224 Pa. 319 | Pa. | 1909
Opinion by
Plaintiff was a workman employed by a subcontractor who had engaged to erect and put in place the iron trusses and beams required by the specifications for the roof of a public school building which the defendant company had contracted to build. When the last of the trusses was about to be placed in position on the walls, something gave way, and the truss fell to the ground below, carrying with it the plaintiff who in the mishap was severely injured. He brought this action for damages against the defendant company, the general contractor, charging it in the statement filed with negligence in having failed to provide sufficient and proper appliances, and permitting certain supports for the roof of the building to be violently thrown to the ground. On plaintiff’s part the case was tried on the theory that the proximate cause of the plaintiff’s injuries was the negligent and defective construction of that part of the wall known as the pilaster, the angular projection of the wall on the top of which the iron truss was intended to rest for support. We need waste no time or
It was developed as part of plaintiff’s case that had the pilaster been constructed in conformity with the architect’s specifications, it would have been more than adequate for the support of the truss. Defendant’s evidence was to like effect. The whole effort on part of the plaintiff was to show that the pilaster had not been so constructed, and that the accident resulted in consequence of this want of conformity. Was the evidence on this point sufficient to carry the case to the jury? Briefly it was this. Two witnesses called by plaintiff testified that after the collapse they had examined the mortar in which the bricks and stones had been laid and described it as “dry and crumbly,” both said it was in bad condition; one, that “it would crumble out like sand, was spongy;” the other, that “it was dry and crumbly, and in bad condition.” This was followed by the testimony of an expert witness, called by plaintiff, who testified that had the mortar been made of the materials called for by the specifications, and mixed in the proportions required, when examined “it would
The jury having found for plaintiff, a motion for judgment non obstante followed. One of the reasons urged in support of the motion was that the wall had been built by an independent subcontractor, that no liability, therefore, attached to the defendant. This point assumes as a fact what was found not to be a fact by the jury. The court was asked to instruct the jury that the wall had been built by an independent subcontractor. This instruction was refused very properly, because the evidence relied upon to establish such fact was wholly in parol, and this circumstance drew the question to the jury necessarily, notwithstanding the fact that the testimony in regard to it was uncontradicted. The court could go no further in this direction than to say to the jury — and this should have been said — that if they believed the testimony of plaintiff's witnesses then the party who had built the walls was an independent subcontractor within the meaning of that term as defined by the court. The credibility of the witnesses was for the jury.
Upon the review we have made of the case, it sufficiently appears without specifying further, that the case required a submission; not, however, for a choice between conflicting
The judgment is reversed, and a venire de novo awarded.