290 Mass. 97 | Mass. | 1935
This is a petition brought by the petitioner under the provisions of G. L. (Ter. Ed.) c. 30, § 39, to establish his claim for labor and materials furnished the
The master found that on February 2, 1932, a contract was executed between the respondents Rooney and Company and the Commonwealth of Massachusetts for the construction of a section of State highway. This was a public work, and a performance bond as required by G. L. (Ter. Ed.) c. 30, § 39, in the amount of $231,000 was executed by the respondent Rooney and Company as principal and the respondent Maryland Casualty Company as surety. . The Commonwealth has in its hands $53,829.72 remaining due to Rooney and Company, being, with the bond, the security required by the statute. The project has been completed and was accepted by the Commonwealth on February 14, 1933, as of February 2, 1933.
The claims of numerous interveners were dealt with in the master’s report in accordance with the alphabetical order of their names. As to the claim of DiPietro the master found as follows: On March 31, 1932, DiPietro entered into a contract with Rooney and Company to perform certain work required by the contract with the Commonwealth in laying drainage pipes. In pursuance of this contract he furnished labor at prices totalling $9,024.82, which were agreed to by the parties. The work provided by the contract with Rooney and Company was that he should “furnish and lay all side drains including all material and labor” and that he should “lay” certain sizes of drain
In Peerless Unit Ventilation Co. Inc. v. D’Amore Construction Co. 283 Mass. 121, 124, 125, it was said: “Work actually called for by the contract or continuing employment, performed in good faith with the intention of completing the job, though done with the ulterior purpose of saving the hen and postponed until long after the bulk of the work has been completed, will permit the filing of the statement within sixty days after the doing of the last work. . . . But ... a gratuitous performance of work not contracted for, does not set the time running so as to preserve a Hen for the earlier work.” Besides, work done to correct defects or to make substitution for previous faulty performance is equally effective to renew the period for filing the claim for a lien. Such correction is as much needed to furnish a complete and proper performance of the contract as work done to finish a previously unfinished detail of the work. In either case the contract obligation is unfulfilled pending the performance of such additional work. See Winer v. Rosen, 231 Mass. 418; McLean v. Wiley, 176 Mass. 233, 234. “Work done to remedy defects may be considered in deciding whether a claim is filed in time.” Dolben v. Duncan Construction Co. 276 Mass. 242, 251.
The appellants contend that for two reasons all contract obligations of DiPietro had ceased when the pipe was originally laid, and hence that any work thereafter done could not have been work called for by the contract. In the first place it is found that this pipe had been laid originally “under the constant supervision of the State engineer and to his satisfaction.” It thus appears that at the time the work was being done the methods employed were satisfactory to the engineer and he saw nothing to criticize in the manner in which the work was performed. It is plain that this pipe in a defective condition would not have been satisfactory on February 2, 1933, when the work as a whole was finally accepted. There was no previous acceptance of the work by Rooney and Company. Moreover, in addition to the express requirement in DiPietro’s contract to perform the work in a satisfactory manner, there was a requirement that the work should measure up to the terms and conditions of the contract between Rooney and Company and the Commonwealth. It was, then, clearly within DiPietro’s obligation to furnish work which would meet with the State engineer’s approval when the time came to accept the work from. Rooney and Company. Besides, it does not appear that at any time previous to the time the pipe was repaired DiPietro’s contract obligation was considered by the parties to be at an end or fully performed so that Rooney and Company would have been precluded from requiring further performance in case DiPietro were in fact at fault in respect to the defective work. The contract between the parties was not treated by them as completed. See Monaghan v. Putney, 161 Mass. 338, 339. Nor could it have been the intention of the parties on a reasonable construction of the contract
The appellants’ second ground of contention that DiPietro’s contractual obligation was at an end is that there is no proof that DiPietro was at fault for. the defective condition of the work. If Rooney and Company could not prove that DiPietro was at fault for the defect it could not prove the obligation to remedy it. Yet the fact might remain that DiPietro had been to blame for the faulty work. It appears that he was willing to accept responsibility for the defect because it occurred in a portion of the work done under his contract, and he made the repairs and remedied the defect. In view of the possibility that he was responsible, it cannot rightfully be held that he was bound to wait until the defect was actually brought home to him before the repair could be held to have been made under the contract. We are of opinion that the work in the circumstances here shown could be found to have been done under his contract if it was “reasonably necessary in order to make a good job and was done in good faith.” Dolben v. Duncan Construction Co. 276 Mass. 242, 252. In that case there was no proof that the particular work done by the Richmond Fireproof Door Company was a specific obligation under its contract, yet it was held that the work, done in good faith by the claimant “to make a good job,” could have been found reasonably necessary to complete the original contract obligation of the claimant and that the work was effective in preserving the lien. In the case at bar it could have been found that DiPietro by his contract assumed the risk of defects in the soil or in previous work and so his work could be reasonably found to be required to complete his obligation under the contract, regardless of his own fault as to causing the defect. It is plain that he agreed to provide Rooney and Company with work which would be acceptable. See
As to the claim of the Quincy Lumber Company, the facts found by the master show that this company furnished lumber to another intervener, the Albany Bridge Construction Company, Inc., at agreed prices totalling $581.11, the last.of such material being delivered on July 12, 1932, and that such amount is still due. On July 25, 1932, within the sixty days specified by the statute, the Quincy Lumber Company duly filed its sworn statement of claim under the statute with the proper State officer. The lumber so furnished was “used and reused several times by the Albany Company for forms for the concrete installed by it on this project, until it was entirely unfit for further use as forms and [was] given away as scrap.” The only question before this court in connection with this claim is whether the Quincy Lumber Company is entitled to share in the security provided by the bond and the moneys retained under the contract by the Commonwealth. This depends upon the ques
The interlocutory decree entered April 18, 1934, as of April 14, 1934, is affirmed. The final decree entered April 18, 1934, as of April 14, 1934, is modified by striking out the provision for payment to Quincy Lumber Company and by dismissing the petition of Quincy Lumber Company without prejudice to proceedings by it against Albany Bridge Construction Company, Inc., and as modified is affirmed.
Ordered accordingly.