MEMORANDUM OPINION
Currently pending and ready for resolution are the following motions: 1) Defendant Chesapeake Electrical Systems, Inc.’s Motion to Dismiss Cross-Claims for Lack of Subjectr-Matter Jurisdiction and, in the Alternative, for Failure to State a Claim Upon Which Relief May be Granted [# 152], 2) L & S Construction’s Motion to Strike Chesapeake Electric Systems Inc. ’s Moot and Untimely Motion to Dismiss, Opposition to Same in the Alternative, and Request for Costs and Attomey[’s] Fees Necessitated in Having to Respond to Same (“L & S’s Mot.”) [# 154], 3) Defendant Chesapeake Electrical Systems, Inc.’s Objection to and Motion to Strike Marathon’s Evidence Submitted in Opposition to Chesapeake’s Motion to Dismiss (“Chesapeake’s MTS”) [# 162], and 4) Cross-Claimant Marathon Corporation’s Motion for Summary Judgment [# 165].
BACKGROUND
The Court will not herein provide a detailed review of the procedural history of this case. Suffice it to say that plaintiff initially alleged various claims against three defendants: 1) Marathon, the general contractor, 2) Capitol Paving, a subcontractor, and 3) Chesapeake Electrical, another subcontractor and that as a result of a cross claim filed by Marathon against third party Ft. Myer Civil, numerous other subcontractors were brought into the suit, along with their various cross and counter claims. The focus of this opinion will be on the claims between defendants Marathon and Chesapeake, and third party defendant L & S, one of the additional subcontractors that was brought into the suit as a result of Marathon’s claim against Ft. Myer.
DISCUSSION
I. L & S’s Motion to Strike Chesapeake’s Motion to Dismiss
L & S moves to strike Chesapeake’s motion to dismiss on two bases. First, L & S argues that the motion to dismiss is moot because the cross claims have already been deemed conceded by the Court: “Due to Chesapeake Electrical Systems, Inc.[’s] failure to answer and/or otherwise file a timely responsive pleading to Marathon and L & S Construction’s Cross — Claims the court has already determined that legal liability with respect to those claims has been conceded.” L & S’s Mot. at 2. Second, L & S argues that Chesapeake waived its right to assert any defenses because of its failure either to timely file an answer or responsive pleading or to move this Court for leave to file its motion to dismiss. Id. at 3.
Chesapeake counters that, pursuant to Rules 12(h)(2) and (3) of the Federal Rules of Civil Procedure, “federal courts must always evaluate their subject matter jurisdiction even if considerable time has passed.” Defendant Chesapeake Electrical Systems, Inc.’s Reply in Support of its Motion to Dismiss and Opposition to L & S Construction’s Motion to Strike at 2 (emphasis in original).
Chesapeake’s interpretation of Rule 12 is correct. In its motion to dismiss, Chesapeake first argues that this Court lacks subject matter jurisdiction under Rule 12(b)(1) and that it is free to make such an argument at any time. Memorandum of Law in Support of Defendant Chesapeake Electrical Systems, Inc. ’s Motion to Dismiss Cross-Claims for Lack of Subjectr-Matter Jurisdiction and, in the Alternative, for Failure to State a Claim Upon Which Relief May be Granted (“Chesapeake’s MTD”) at 5. Without regard to the merits of Chesapeake’s argument, the case law clearly supports the proposition that a court may at any time consider a challenge to its jurisdiction over the subject matter of a case. See Arbaugh v.Y & H Corp.,
II. Chesapeake’s Motion to Dismiss Marathon’s and L & S’s Cross Claims
The gravamen of Chesapeake’s motion is that the Court lacks jurisdiction over the subject matter of Marathon’s and L & S’s cross claims because the relief they seeks is contingent upon a finding of liability on Chesapeake’s part, a determination which the Court is yet to make. Chesapeake’s MTD at 10. L & S counters that it is the practice of this Circuit to allow cross claims for indemnification and contribution to go forward once the underlying liability is determined and that the need for judicial economy argues against dismissing the cross claims at this point in the litigation. L & S’s Mot. at 6.
Pursuant to Article III of the United States Constitution, “the judicial power of the United States, shall be vested in one supreme Court, and in such inferior Courts as the Congress may from time to time ordain and establish.” U.S. CONST, art. Ill, § 1. Such power to preside extends only to “cases” and “controversies.” Id. § 2. In order to determine whether there exists a ease or controversy, the courts have developed various justiciability doctrines. Allen v. Wright,
The first doctrine, standing, contains the following three elements:
First, the plaintiff must have suffered an “injury in fact”-an invasion of a legally protected interest which is (a) concrete and particularized ... and (b) “actual or imminent, not ‘conjectural’ or ‘hypothetical,’ ” ... Second, there must be a causal connection between the injury and the conduct complained of-the injury has to be “fairly ... trace[able] to the challenged action of the defendant, and not ... th[e] result [of] the independent action of some third party not before the court.” ... Third, it must be “likely,” as opposed to merely “speculative,” that the injury will be “redressed by a favorable decision.”
Lujan v. Defenders of Wildlife,
L & S’s and Marathon’s claims for indemnification and contribution are, by their very nature, contingent upon future events because they were asserted as derivative cross claims against Chesapeake as a result of plaintiffs original claims against Chesapeake. While the court of appeals for this Circuit has not yet spoken to the issue, other Cir
There is a perfect coincidence between the application of this principle and this Court’s obligation to apply District of Columbia law in this diversity action. Erie R. Co. v. Tompkins,
The counterclaim for indemnification was properly dismissed because that action is premature. The District has not yet paid any money, and while it could have filed a cross claim for indemnity or contribution in the first action under GS Civil Rule 13(f), it failed to do so. Therefore, we think the general rule that the right to sue for indemnification (absent a specific contract for indemnity to the contrary) accrues when payment has been legally made by the indemnitee applies here. 42 C.J.S Indemnity § 25 (1944).
District of Columbia v. D.C. Transit Sys., Inc.,
If this Court were to entertain the indemnity and contribution claims, the result in this case would be entirely different from the result had the case been filed in the Superior Court, for this Court would be entertaining a case that the Superior Court would dismiss. That result is, simply put, impossible. In Hanna v. Plumer,
Erie and its progeny make clear that when a federal court sitting in a diversity ease is faced with a question of whether or not to apply state law, the importance of a state rule is indeed relevant, but only in the context of asking whether application of the rule would make so important a difference to the character or result of the litigation that failure to enforce it would unfairly discriminate against citizens of the forum State, or whether application of the rule would have so important an effect upon the fortunes of one or both of the litigants that failure to enforce it would be likely to cause a plaintiff to choose the federal court.
Id. at 468 n. 9,
II. Marathon’s Cross Claims Based on Negligence and Breach of Contract State Claims Upon Which Relief Can be Granted and Chesapeake Will Be Deemed to have Admitted Them.
Unlike L & S, which only cross claims for indemnity or contribution, Marathon also presses cross claims for negligence (Count I) and Breach of Contract (Count II). Defendant Marathon Corporation’s Cross-Claim Against Defendant Chesapeake Electrical System, Inc. [# 10-2], In Count I, Marathon alleges that Chesapeake had a duty to Marathon to safely install the wire that struck plaintiff but breached that duty and, as a result, “Marathon has sustained damages in being required to defend the instant lawsuit.” Id. ¶ 8. In Count II, Marathon alleges that it and Chesapeake entered into a contract pursuant to which “Chesapeake agreed to install, monitor, inspect, maintain, and repair” the line that struck Casanova. Id. ¶ 10. Because of the breach of that contract, Marathon “demands judgment against co-defendant Chesapeake for money damages, plus interest, costs, and reasonable attorney’s fees.” Id., ad damnum clause at page 3.
Thus, Marathon is claiming that due to Chesapeake’s negligence, it has sustained damages “in being required to defend the instant lawsuit.” Surely, claims for negligence and breach of contract state claims upon which relief can be granted. They cannot be described as premature since they speak of damages that have already been suffered and are being suffered.
In the ordinary case, those claims would proceed to trial but I have already concluded that Chesapeake must be deemed to have conceded the claims made against it by Marathon and L & S. Casanova v. Marathon Corp.,
III. Chesapeake’s Motion to Strike Marathon’s Opposition Evidence
I have already concluded that statement of a worker, that was referenced by Liberto Nunes, who told Nunes that he had dropped the cable that might have hit Casanova is not hearsay as to Chesapeake. Casanova v. Marathon Corp.,
IV. Marathon’s Motion for Summary Judgement as to Chesapeake
In its motion for summary judgment, Marathon argues that the Court has already concluded that by virtue of Chesapeake’s failure to file a timely answer to Marathon’s cross-claims, “ ‘Chesapeake will be deemed to have conceded the claims made by Marathon.’ ” Memorandum of Points and Authorities in Support of Cross-Claimant Marathon Corporation’s Motion for Summary Judgment [# 165^4] at 3 (quoting Casanova v. Marathon,
While Marathon has not yet sought a default judgment, contrary to Chesapeake’s argument, this in no way affects this Court’s previous finding that by failing to file a timely answer to Marathon’s cross-claim, Chesapeake conceded Marathon’s allegations. Default judgments are governed by Rule 55 of the Federal Rules of Civil Procedure. According to the Rule, where the claim is for an amount that it not yet certain, the prevailing party must apply to the court for a default judgment. Fed.R.Civ.P. 55(b). The basis for this Court’s previous decision denying Chesapeake’s motion for reconsideration was the principle, articulated in the case law and Local Rule 7(b), that a party’s failure to timely file an opposition to a motion seeking relief permitted the Court to 1) strike the untimely opposition, 2) deem the motion conceded, and 3) grant the relief requested. Casanova,
Although Chesapeake has not formally moved this Court to reconsider its December 10, 2007 opinion cited above, it also has not provided any reason for the Court to do so, save its argument that, under Rule 55, it should be permitted to file its answer to Marathon’s cross-claim because a default judgment has not been entered against it. As the Court noted above however, Rule 55 is inapplicable in this situation and therefore the Court’s previous ruling stands. Marathon’s motion for summary judgment regarding its claims of negligence and breach of contract as against Chesapeake will therefore be granted insofar as Chesapeake’s liability will be deemed conceded and denied insofar as there remain genuine issues of material fact as to the amount of damages Marathon incurred.
CONCLUSION
For the reasons stated herein, L & S’s motion to strike Chesapeake’s motion will be denied, Chesapeake’s motion to dismiss Marathon’s and L & S’s cross claims for indemnity and contribution will be granted, Chesapeake’s motion to strike Marathon’s evidence will be denied, and Marathon’s motion for summary judgment as to Chesapeake will be granted in part and denied in part. An Order accompanies this Memorandum Opinion.
