198 Ky. 243 | Ky. Ct. App. | 1923
Opinion of the Court by
Reversing.
In a-suit in the Letcher circuit court the Caudill Coal Company set up a lease contract between it and one John T. Solon executed on the • — • day of October, 1918, in which it leased to him certain mining properties, including ta'railway spur and full equipment, and sold to him its stock of .goods and other personal property at its commissary, he agreeing to pay a royalty of 25 cents a ton on the coal produced, settlement to be made on the. 10th of each month for the coal produced in the preceding month.
The defendant filed no answer and a default judgment was taken in accordance with the prayer of the petition. It further appears that on the 4th day of March, 1920, the Solner Mining Company executed a mortgage on the two machines above mentioned, to the Maynard Coal Company to secure it on a pre-existing debt for $6,000.00. This mortgage was filed for record on the 20th day of March and recorded on the 30th of March, 1920.
The petition above referred to was filed on the 28th day of March but made no allusion to the Maynard Coal Company’s claim. At the July term of court the Maynard Coal Company filed an intervening petition setting up its claim and seeking the enforcement of this lien, but no notice was taken of it by the Caudill Coal Company until January 3, 1921, at which time it filed an answer attacking the conveyance for several reasons; this answer was taken ras controverted of record, and over the objection of the Maynard Coal Company the case was submitted. It had also filed its claim asserting its lien, with the master commissioner, to whom the case had been referred for a settlement of the affairs of the defunct corporation.
The master commissioner allowed the claims of plaintiff and the Maynard Coal Company as ordinary claims
The appeal of the Maynard Coal Company was filed May 7th, 1921, and its statement reads as follows:
“Court of Appeals of Kentucky.
Caudill Coal Co., et al., Appellants,
vs. Statement.
Solner Mining Co., et al, Appellees.
The appellant is the Maynard Coal Co.
The judgment appealed from was rendered at the January term, 1921, of the Letcher circuit court and may be found on page 161 of the record.
No summons or warning order is desired.
PoSTLEWAITE & MARTIN,
Columbus 0., Attys. for appellant,
The Maynard Coal Co.
J. B. Snyder, Williamsburg, Ky.,
R. Monroe Fields, Whitesburg, Ky.,
Attorneys for appellee.”
It is evident that the caption in this appeal is confused with that of the pleadings in the lower court. The Caudill Coal Company is not the appellant and the words “et al.” are not sufficient to so constitute the Maynard Coal Company, but as the latter is specifically named as appellant in the body of the statement this may be sufficient in that particular. The Solner Mining Company is named as appellee in the statement, and while it is such, it is taking no part in the contest and is only a nominal party, and although its name is followed by the words “et al.” it is uniformly held that in such a case the appeal will be treated as if prayed against the party first named only. It follows that in such case the Caudill Coal Company would not be affected by this appeal. Matney v. Edmonds, 179 Ky. 243; Brody v. Parsons, 23 Rep. 831; Comth. v. Columbia Trust Co., 162 Ky. 825. It later, on the 19th day of September, 1921, filed an independent appeal on the same record and in this proceeding the Maynard Coal Company might
" In this state royalties contracted to be paid the -lessor for the use of -coal property are regarded as rents. Saulsbury v. Saulsbury, 162 Ky. 486; and no attachment .or distress was necessary to create a lien when suit was filed. Wonder Blue Gem Coal Co. v. Louisville Property Company, 137 Ky. 352.
By the provisions of sections 2316, Kentucky Statutes, the landlord is given a superior lien on the tenant’s property for not exceeding one year’® rent as against all other liens, except -such as were created before the property was moved on the leased premises, provided the same is sued out in 120 days from the time the rent is due. Section 2317, Kentucky Statutes, gives a superior lien on the tenant’s property for not exceeding one year’s rent due or to become due which had not been due for more than eleven months.
The construction given these statutes in Petry v. Randolph, 85 Ky. 354, is that the first applies to liens of third parties while the latter applies to all other character of claims.
It follows that if the lien of the Maynard Coal Company had been allowed, the Caudill Coal Company would have had a superior lien as against it on all property owned by the -Solner Mining Company and .moved on the leased premises prior to the execution of its mortgage to the extent -of $7,112.60, the amount of the rent which had not been due for exceeding four months; but inasmuch as the Maynard Coal Company was not allowed a lien in the lower court and the effect of its appeal i® to affirm the judgment of that court and there being no other lien creditors, it results that the Caudill Coal Company has a lien under section 2317, supra, for all the rents which had not been due for more than eleven months at the time suit was filed, or for the gross amount of $13,860.40, and that this lien should prevail over all ordinary claims.
Wherefore, judgment is reversed -on the appeal of the Caudill Coal Company against the Maynard Coal Company and cause- remanded for proceedings consistent with this opinion.