Jаmes King (“Defendant”) timely appeals a civil judgment for monetary damages entered against him in favor of plaintiffs Larry and Paula Cason (“the Casons”) and Donnie and Kelly Hatton (“the Hat-tons”) (collectively, “Plaintiffs”) after a bench trial. The suit arose out of work Defendant performed on two septic systems. The judgment awarded the Casons $3,500, representing the cost to repair their defective septic system, plus $5,000 for the loss of the full use of their property. 1 The judgment awarded the Hattons $4,900 for the cost to repair their septic system.
Defendant presents one point on appeal, asserting the trial court erred in awarding damages “becаuse the evidence was insufficient to prove damages in that neither [set of] Plaintiffs] produced any evidence regarding diminution in land value and the court therefore had no basis for awarding repair costs[.]” In the same point, Defendant also asserts that Mr. Cason failed to “produce any evidence supporting the $5,000 amount that the court awarded him for loss of use of his lake, and [ ] that the proper measure for damages resulting from the loss of use of his lake is either the diminution in value or repair costs.”
Finding merit in Defendant’s claim that the evidence was insufficient to support the amount of the trial court’s loss of use award to the Casons, wе reverse that portion of its judgment, affirm the balance, and remand the matter for a new trial on the limited issue of damages suffered by the Casons as a result of their lake being contaminated by the defective septic system installed by Defendant.
Facts
In a court-tried case, “[a]ll evidence and permissible inferences therefrom are
*546
considered in the light most favorable to the trial court’s decision, and all contrary-evidence and inferences are disregarded.”
Pruitt v. Pruitt,
The Casons lived on a 100-acre cattle farm in Owensville. The Hattons, who were the Casons’ daughter and son-in-law, owned a house on neighboring land. In July 2000, Mr. Cason was adding a seven-acre lake to his property and hired Defendant to add a new ground field to his existing septic system. Mr. Cason told Defendant “that [he] was installing the septic field because [he] was building a new lake and [he] didn’t want the raw sewage draining into the lake.” Defendant installed approximately 220 feet of pipe to create the new ground field, and Mr. Ca-son paid Defendant $1,500 for this work. “A few weeks after the installation^] after [Defendant] had left, [the system] started leaking sewage to the surface and smelling.”
Mr. Cason contacted Defendant, who attempted repairs. Over the next several years, problems with sewage seeping to the surface of the ground continued. Defendant’s additional attempts to fix the problems were unsuccessful, and the instant lawsuit was filed in May 2005. In June 2006, Mr. Cason had the septic system replaced by a new contractor for $3,500. The replacement system was rerouted to a new field, additional pipe was used, and the system was “slightly larger” than the prior system. After the new system was installed, no more leaks occurred.
Mr. Cason planned on using his new lake for recreation and to water his cattle. The lake was not finished until after the septic system started leaking. Sewage seeped into the lake from a cesspool that resulted from the leaking system. Additional sewage ran into the lake whenever Defendant would open the system in furtherance of his attempts to repair it. The odor from the leaking sewage on the Ca-sons’ property was so bad during these times that the family and their guests could not remain outside. The water in the lake also began to emit a foul odor, and Mr. Cason could not use it to water his cattle. Children did swim in thе lake, although they had to bathe afterwards, and the Casons generally did not keep “very many” fish caught in the lake.
The lake remained malodorous after the replacement system was installed. The lake was not drained after the sewage leaks had occurred, and Mr. Cason did not attempt to purify the water or otherwise clean the lake. Mr. Cason testified that “[t]he lake cost well over $10,000 to build[.]” Mr. Cason requested “maybe $5,000” as damages for the Casons’ loss of use of the lake. No evidence, other than the original cost to build the lake, was offered as support for the amount requested.
Defendant installed a new septic system fоr the Hattons’ home shortly before he installed the ground field for the Casons. Mr. Hatton paid Defendant $3,000 for the septic system. Approximately four-to-six months after the system was installed, Mr. Hatton began to notice sewage leaching up in his yard. Mr. Hatton called Defendant about it. Defendant came out to look at it, but did not make any repairs. Defendant suggested that perhaps Mr. Hatton had run over the system and broken a pipe.
Mr. Hatton then had another contractor inspect the system. That contractor did *547 not find a broken pipe. He repaired the Hattons’ septic system by installing both a pump station and a new ground field using additional pipe. The cost of the replacement system was $4,900.00.
Standard of Review
The judgment of the trial court must be affirmed “unless there is no substantial evidence to support it, unless it is against the weight of the evidence, unless it erroneously declares the law, or unless it erroneously applies the law.”
Murphy v. Carron,
Analysis
Defendant claims the trial court misаpplied the law and that its judgment is not supported by substantial evidence. At the outset, we note that Defendant’s point relied on improperly asserts more than one claim of error. It states:
The trial court erred in awarding the amount of damages to both [the Casons and the Hattons] because the evidence was insufficient to prove damages in that neither [the Casons nor the Hat-tons] produced any evidence regarding diminution in land value and the court therefore had no basis for awarding repair costs, in that [Mr. Cason] did not produce any evidence supporting the $5,000 amount that the court awarded him for loss of use of his lake, and that thе proper measure for damages resulting from the loss of use of his lake is either the diminution in value or repair costs.
A point relied on must identify a single trial court ruling that is challenged, state concisely the applicable legal principle(s) supporting that challenge, then summarize how the legal reason(s) stated apply to the facts of the case. Rule 84.04(d). Defendant’s single point attempts to challenge the trial court’s ruling on cost of repair damages as to both the Casons and the Hattons as well as its loss of use award to the Casons. A point that groups together multiple contentions of error does not satisfy Rule 84.04.
Martin v. Reed,
From the аrgument section of Defendant’s brief, we discern that his primary complaints are: 1) evidence of diminution in value must always be produced before evidence of cost of repair can be received and Plaintiffs presented no such evidence; and 2) insufficient evidence was presented as to the damages suffered by the Casons due to the loss of use of their lake. Because there is a preference that appeals be resolved on the merits whenever possible, and the deficiency of Defendant’s point does not substantially impede appellate review, we will address his claims of error
ex gratia. See Comp & Soft, Inc. v. AT & T Corp.,
Actual Damages Based on Cost of Repair
Defendant argues the trial court misapplied the law by awarding cost of *548 repair damages without first determining that the cost of repair was less than any diminution to the value of the properties caused by his breach of contract. The trial court’s judgment stated:
The court, having taken the matter under advisement, now finds the issues contained in Counts I [the Casons’ breach of contract claim] and V [the Hattons’ breach of contract claim] in favor of the Plaintiffs and against the Defendant. The [c]ourt finds that there are due to Plaintiffs from the Defendant the following amounts:
To [the Casons]:
Cost of Repair in the amount of Three Thousand Five Hundred Dollars ($3500.00) and for Loss of Use of the property and pond the amount of Five Thousand Dollars ($5000.00) for a total amount of Eight Thousand Five Hundred Dollars ($8500.00).
To [the Hattons]:
Cost of Repair in the amount of Four Thousand Nine Hundred Dollars ($4900.00).
“A plaintiff claiming a breach of contract has available and need not choose between three types of damages — actual, consequential, and benefit-of-the-bargain— as such damages are not necessarily inconsistent with one another; a plaintiff may not, however, be made whole more than once.”
Catroppa v. Metal Bldg. Supply, Inc.,
Damages resulting from a faulty septic system were considered in the context of a real estate contract in
Kelsey v. Nathey,
Defendant asserts here the same argument that failed in
Kelsey,
but cites other cases,
Plunk v. Hedrick Concrete Prod. Corp.,
In another case cited by Defendant,
Evans v. Werle,
Just what rule of law the trial court should have applied has not been consistently expressed in the existing case law. Of the cases cited by Defendant,
Evans
is рerhaps the most challenging to reconcile with other breach of contract cases. In
Evans,
the plaintiffs proved that the roof installed by the defendant leaked and regularly lost shingles during storms.
Even if-[one of the plaintiffl’s testimony was not hearsay, it would have been necessary for [plaintiffs] to first provide evidence of the diminution in value of their home due to the roof damage. “In real property cases, courts generally utilize the ‘diminution in value’ test, turning only to the ‘cost of repair’ test when it constitutes a lower amount of recovery.” Business Men’s Assur. Co. of America v. Graham,891 S.W.2d 438 , 450 (Mo.App.1994), affirmed after remand and transfer984 S.W.2d 501 (Mo. banc 1999). “In defective construction cases, on the other hand, the ‘cost of repair’ test is favored, so that courts normally determine the damages by assessing the cost of correcting the defects or supplying the omissions.” Id. A court, however, cannot apply cost of repair damages until after it hears evidence of value. Flora v. Amega Mobile Home Sales, Inc.,958 S.W.2d 322 , 324 (Mo.App.1998). Without evidence of the cost of repair of the roof or the diminution in value of their home, [plaintiffs] did not provide sufficient evidence of damages, and in turn, did not make a submissible case for breach of contract. Their claim, however, does give rise to nominal damages.
Id. at 492-93.
In
Plunk,
a case involving damages resulting from a breach of an implied warranty of merchantability rеgarding bricks installed on a house, the homeowner’s testimony as to diminution in value was held sufficient.
In
Sheridan,
the court reversed and remanded a judgment based on the cost to replace an in-ground swimming pool after the defendant negligently drained it because “no evidence of diminution in value was presented to the trial court.”
In
Lewis,
a backhoe was negligently damaged, but “there was no evidence of the monetary diminution in value of the backhoe to compare with the cost of repairs.”
In
King,
a house was damaged by sewage that backed up from a city’s sanitation system, and the owner was awarded damages caused by the nuisance.
4
Plaintiffs assert it is also permissible to rely on the cost of repair alone when the defendant does not inject the issue of economic waste, citing
Trident Group, LLC v. Mississippi Valley Roofing, Inc.,
In Trident, damages were awarded against defendant based on breach of contract. Id. at 197. The defendant complained that the trial court should not have excluded evidence obtained on the eve of trial with a subpoena duces tecum. The excluded evidence would have established that there was no diminution in value to two buildings that had leaky roofs installed by defendant. Id. at 200. The court rejected this argument, stating:
Even assuming the evidence sought by the subpoena would have shown a lack of diminution in value to the real estate, Defendant failed to present the requisite evidence of economic waste in order to make diminution in value the proper measure of damages. Unless Defendant presented evidence that the cost of repair or replacement would constitute economic waste, the proper measure of damages could not have been the diminished value of the property due to the defective work. Dubinsky v. United States Elevator Carp.,22 S.W.3d 747 , 751-52 (Mo.App. E.D.2000) (proper measure of damages in a breach of construction contract is cost of repair); see also McLane v. Wal-Mart Stores, Inc.,10 S.W.3d 602 , 605 (Mo.App. E.D.2000).
Id.
In
Dubinsky v. United States Elevator Corp.,
However, the general rule in calculating damages for a breach of contract is that the non-breaching party is entitled to the cost of repairing or replacing the defective work. Ken Cucchi Construction, Inc., v. O’Keefe,973 S.W.2d 520 , 527 (Mo.App. E.D.1998).[ 6 ] However, if the cost of repair or replacement would constitute an economic waste, then the proper measure of damages is the diminished value of the property because of the defective work.
Id. at 751-52. The court further noted that it is the responsibility of the defendant to inject the issue of economic waste.
Once the landowner presents evidence on the cost of repair or replacement, the contractor has the burden of presenting evidence that the cost of repairing or replacing the property is disproportionate to the diminution in value of the property and if the contractor fails to present any evidence on the diminution of value of the property it fails to meet its burden of production. The rationale for the general rule in favor of cost of repairs recovery is bаsed on the purpose of damages in a contract action, which is to restore a plaintiff to the position plaintiff would have been in if the contract had not been breached, rather than to place plaintiff in a better position.
Id. at 752 (internal citation omitted).
In another case cited by Plaintiffs, homeowners sued for damages for breach of contract when windows in a sunroom installed by defendant leaked during storms.
Stom,
“The general rule in calculating damages for a breach of сontract is that the non-breaching party is entitled to the cost of repairing or replacing the defective work.” Ken Cucchi Const., Inc. v. O’Keefe,973 S.W.2d at 527 . But, when the cost of repair or replacement would constitute an economic waste, then the proper measure of damages is the diminished value of the property because of the defective work. Id.; Dubinsky v. U.S. Elevator Corp.,22 S.W.3d 747 , 751-52 (Mo.App. E.D.2000). Economic waste exists when the cost of repair or replacement of the defective property is disproportionate to the diminution in value of the property. Ken Cucchi Const., Inc.,973 S.W.2d at 527 . When the homeowner presents evidence of the cost of repair or replacement, “thе contractor has the burden of presenting evidence that the cost of repairing or replacing the property is disproportionate to the diminution in value of the property.” Id.; see Erney v. Freeman,84 S.W.3d 529 , 536 (Mo.App. S.D.2002).[ 7 ] If the contractor fails to present any evidence of the value of the property, it fails to meet its burden of *552 production. Ken Cucchi Const., Inc.,973 S.W.2d at 527 .
Id. at 364. We concluded that “the trial court erred in applying the law by improperly placing the burden of production of evidence as to diminished value on [plaintiffs] and not [defendant] after [plaintiffs] produced evidence of cost of repair or replacement” ánd remanded the case on the issue of damages. Id. at 365.
In the instant case, the trial court found in favor of the Casons and Hattons on the counts that alleged breach of contract. With the exception of
Evans,
the cases cited by Defendant and those cited by Plaintiffs may be distinguished based on the cause of action asserted by the plaintiff.
8
Despite the language in
Evans
requiring evidence of value as a prerequisite to any consideration of cost of repair in a breach of contract case, we do not believe it governs the case at bar for two reasons. First, the statement is
dicta
as no proper proof of
any
type of damages was presented.
Consequential Damages for Loss of Use
Defendant further argues that because there was no evidence of diminution in value, “the trial court also committed error by awarding [Mr. Cason] $5,000 in damages for the ‘loss of use’ of his lake.” *553 Defendant concedes that damages for lost profits could theoretically be recovered in a case where a business was affected by a period of repair, 10 but he points out that there was no evidence of lost income here. He also argues that while “[Mr. Cason] may have been entitled to recover damages for the problems caused to his lake by the sewage run-off, [ ] hе is not entitled to any amount he asks for.”
The Casons respond that “[a] loss of use award in addition to other damages is not unprecedented” and offer
Children Int’l v. Ammon Painting Co.,
Damages for loss of use have been regarded as consequential damages.
See World Enters., Inc. v. Midcoast Aviation Servs., Inc.,
The parties did not request findings of fact and conclusions of law from the trial court, and specific facts supporting its judgment are not stated. As a result, “all issues of fact on which no specific findings were made are considered to have been found in accordance with the judgment.”
Ankrom v. Roberts,
In the case at bar, the trial court heard evidence that Mr. Cason contracted with Defendant to enlarge the septic system on the Casons’ property because Mr. Cason was building a lake and did not want sewage to leak into it. Further, Mr. Cason expressly told Defendant that he wanted to prevent sewage from leaking into the lake. Defendant’s friend testified that there was no fence around the septic system’s ground field and that there *554 should have been one “from day one” to keep the cows off of it. The trial court could have inferred that Defendant would also have seen the Casons’ cows, that those cows would have access to the lake, and knew, or should have known, that they would be able to drink from the lake if the water in it was potable. Under these circumstances, the trial court did not err in finding that consequential damages in the form of loss of use of the lake were reasonably foreseeable to Defendant at the time of the parties’ contracting.
We must next consider whether the trial court erred in determining the proper amount of damages to award for that loss of use. Defendant asserts in his point relied on that Mr. Cason “did not produce any evidence supporting the $5,000 amount that the court awarded him for loss of use of his lake[.]”
The trial court heard evidence that the purpose of the lake was to water cattle on the 100-acre farm and provide recreation. The evidence was that the watering function was lost as a result of Defendant’s breach of contract, and the recreation function was restricted. But no evidence was presented as to what it cost the Ca-sons to supply their cattle with water by other means or whether it was feasible to clean the lake and, if so, what such an undertaking would cost. Mr. Cason testified that “[t]he lake cost well over $10,000 to build[.]” He then asked the court to award $5,000 for the Casons’ loss of use of their lake. 11
An owner is generally entitled to testify as to the value of his property, but “when [the] property owner’s opinion is based on improper elements or an improper foundation his opinion loses its probative value.”
Cohen v. Bushmeyer,
While one-half of the cost to install the lake might arguably constitute substantial evidence of the value of a permanent loss of one of two intended uses for a private lake, we are not prepared to say that it constitutes substantial evidence of such a loss when the duration of the loss is unknown. As a result, we reverse the trial court’s $5,000 judgment in favor of the Casons for loss of use as not supportеd by substantial evidence and remand the matter for a new trial on the issue of the Casons’ loss of use damages only. 12 In all *555 other respects, the judgment of the trial court is affirmed.
Notes
. Judgment was granted in favor of the Ca-sons and Hattons as to counts one and five of the amended petition. Counts one and five stated claims for breach of contract. A directed verdict in favor of Defendant was granted at the close of Plaintiffs’ evidence as to the remaining counts alleging breach of warranty of merchantability, breach of warranty as to fitness for a particular use, and fraudulent concealment.
. Unless otherwise noted, all rule referencеs are to Missouri Court Rules (2010).
. The plaintiff in Catroppa failed to prove actual damages because he only offered proof of what it originally cost to build the stage. Id. at 818.
. A claim against a public entity with condemning authority based on a theory of nuisance (distinguished from an inverse-condemnation action) is no longer viable.
George Ward Builders, Inc. v. City of Lee’s Summit,
. The loss may also have been based on permanent, not temporary damages. The case was remanded for a new trial on the issue of damages. Id. at 342.
.
Ken Cucchi Constr.
involved a claim and cross-claim between a homeowner and a contractor based on a contract to rebuild a house after the original was destroyed by fire.
. In
Erney,
homeowners sued a contractor for breach of contract involving a botched basement remodel.
. As indicated earlier in the discussion of these cases, the damages were based on: breach of implied warranty of merchantability in
Plunk v. Hedrick Concrete Prod. Corp., 870
S.W.2d 942, 944 (Mo.App. S.D.1994); negligence in
Sheridan v. Sunset Pools of St. Louis, Inc.,
. Defendant does not argue that the amount calculated as repair or replacement damages was not supported by substantial evidence nor that the amount was against the weight of the evidence,
see Murphy v. Carron,
. Defendant cited
Southern Missouri Dist. Council of the Assemblies of God v. Hendricks,
. The trial court may have simply concluded that the Casons were entitled to compensation for half of the minimum it cost them to build the lake because they were unable to use the lake for half of its intended purpose — watering cattle.
. Reversal and remand is the preferred outcome unless it is clear that the Casons would be unable to present any proper proof of their loss of use damages on remand.
Cf. Glenstone Block Co. v. Pebworth,
