Catlyn & Derzee, Inc., Appellant, v Amedore Land Devеlopers, LLC, et al., Respondents. [19 NYS3d 348]
Peters, P.J. Appeal from an order of the Supreme Court (McNamara, J.), entered March 31, 2014 in Albany County, which, among other things, denied plaintiff's motion for partial summary judgment.
In
"[t]he purchase price is $15,000 per multi-family unit approved by the Town of North Greenbush and all necessary governmental agencies, . . . with an anticipated purchase price of . . . $2,700,000."
The contract further provided, in paragraph 13 (A) (2), that certain costs incurred by Amedore in obtaining the remaining necessary governmental approvals for the development would be credited from the purchase price at closing, so long as the invoices for such costs were suppliеd to plaintiff at least five days prior to the payment of the invoice.
By February 2010, Amedore had succeeded in obtaining all the necessary approvals for the construction of the 180 residential units authorized by Local Law No. 8. On May 25, 2010, the рarties executed an amendment to the contract which, among other things, altered the provisions regarding the purchase price and credit for costs incurred in obtaining governmental approvals.2 As relevant here, such amendment specifically provided that "[t]he purchase price referenced in [p]aragraph 2 [of the contract] shall be reduced to . . . $2,520,000.00." It also required that Amedore provide plaintiff with invoices to supрort a $210,000 credit against the purchase price pursuant to paragraph 13 (A) (2) of the contract. The parties closed on the property that same day, with plaintiff tendering the deed for the premises in exchange for the gross sum of $2,310,000, representing the $2,520,000 purchase price less the $210,000 credit authorized by paragraph 13 (A) (2).
Approximately two years later, defendants successfully applied to the Town Board of the Town of North Greenbush to
Thereafter, plaintiff moved for summary judgment on its causes of aсtion for breach of contract and declaratory judgment and sought dismissal of the counterclaim. Defendants opposed the motion and cross-moved for summary judgment on their counterclaim. Supreme Court, among other things, searched the record and granted defendants summary judgment dismissing the cause of action for breach of the purchase price provision, found that questions of fact existed as to whether defendants were contractually entitled to the credits claimed at closing, and declared that any breach of the contract's cost reimbursement prоvision is insufficient to relieve plaintiff of its obligations under the contract. Plaintiff appeals.
"The fundamental, neutral precept of contract interpretation is that agreements arе construed in accord with the parties' intent[, and] [t]he best evidence of what parties to a written agreement intend is what they say in their writing" (Greenfield v Philles Records, 98 NY2d 562, 569 [2002] [internal quotation marks and citations omitted]; see Ellington v EMI Music, Inc., 24 NY3d 239, 244-245 [2014]; Schron v Troutman Sanders LLP, 20 NY3d 430, 436 [2013]). As such, "'a written agreement that is complete, clear and unambiguous on its face must be enforced according to the plain meaning of its terms'" (MHR Capital Partners LP v Presstek, Inc., 12 NY3d 640, 645 [2009], quoting Greenfield v Philles Records, 98 NY2d at 569; see Vermont Teddy Bear Co. v 538 Madison Realty Co., 1 NY3d 470, 475 [2004]). Further, we "may not by construction add or excise terms, nor distort the meaning of those used and thereby make a new contrаct for the parties under the guise of interpreting the writing" (Bailey v Fish & Neave, 8 NY3d 523, 528 [2007] [internal quotation marks and citations omitted]; accord Beardslee v Inflection Energy, LLC, 25 NY3d 150, 157 [2015]; see NML Capital v Republic of Argentina, 17 NY3d 250, 259-260 [2011]). Adherence to these principles is "particularly
Guided by these precepts, we address plaintiff's contention that Supreme Court erred in dismissing its cause of action for breach of the purchase price provision of the contract. Plaintiff argues that the amendment simply changed the "anticipated purchase price" set forth in the contract while leaving intact the $15,000 per unit formula for determining the "purchase price," suсh that defendants were obligated to compensate it for the 44 units that were subsequently approved by the Town years after the closing.3 Such an interpretation, however, is not supported by the language of the amendment. The amendment makes no mention of the "anticipated purchase price"—a figure that was originally arrived at based upon the expectation that 180 units would ultimately be approved at the time of closing. Rather, the amendment expressly references the contract's "purchase price"—which is expressly defined in the contract as $15,000 per multifamily unit approved by the Town and all necessary governmentаl agencies—and specifies that such "purchase price" is being changed to $2,520,000. The amendment, therefore, plainly and unambiguously modified the purchase price of the property from a per-unit cost to a fixed price. Indeed, when consideration is given to the entire contract and "the circumstances under which [the amendment] was executed" (Currier, McCabe & Assoc., Inc. v Maher, 75 AD3d 889, 890-891 [2010] [internal quotation marks and citation omitted]), it would be illogical to read the amendment as merely modifying the "anticipated purchase price," since the amendment was executed on the day of the closing when the 180 units had, in fact, already been approved. Since the "'only reasonable interpretation'" of the amendment is that the parties abandoned a per unit purchase price (id. at 892, quoting B.T.R.-E. Greenbush v General Acc. Co., 206 AD2d 791, 792 [1994], lv
denied 84 NY2d 808 [1994]), Supreme Court properly dismissed plaintiff's cause of action for breach of the contract's purchase price provision.
We turn next to plaintiff's claim that defendants breached the contract's cost reimbursement provision. It is undisputed that defendants failed to provide plaintiff with invoices for the costs incurred in procuring the necessary government approvals within five business days of paying such invoices, as required by paragraph 13 (A) (2) of the contract. In amending the contract on the date of closing, however, the parties agreed that defendants would furnish plaintiff with the invoices to support the $210,000 credit claimed. In our view, this clause of the amendment authorizing the subsequent submission of invoices unambiguously supplanted the inconsistent provision of the original contract requiring submission of such invoices prior to payment (see generally British Am. Dev. Corp. v Schodack Exit Ten, LLC, 83 AD3d 1247, 1249 [2011]; Benipal v Herath, 251 AD2d 933, 934 [1998]). Moreover, even were we to find an ambiguity, the extrinsic evidence submittеd on the motions fully supports the conclusion that, in amending the contract, the parties intended to eliminate the prior submission requirement.
Nevertheless, a question of fact exists as to defendants' entitlement to the entirety of the $210,000 credit. More than $50,000 of the claimed credit was for the payroll costs of an employee of Amedore who was involved in obtaining the governmental approvals for the property. Although the contract lists fivе categories of allowable expenses, all of which consist of fees that, by their nature, would generally be paid to third parties, it specifically provides that the creditable costs "are not limited to" those specifically listed. As the parties expressed a general intent to reimburse defendants for the costs of obtaining governmental approvals and the list of allowable expеnses was not meant to be exhaustive, we agree with Supreme Court that a question of fact remains as to whether payroll costs fall within the scope of the permissible expenses (see generally Red Hook Cold Stor. Co. v Department of Labor of State of N.Y., 295 NY 1, 8 [1945]; Helvering v Morgan's Inc., 293 US 121, 124-125 [1934]).
Finally, plaintiff was not entitled to a declaration that it was relieved of all outstanding obligations under the contract. "[A] party's оbligation to perform under a contract is only excused where the other party's breach of the contract is so substantial that it defeats the object of the parties in making the contrаct" (Robert Cohn Assoc., Inc. v Kosich, 63 AD3d 1388, 1389 [2009]
McCarthy, Garry and Rose, JJ., concur. Ordered that the order is affirmed, with costs.