10 Utah 322 | Utah | 1894
In this case it appears that the appellant Partridge, having a contract interest in land belonging to one Elmira Shearman, contracted with Charles Sheets, the contractor, by which Sheets was to furnish material and build a house upon 'the premises, for which Sheets was to receive 12,200, in -certain payments, as the building progressed. Elmira Shearman held the legal title to the land, and Partridge was in possession under contract of purchase. Elmira Shearman, furnished Partridge $2,200, with which to build the house, and, when paid for, Partridge was to receive the legal title. The findings of fact by the referee show
The court, on motion, set aside the conclusions of law by the referee, and entered a decree that plaintiff had a lien against the property fo,r the sum of §646.52, due and owing plaintiff from Sheets, and ordered sale of the property to satisfy the decree. This decree and judgment are appealed from, and error is assigned in the refusal of the court to affirm the report of the referee, and in setting aside the conclusion of law found by the referee, and in granting the decree, under the facts found. We deem it unnecessary to discuss any of the assignments of error except the last. The questions presented are whether or not Partridge was the owner or had such an interest in the property as would authorize a mechanic’s lien to attach to it; and, second, when, if at all, such lien should attach, so as to affect the rights of the owner who had
TJnder sectiop 1, p. 24, Sess. Laws 1890, “whoever shall do work or furnish materials by contract, express or implied,, with the owner of any land, to any amount, for the construction, * * * of any building * * * shall have a lien thereon * * * for the amount and value of the work so done, or material so furnished to the extent of the interest or claims of such owner thereto at the time of the commencement to do such work or to furnish such materials. Said lien shall likewise attach to another or greater interest in any of such property acquired by such owner at any time subsequent to such commencement to do-work or to furnish materials and before the establishment of said lien by process of law, * * * any person having an assignable, transferable or conveyable interest or claim in or to' any land, building, structure, or other property mentioned in this act, shall be deemed an owner. ^ Under the findings of fact', Mr. Partridge had an equitable interest in the premises. He had contracted with Sheets to build the house for him. Mrs. Shearman had furnished him $2,200 with which to build the house on this land, and when Partridge had paid for the land he was, by contract, to receive the legal title to it. He was in possession when the contract was made, and had the supervision of the building. Such being the case, he must be held to have had an assignable, transferable, or conveyable interest and claim to the land and premises, sufficient to be the owner, within the meaning of the statute. Such lien under the statute may also be extended, to any other or greater interest which, such owner may acquire to such property thereafter, and before the lien is established by process of law. Morrison v. Carey-Lombard Co., 9 Utah, 70, 33 Pac. 238; Sess. Laws 1890, p. 25, § 2. Under Sess. Laws 1890, p. 29, § 19, “ all such liens
It will be seen that, under the findings of fact, Sheets performed the labor and furnished the material between the 9th of June and the 19th of July, 1890, and that the plaintiff commenced furnishing material for the building June 9, and continued to furnish such material until July 12, 1890. The plaintiff’s lien was filed July 29, or within 17 days from the date of the last material furnished. This brings the act of filing the lien within the 40 days limited by sections 10 and 11, p. 26, Sess. Laws 1890. Under these statutes, from the day the sub-contractor or material man commences to furnish material, it is notice to the owner, and to all other persons thereafter contracting with the owner, that the property is burdened with a lien, and no previous notice is required to be given the owner than the fact of the delivery of the material for the construction of the building. Such lien relates back to the time of the furnishing materials, and under section 2, referred to, the sub-contractor has a lien upon any and all such property in like manner as said principal contractor under section 1 of the act. Sections 1 -and 2 refer to those persons who shall do work, while section 12 refers to that class of persons who shall intend to do work or intend to furnish materials at some future day. If one ■enters into a contract with another of a higher degree, to do work or furnish materials at some future day, he may, under section 12 of this statute, file this statement; and from the time he files it “he shall have a lien for such work thereafter done by him, or for such materials thereafter furnished by him not exceeding the sum stated
The effect of these provisions is to protect him against, and to give him priority over, any other sub-contractors who might commence to do work or to furnish materials between the date of his contract and the date of his entering upon the performance of it; and no lien can attach in favor of any such claimant until he files this statement, or begins to. work or to furnish materials. Any other construction of these provisions of the statute would render sections 1 and 2 repugnant to section 12, and give no effect to the former, as applied to sub-contractors, which would be contrary to the proper rule of construction,— that when an act is susceptible of two constructions, and one gives effect to all its provisions and the other does not,- the one giving effect to all should be adopted. These questions were carefully and ably considered by Mr. Justice Bartch in the case of Morrison v. Carey-Lombard Co., 9 Utah, 70, 33 Pac. 238, and >vere referred to in Teahen v. Nelson, 6 Utah, 363, 23 Pac. 764, to which reference may 'be had.
We are of the opinion that the lien of the plaintiff attached at the time the first materials were furnished the contractor; that Partridge, the owner, was bound to take notice of such lien, and any payments made by him to the contractor after such lien attached must be held to have been made at his risk and peril. Upon the whole case, we find no error. The judgment of the district court is affirmed, with costs.