibility Criteria listed below and the contractor’s responses, or failure to respond, to same; (2) the contractor’s compliance with this Policy and all applicable local, state and federal laws; (3) the input of the District’s architect(s) [here defendant] and/or construction manager(s), if any; (4) review of the contractor’s proposed subcontractors; and (5) other relevant factors particular to the Construction Project.
It is undisputed that plaintiff was the lowest bidder, having submitted a bid that was $50,000 less than the next-lowest bid, and plaintiff was aware that it had provided the lowest bid. However, Hoist sent a letter to the school district recommending that the district not accept plaintiffs bid and instead accept the bid of the next-lowest bidder, US Construction and Design Services, LLC. Hoist’s notes indicated that while several references provided positive reviews of plaintiffs work, other references provided negative feedback and that Hoist had had personal negative experiences with plaintiff on a previous project. Plaintiff alleges that Hoist’s notes regarding various references’ comments were untrue. Additionally, plaintiff alleges that defendant’s recommendation that the school district reject plaintiffs bid was born out of a desire to punish plaintiff for a dispute between defendant and plaintiff on the previous “Holly Academy project” that resulted in defendant’s discharge from that project. The record also
The school board’s review committee endorsed defendant’s recommendation to reject plaintiffs bid, and the school district awarded the project to US Construction, explaining that its decision was made in reliance on defendant’s recommendation.
Plaintiff filed a complaint against defendant alleging tortious interference with prospective economic relations, arguing that it had “a legitimate expectancy in obtaining a contract to complete work for the [school] Project,” that defendant had “wrongfully persuaded the School District” to reject plaintiffs bid, and that defendant had “intentionally interfered with the expectant business relationship ... by wrongfully claiming that [plaintiff] was unqualified to perform” the necessary work. Defendant moved for summary disposition, which was eventually granted under MCR 2.116(C)(10).
II. STANDARD OF REVIEW
This Court reviews de novo a trial court’s decision on a motion for summary disposition de novo. Shepherd Montessori Ctr Milan v Ann Arbor Charter Twp,
III. ANALYSIS
The elements for a claim of tortious interference with advantageous business relationships or prospective economic relations are
(1) the existence of a valid business relationship or expectancy; (2) knowledge of the relationship or expectancy on the part of the interferer; (3) an intentional interference causing a breach or termination of the relationship or expectancy; and (4) resulting damage to the party whose relationship or expectancy has been disrupted. [Joba,121 Mich App at 634 .]
At issue in this case is whether plaintiff had a “valid business expectancy.” To avoid summary disposition, a plaintiff must assert “a specific and reasonable prospective economic advantage that was interfered with.” Id. The business expectation must be proved “with some degree of specificity” so that it is a “realistic expectation and not merely wishful thinking,” “mere hope,” or “the innate optimism of the salesman.” Id. at 634-635 (quotation marks and citations omitted). However, a plaintiff “need not demonstrate a guaranteed relationship” given the prospective nature of the expectation at issue. Id. at 635 (quotation marks and citations omitted); see, also, Trepel v Pontiac Osteopathic Hosp,
Although it is generally difficult to claim that a bid — which, at its heart is an offer to perform the work for a specified price — can generate a realistic expectation in the bidder that it will be awarded the project,
Accordingly, given that plaintiff was aware of its status as the lowest bidder, and keeping in mind that plaintiff “need not demonstrate a guaranteed relationship,” id. (quotation marks and citations omitted), I believe that plaintiff might have had a valid business expectation as long as plaintiff was able to establish a genuine issue of material fact regarding whether it was a responsible bidder.
Although defendant’s investigation and opinion of plaintiffs qualifications are certainly valid considerations in determining whether plaintiff was a responsible bidder, the parties presented conflicting evidence regarding plaintiffs qualifications. While I do not think that the mere fact that plaintiff believed that it was qualified is sufficient to avoid summary disposition on this issue, plaintiff presented evidence that defendant’s opinion and recommendation regarding plaintiffs qualifications might have been improperly influenced by misplaced or unsupported animosity toward plaintiff related to problems between plaintiff and defendant on a previous project. Plaintiffs evidence included Hoist’s
As the majority notes, however, a specific line of cases beginning with Talbot Paving Co v Detroit,
Notably, however, the “disappointed bidder” rule developed by this line of cases has generally been applied only when the plaintiff files suit against the contracting governmental entity rather than another private entity. Indeed, in Joba,
In Joba, the plaintiff was the lowest bidder for a contract with the city of Detroit. The defendant had been retained by the city to evaluate bids and make recommendations regarding which bidders to select for certain contracts, including the contract on which the plaintiff was the lowest bidder. The defendant recommended that the city not accept the plaintiffs bid because, in the defendant’s opinion, the plaintiff was unqualified to perform the contract. However, just as in this case, there was also evidence presented that animosity existed between the defendant and the plaintiff, partially resulting from past interaction on a different project. The case went to trial, the jury returned a verdict in favor of the plaintiff, and the defendant sought a directed verdict, which the trial court denied. Accordingly, the Joba Court considered the defendant’s appeal of the trial court’s denial of a directed verdict in the light most favorable to the plaintiff as the nonmoving party, and it concluded that the “plaintiff presented sufficient evidence to create a question of fact as to whether it was the lowest qualified bidder and thus had a legitimate expectancy in obtaining the contracts . . ..” Id. at 635. As previously stated, Joba did not apply the disappointed-bidder rule to the dispute between the two private entities.
The majority, however, summarily discards Joba as not “particularly helpful,” ante at 52 n 6, and instead relies on Mago Constr Co v Anderson, Eckstein & Westrick, Inc, unpublished opinion per curiam of the Court of Appeals, issued November 8, 1996 (Docket No. 183479), to support its argument that the disappointed-bidder rule should apply in this case. Mago, however, is unpersuasive for a variety of reasons. First, to the
Likewise, the majority’s reliance on an unpublished opinion of the United States Court of Appeals for the Sixth Circuit, EBI-Detroit, Inc v Detroit,
Furthermore, unlike the majority’s holding in this case, Joba’s decision to limit the disappointed-bidder rule to suits against governmental entities is consistent with the purpose of that rule. Specifically, by declining to provide private entities with the same protection from suit granted to governmental entities, Joba ensures that taxpayers obtain the best price possible for public contracts, free of improper interference by private entities. As evidenced by the facts of Joba and, potentially, the facts of this case, private entities may be motivated to make contracting decisions for reasons that are not consistent with the purpose of competitive bidding for government contracts. Because these potential motivations may not result in the selection of the “lowest responsible bidder,” they are contrary to the purpose of the disappointed-bidder rule: to protect taxpayers.
However, when a private entity intentionally provides inaccurate or misleading information to a governmental entity and the governmental entity in turn relies on that information in making a contracting
Accordingly, although a governmental entity is entitled to deference regarding its discretionary selection of a bidder under this Court’s jurisprudence, that caselaw does not protect a private entity that dishonestly influences the governmental entity. All the various documents and statutes that the majority cites to establish the fact that the school district in this case had the authority to reject any and all bids are rooted in deference to the school district’s discretion in making contracting decisions. However, this case raises the
I recognize that, under MCR 7.215(J), the Court of Appeals was not hound to follow Joba, because Joba was issued before November 1, 1990. However, when faced with two nonbinding opinions reaching different results on the same issue, the Court of Appeals properly gave more weight to the published opinion. Moreover, Mago is distinguishable from this case for the reasons discussed later in this opinion. Finally, the majority’s decision to reject Joba in part because this Court is not bound by the Court of Appeals’ opinions, see ante at 52 n 6, citing Catalina Mktg Sales Corp v Dep’t of Treasury,
The majority misconstrues my discussion of the purpose of the disappointed-bidder rule. See ante at 47-48 n 3. As stated previously, in my view the disappointed-bidder rule should not be extended to protect
Plaintiffs letter to the school board, which the majority cites, see ante at 49, merely recognizes the school district’s discretion in selecting a bidder. The letter cannot be reasonably interpreted as implying that plaintiff consented to defendant’s alleged efforts to improperly influence the school district’s exercise of that discretion.
Even the Court of Appeals dissent in this case recognized that “a plaintiff does have a legitimate expectancy that the bid it submits will be evaluated fairly and openly and will be subject to the same or similar scrutiny as other bids, so that the plaintiffs bid stands on an even playing field with all other bids.” Cedroni,
