— Appellant filed his final report as constructing commissioner of a drain established under the provisions of the act of 1885, §5622, et seq. Burns 1901. Appellees, being interested landowners, filed exceptions to divers items claimed as credits, which exceptions were sustained to items four, five, six, seven, and eight.
The material facts are these: June 30, 1893, appellant was appointed construction commissioner, and in due time contracted the work to be performed according to plans and specifications. January 2, 1894, one Hancock, an interested party, filed in court his petition reciting that the commissioner was about to accept said ditch as completed, while in fact it was incomplete, and requested the court to appoint and sencj, out an engineer to verify the work. January 16, 1894, upon appellant’s motion, the court struck out Hancock’s petition. On June 11, 1894, numerous other interested landowners filed a petition praying the court to grant an order against appellant to show cause why he did not, as commissioner, proceed to complete said drain in accordance with the plans and specifications. The order was issued, and on September 17, 1894, appellant appeared to the petition, and filed an answer thereto in two paragraphs: (1) A general denial, and (2) an argumentative denial. The completion of the drain being thus put in issue, — affirmed by appellant, and denied by the landowners, — was submitted to the court for trial. The contractor, whose duty it was to construct the drain according to the specifications, does not seem to have been made a party, or to have been brought
The first four of these items were wholly disallowed, and the last disallowed for one-half of the amount. The action of the court upon these items presents the real question in the case. With respect to the first four items, they wei’e for disbursements in carrying on the controversy that arose over
The obstinacy of appellant is unaccountable. It appears that ten months after the court had adjudged the ditch incomplete, and had ordered him to proceed without unnecessary delay to complete it in accordance with the report of the three special engineers, appellant, upon order of the court to show cause, reported that the drain was completed in accordance with the order and plans and specifications, and, at the same time, in his answer to interrogatories, admitted that no work had been done on the ditch since the court’s order, for the reason that upon a careful examination by himself and others it was found that the ditch already met all the requirements of the plans and specifications. And, furthermore,'upon the court’s peremptory rule to proceed forthwith to comply with the order of the court, he, upon his own motion, and without the advice or approval of the court, employed the county surveyor to take charge and superintendence of the additional work required, and paid him therefor $104, being $4 per day for twenty-six days’ work.
Appellant had no authority under the láw (§5626 Burns 1901) to pay any of the items in controversy here until the claim therefor had first been presented to and allowed by the court. His failure first to procure the approval of the court left the propriety of the payment an open question to be decided when credit therefor was claimed.
As to item fifteen, being for amount paid the county surveyor for services in superintending additional work required, the expenditure can only be justified upon the ground that that amount of skilled labor was reasonably necessary to the proper execution of the work. Whether or not it was necessary was a question of fact to be determined from the evidence, and, the court having found against the
• The court was clearly right in disallowing items eighteen, twenty-three, and twenty-five. Whatever sums appellant paid to attorneys, or expended as costs, or caused others to expend in his strange effort to prevent the landowners from enforcing a proper construction of the drain, were not chargeable against the ditch assessments. The allowance of the claim for costs is urged for the reason that no judgment for costs was rendered against appellant. It is a sufficient answer to say, neither was there a judgment for costs rendered against the drainage fund. The costs were simply taxed in the proceeding by the clerk, without judgment against any one, and were paid by appellant, without any action of the court authorizing him to do so.
It is also insisted that item twenty-five, being for amount paid the three special engineers appointed by the court, should have been allowed, because the engineers were appointed by the court, and their claims approved before payment. This prior approval by the court does not alter the case in this instance. The claim was disallowed, not because the services were needless, nor because the amount paid was unreasonable, but because the appointment and expenditure were, by the unwarranted conduct of appellant, made necessary to enable the court correctly to determine the controversy precipitated by him. Whether the parties did, or not, agree to the appointment is of no consequence. The court made the appointment as it had the right to do with or without an agreement. It can not be doubted that the court had power, as it has in all doubtful cases, to take such reasonable steps as will bring accessible, trustworthy evidence before it, and adjudge the cost thereof as an incident of the trial.
With respect to item twenty-six, it is contended that the court erred in reducing appellant’s service claim from 144 to seventy-two days; the argument being that since all the
There are other questions presented, relating to the admission and exclusion of evidence, that we have not considered for the reason that they are of such minor importance as would not, if erroneous, warrant a reversal of the judgment, which is plainly right upon the merits.
Judgment affirmed.