Cassidy v. Highrise Hoisting & Scaffolding, Inc.Cassidy v. Highrise Hoisting & Scaffolding, Inc.
At the time of plaintiff’s accident, Midtown West A.L.L.C. owned a building under construction, for which Rockrose GC MWA L.L.C. was the general contractor. Defendant Highrise Hoisting & Scaffolding, Inc. had installed a sidewalk bridge, hoistway and temporary loading dock. The temporary loading dock constructed by Highrise was a wooden platform measuring 20 feet by 40 feet and was, depending upon the witness, approximately 48 to 60 inches above the ground, about the height of a trailer truck. At the section of the loading dock where trucks load and unload, there was a removable horizontal pipe railing that was approximately eight feet long and two inches in diameter. The horizontal pipe railing was secured to vertical posts with clamps at each end, and tightened into place with a nut and bolt. In order to allow for a delivery, the horizontal pipe railing would be unbolted from the clamps and removed.
Plaintiff, a laborer employed by the nonparty concrete subcontractor, was waiting for the hoist to come to the loading dock level, when he leaned against the dock railing, which fell, causing him to fall as well. He suffered personal injuries to his neck and back.
The motion court properly granted plaintiff summary judgment on his
However, defendants established that plaintiff could not recover under
Plaintiff’s common-law and
We decline to reach defendants’ argument concerning