MEMORANDUM OPINION
This case arises from a critical habitat designation and recovery plan that defendant U.S. Fish and Wildlife Service (the “FWS”) promulgated with respect to the threatened northern spotted owl in 2008. Plaintiffs Carpenters Industrial Council, American Forest Resource Council, Swanson Group, Inc., Rough & Ready Lumber Co., Perpetua Forests Company, and Seneca Jones Timber Company (collectively, the “CIC plaintiffs”) contend that the FWS’s final rule on the Revised Designation of Critical Habitat for the Northern Spotted Owl, 73 Fed.Reg. 47326 (the “2008 Critical Habitat Designation”), was arbitrary and capricious and rendered in violation of the National Environmental Policy Act (“NEPA”), 42 U.S.C. §§ 4321 et seq., the Endangered Species Act (“ESA”), 16 U.S.C. §§ 1531 et seq., and the Administrative Procedure Act (“APA”), 5 U.S.C. § 553. Plaintiff-intervenors Seattle Audubon Society, National Center for Conservation Science and Policy, Oregon Wild, Klamath-Siskiyou Wildlands Center, Wilderness Society, Sierra Club, Center for Biological Diversity, Environmental Protection Information Center, Conservation Northwest, Audubon Society of Portland, National Audubon Society, Cascadia Wild-lands Project, Klamath Forest Alliance, Conservation Congress, American Bird Conservancy, Umpqua Watersheds, and Gifford-Pinchot Task Force (collectively, the “Seattle Audubon plaintiff-intervenors”), challenge the federal defendants’ 2008 Critical Habitat Designation as well as the 2008 Recovery Plan for the Northern Spotted Owl (the “2008 Recovery Plan”) pursuant to the ESA and the APA.
Pending before the Court is the federal defendants’ motion for voluntary remand and vacatur. In their motion, the federal defendants confess legal error as to the 2008 Critical Habitat Designation and the 2008 Recovery Plan, and ask the Court to: (i) remand and vacate the 2008 Critical Habitat Designation; (ii) remand the 2008 Recovery Plan; and (iii) order the FWS, after issuance of a revised recovery plan, to evaluate whether revision of the 1992 Critical Habitat Designation is appropriate, and if so, to complete rulemaking for a new critical habitat designation after issuance of a revised recovery plan. Fed. Defs.’ Mot. at 1-2. The Seattle Audubon plaintiff-intervenors consent to the requested relief and ask the Court to enter the proposed order submitted by the federal defendants, see generally Seattle Audubon Mot., 1 while the CIC plaintiffs op *129 pose the requested relief and urge the Court to enter a briefing schedule on cross-motions for summary judgment, see CIC Opp’n Br. at 32. Upon consideration of the motions, the response, the replies and sur-replies thereto, the applicable law, the parties’ arguments at the January 20, 2010 hearing, and all post-argument briefs, the Court GRANTS IN PART AND DENIES IN PART the federal defendants’ motion for remand and vacatur. As discussed below, the Court GRANTS the federal defendants’ request to remand the 2008 Critical Habitat Designation and 2008 Recovery Plan, and DENIES the federal defendants’ request to vacate the 2008 Critical Habitat Designation.
1. BACKGROUND
The northern spotted owl is a medium-sized nocturnal bird that inhabits old-growth forests of western North America, including parts of northern California, the Pacific Northwest, and British Columbia. CIC Am. Compl. ¶ 15; Seattle Audubon Compl. ¶ 28. Due to concerns regarding the widespread loss and modification of the owls’ habitat, on June 26, 1990, the FWS published a final rule listing the northern spotted owl as a “threatened species” under the ESA. CIC Am. Compl. ¶ 16 (citing 55 Fed.Reg. 26114); Seattle Audubon Compl. ¶ 34. 2 The final listing rule indicated that the northern spotted owl is threatened throughout its range “ ‘by the loss and adverse modification of suitable habitat as the result of timber harvesting and exacerbated by catastrophic events such as fire, volcanic eruptions, and wind storms.’ ” Seattle Audubon Compl. ¶ 31 (quoting 55 Fed.Reg. 26151). Consequently, on January 15,1992, the FWS designated 6,887,000 acres in California, Oregon, and Washington as critical habitat for the northern spotted owl (the “1992 Critical Habitat Designation”). CIC Am. Compl. ¶ 20; Seattle Audubon Compl. ¶ 37. 3
While no recovery plan was immediately developed for the owl, on April 13, 1994, the Secretary of Agriculture and the Secretary of Interior developed a land management plan for the owl referred to as the “Northwest Forest Plan.” CIC Am. Compl. ¶ 22; Seattle Audubon Compl. ¶¶ 38-39. After determining that the Northwest Forest Plan provided a sound framework for the recovery of the owl, the FWS suspended the northern spotted owl recovery plan preparation process. See also Seattle Audubon Compl. ¶ 39 (explaining that the Northwest Forest Plan did not satisfy the ESA’s criteria for a recovery plan). 4
*130 In May 2006 — nearly sixteen years after the northern spotted owl was listed as a threatened species — the FWS assembled a recovery team (the “Recovery Team”) which began to devise a recovery plan for the owl. Seattle Audubon Compl. ¶45. 5 In September 2006, the Recovery Team forwarded its draft recovery plan to FWS’s Washington, D.C. headquarters for review by an oversight committee (the “Washington Oversight Committee”). Seattle Audubon Compl. ¶ 47. One member of the Washington Oversight Committee was Former Deputy Assistant Secretary Julie MacDonald (“Deputy Assistant Secretary MacDonald”). Seattle Audubon Compl. ¶ 47. The Washington Oversight Committee informed the Recovery Team that it was concerned that the draft recovery plan was based on the Northwest Forest Plan and purportedly advised the team to (i) “put less focus on habitat preservation and to de-link the recovery plan from the Northwest Forest Plan”; (ii) “include a second alternative that did not rely on fixed habitat reserves”; and (iii) “minimize the threat to northern spotted owls from the loss of habitat and emphasize the threat from barred owls.” Seattle Audubon Compl. ¶ 48; see also Seattle Audubon Ex. A, Docket No. 45-2, Investigative Re port: The Endangered Species Act and the Conflict between Science and Policy at 27-28.
Based on the guidance issued by the Washington Oversight Committee, significant revisions were made to the initial draft recovery plan. A revised draft recovery plan was published on April 26, 2007 (the “2007 Draft Recovery Plan”), Seattle Audubon Compl. ¶ 52, and the final recovery plan for the owls was issued on May 13, 2008 (the “2008 Recovery Plan”), Seattle Audubon Compl. ¶ 58.
Following issuance of the 2008 Recovery Plan, on August 13, 2008, the 1992 Critical Habitat Designation was replaced by the 2008 Critical Habitat Designation. Seattle Audubon Compl. ¶ 68. The 2008 Critical Habitat Designation, which was based on both the 2007 Draft Recovery Plan and the final 2008 Recovery Plan, see 73 Fed.Reg. 47,328, 6 reduced designated northern spotted owl habitat by approximately 1,574,000 acres, Seattle Audubon Compl. ¶ 68.
Displeased with the 2008 Critical Habitat Designation, on August 13, 2008, the CIC plaintiffs fried the instant action alleging that the 2008 Critical Habitat Designation violates NEPA, ESA, and the APA. The CIC plaintiffs seek declaratory and *131 injunctive relief, and ask the Court for “a limited remand without vacatur [of the 2008 Critical Habitat Designation] to address the specific legal inadequacies presented in their complaint.” CIC Opp’n Br. at 8.
On November 14, 2008, fourteen environmental conservation groups sought leave to intervene in the action, which this Court granted on February 18, 2009. Pursuant to the ESA and the APA, the Seattle Audubon plaintiff-intervenors challenge the FWS’s issuance of the 2008 Critical Habitat Designation as well as the 2008 Recovery Plan. Plaintiff-intervenors seek declaratory and injunctive relief, and ask the Court to remand the 2008 Critical Habitat Designation and the 2008 Recovery Plan and reinstate the original 1992 Critical Habitat Designation.
On December 22, 2008, the federal defendants notified the Court that the Inspector General of the Department of Interior had issued an Investigative Report entitled “The Endangered Species Act and the Conflict Between Science and Policy” (hereinafter, the “IG’s Report”), which examined the influence of Deputy Assistant Secretary MacDonald on twenty ESA decisions and actions, including the recovery plan for the northern spotted owl. See Notice, Docket No. 22. The IG’s Report concludes that Deputy Assistant Secretary MacDonald, acting alone or in concert with other Department officials, took actions that “potentially jeopardized” the decisional process for the recovery plan of the owl. See generally Seattle Audubon Ex. A, Docket No. 45-2 (Letter from Inspector General Earl E. Devaney to former Secretary of the Interior Dirk A. Kempthorne, dated Dec. 15, 2008, and the attached IG’s Report). In their notice, the federal defendants advised the Court that it needed to reviéw the IG’s Report and the administrative record for the 2008 Recovery Plan and the 2008 Critical Habitat Designation “to determine whether to continue this litigation, amend their litigation posture, or pursue further administrative action with respect to this final recovery plan.” Notice, Docket No. 22 at 2. On March 31, 2009, the federal defendants informed the court that it had concluded its review, and determined that it was appropriate to seek a remand of the 2008 Recovery Plan and 2008 Critical Habitat Designation. See Notice, Docket No. 35.
Accordingly, on July 30, 2009, the federal defendants filed their motion for voluntary remand and vacatur. The Seattle Audubon plaintiffs then filed a motion in support of the federal defendants’ request for remand and vacatur, while the CIC plaintiffs filed an opposition brief. The federal defendants’ motion is now ripe for determination by the Court.
II. ANALYSIS
In their motion, the federal defendants “confess[ ] legal error as to the 2008 critical habitat designation and recovery plan,” and ask the Court to: (i) remand and vacate the 2008 Critical Habitat Designation, thereby restoring the 1992 Critical Habitat Designation for the owl; (ii) remand the 2008 Recovery Plan and order the FWS to issue a revised recovery plan within nine months of the Court’s remand order; and (iii) order the FWS, after issuance of the revised recovery plan, to evaluate whether revision of the 1992 Critical Habitat Designation is appropriate, and if so, to complete rulemaking for a new critical habitat designation with 24 months of the issuance of the recovery plan. Fed. Defs.’ Mot. at 1-2. As discussed above, the Seattle Audubon plaintiff-intervenors consent to the requested relief, while the CIC plaintiffs oppose it. The Court will explore the federal defendants’ requests in turn.
*132 A. Voluntary Remand & Vacatur of the 2008 Critical Habitat Designation
1. Voluntary Remand
The first issue to be resolved is whether the Court has the authority to remand the 2008 Critical Habitat Designation to the FWS, and if it does, whether voluntary remand is appropriate. Federal defendants and plaintiff-intervenors argue that the Court may exercise its equitable power to order voluntary remand because the federal defendants admit that “the recovery plan and critical habitat revision for the northern spotted owl are legally erroneous”; in light of this admission, these parties argue that “further proceedings on the claims presented by CIC and Seattle Audubon would simply waste the resources of the Court and the parties.” Fed Defs.’ Mot. at 7-8; Seattle Audubon Mot. at 6. The CIC plaintiffs, by contrast, contend that the Court lacks the authority to remand and vacate the 2008 Critical Habitat Designation without a final determination of the merits, see CIC Opp’n Br. at 10-16, and that even if it does, remand is unwarranted, see CIC Opp’n Br. at 17-22. For the reasons discussed below, the Court concludes that it has the authority to remand the 2008 Critical Habitat Designation, and that voluntary remand is, in fact, appropriate in this case.
i. The Court’s Authority to Grant Voluntary Remand
As a threshold matter, courts have long recognized the propriety of voluntarily remanding a challenged agency action without judicial consideration of the merits upon an admission of agency error. Specifically, courts have recognized that voluntary remand is generally appropriate (i) when new evidence becomes available after an agency’s original decision was rendered,
see, e.g., Ethyl Corp. v. Browner,
Indeed, at least three courts have granted the FWS’s requests for voluntary remand where new evidence or a change in the law rendered the agency’s critical habitat designations suspect.
See Alliance for the Wild Rockies, Inc. v. Allen,
No. 04-1813,
Therefore, consistent with the case law discussed above, the Court concludes that it has the equitable power to grant the federal defendants’ request for voluntary remand. 7
ii. The Appropriateness of Voluntary Remand
Having determined that it has the authority to grant voluntary remand, the Court must now determine whether the FWS’s request is warranted. The federal defendants and the Seattle Audubon plaintiff-intervenors argue that voluntary remand is appropriate in light of the IG’s Report, which found that the decisional. process for the recovery plan for the northern spotted owl was “potentially jeopardized” by the actions of Deputy Assistant Secretary MacDonald. The federal defendants explain that “[rjeconsideration here would allow the Service to remove any question of potential taint from Ms. MacDonald’s interference and ensure that the owl’s survival and recovery are supported by scientifically valid measures.” Fed. Defs.’ Reply Br. at 9. The CIC plaintiffs reject this contention, arguing that “[t]he Court must independently determine whether legal error occurred, and may not simply accept confession of error by the government,” and that, in any event, “[t]he record does not establish any legal error that permits remanding the *134 2008 critical habitat rule to the FWS.” CIC Opp’n Br. at 17, 18. Finding the federal defendants’ request for voluntary remand .consistent with the case law discussed above, the Court will explore the CIC plaintiffs’ objections in turn.
With regards to the CIC plaintiffs’ first objection,
see
CIC Opp’n Br. at 17-18, the Court is not persuaded that it must independently determine whether legal error occurred in order to grant a request for voluntary remand. While it is undoubtedly true that “[a] court is ‘not obligated to accept the government’s confession of error, particularly when there is reason to doubt whether the government’s position is correct,’” CIC Opp’n Br. at 17, the CIC plaintiffs’ contention that the Court
must
conduct an independent inquiry to determine that wrongdoing occurred in order to remand an agency decision for reconsideration is unpersuasive.
See, e.g., Sierra Club,
Moreover, the Court also disagrees with the CIC plaintiffs’ assertion that the record lacks evidentiary support for the federal defendants’ confession of legal error. Indeed, to the contrary, the Court finds that the federal defendants submitted compelling evidence in support of their claim of legal error and request for remand: the IG’s Report, which was completed before the change in administrations. See Fed. Defs.’ Reply Br. at 8-12. Given the current posture of this case, the Court finds no reason to question the Inspector General’s determination that Deputy Assistant Secretary MacDonald’s “zeal to advance her agenda ... [and] heavy-handedness ... potentially jeopardized” the FWS’s 2008 rulemaking as to the northern spotted owl. See Seattle Audubon Ex. A, Docket No. 45-2 (Letter from Inspector General Earl E. Devaney to former Secretary of the Interior Dirk A. Kempthorne, dated Dec. 15, 2008). 8
Therefore, in view of the federal defendants’ later-acquired information regarding the actions of Deputy Assistant Secretary MacDonald, which raise “substantial and legitimate concerns” about the rule-making process for the northern spotted owl, the Court concludes that the FWS’s request for voluntary remand is well justified.
See also, e.g., Alliance for the Wild Rockies, Inc.,
2. Vacatur
Having concluded that the 2008 Critical Habitat Designation should be remanded for reconsideration, the Court must now determine whether it has the authority to vacate the 2008 Critical Habitat Designation, thereby reinstating the preceding 1992 Critical Habitat Designation for the owl, and if so, whether vacatur is appropriate. The federal defendants argue that in light of their confession of “legal error” the 2008 Critical Habitat Designation should be vacated, explaining that “ ‘[t]he usual remedy for a procedural violation of the APA is to set the regulation aside.’ ” Fed. Defs.’ Mot. at 10 (quoting
Endangered Species Comm. of the Building Ass’n v. Babbitt,
i. The Court’s Authority to Vacate the 2008 Critical Habitat Designation Without a Determination of the Merits
The federal defendants and the Seattle Audubon plaintiff-intervenors argue that the Court has the authority to vacate the 2008 Critical Habitat Designation without making a determination of the merits as a result of the federal defendants’ confession of legal error.
See
Fed. Defs.’ Mot. at 11-13; Fed. Defs.’ Reply Br. at 18-23;
see also
Seattle Audubon Post-Argument Br. at 4 (“Here, by itself, the federal defendants’ confession of legal error is sufficient to justify vacating the 2008 critical habitat revision under 5 U.S.C. § 706(2).”). Although two courts have agreed with this position and exercised their equitable power to summarily vacate critical habitat designations,
see Coal. of Arizona/New Mexico Counties for Stable Econ. Growth v. Salazar,
No. 07-876, slip op. at 5 (D.N.M. May 4, 2009);
Natural Res. Def. Council,
ii. The Propriety of Ordering Partial Summary Judgment Briefing
The Court also declines the invitation of the Seattle Audubon plaintiff-intervenors to proceed with partial summary judgment briefing on the issue of whether the improper influence of Deputy Assistant Secretary MacDonald caused the 2008 Critical Habitat Designation to depart from the best available science. See Seattle Audubon Posfl-Argument Br. at 5. 10 While the Court is sensitive to the plaintiff-intervenors’ strong opposition to remand without vacatur, see Seattle Audubon’s Posfl-Argument Br. at 3, the Court concludes that such a piecemeal approach to the resolution of this litigation is not in the interest of justice.
The Court, therefore, concludes that remand of the 2008 Critical Habitat Designa *137 tion without vacatur is the most equitable outcome, as it will preserve this Court’s scarce judicial resources by allowing the FWS to cure its own purported “legal error,” and allow the agency to focus its efforts on issuing a revised recovery plan and critical habitat designation for the owl. See Fed. Defs.’ Post-Argument Reply Br. at 4 n. 3 (explaining that requiring the FWS to file an administrative record in this case “would have the disadvantage of delaying resolution of this case and agency reconsideration of the owl’s critical habitat needs” because “agency personnel now working on the habitat reserve system for any revised recovery plan would have to delay that work and be tasked with preparation of the record”). Accordingly, the federal defendants’ request for vacatur of the 2008 Critical Habitat Designation is DENIED.
B. Remand of the 2008 Recovery Plan
Next, the federal defendants and the Seattle Audubon plaintiff-intervenors ask the Court to remand the 2008 Recovery Plan to the agency and to order the FWS to issue a revised plan within nine months of the Court’s remand order.
11
Although the CIC plaintiffs do not challenge the lawfulness of the 2008 Recovery Plan, they nevertheless object to the federal defendants’ request for remand arguing that the Court lacks jurisdiction to remand a recovery plan. Substantially for the reasons stated in the federal defendants’ post-argument reply brief, the Court disagrees.
See
Fed. Defs.’ Post-Argument Reply Br. at 2 (explaining that the APA’s final agency action requirement is not jurisdictional in this Circuit (citing
Trudeau v. FTC,
C. Rulemaking for a New Critical Habitat Designation
Finally, the federal defendants ask the Court to order the FWS, after issuance of the revised recovery plan, to evaluate whether revision of the 1992 Critical Habitat Designation is appropriate, and if so, to complete rulemaking for a new critical habitat designation with 24 months of the issuance of the recovery plan. The Court finds this request — which was premised upon vacatur of the 2008 Critical Habitat *138 Designation — moot in light of the Courts ruling on the issue of vacatur.
However, in view of the federal defendants’ confession of legal error as to the 2008 Critical Habitat Designation, the Court is sensitive to the need for new rulemaking for the owl to be undertaken as expeditiously as possible. Accordingly, by no later than September 30, 2010, the parties are directed to submit a joint proposed timetable to the Court addressing the length of time within which rulemaking for a new critical habitat designation for the northern spotted owl shall be completed; in the event that the parties are unable to reach a joint recommendation, each party shall submit an individual recommendation by that time. The Court will withhold issuance of its Order remanding the 2008 Critical Habitat Designation to the FWS pending resolution of this issue.
III. CONCLUSION
For the foregoing reasons, the Court GRANTS IN PART AND DENIES IN PART the federal defendants’ motion for remand and vacatur. Pursuant to the Order accompanying this Memorandum Opinion, the 2008 Recovery Plan shall be remanded forthwith for the issuance of a revised recovery plan within nine months of this Order. The Order remanding the 2008 Critical Habitat Designation, however, shall be withheld pending resolution of the timetable for the proposed rulemaking. Finally, the federal defendants’ request to vacate the 2008 Critical Habitat Designation is DENIED. The 2008 Critical Habitat Designation shall remain in force during the rulemaking period.
Notes
. Also pending before the Court is the motion of the Seattle Audubon plaintiff-intervenors for the entry of a proposed order with respect to the federal defendants’ motion for voluntaiy remand and vacatur. See Docket No. 43. Specifically, plaintiff-intervenors ask the Court to enter the proposed order filed with the federal defendants' motion. For the rea *129 sons discussed herein, the Court declines to enter the proposed order. Accordingly, Seattle Audubon’s motion for entry of the proposed order is DENIED.
. A threatened species is one that is "likely to become an endangered species within the foreseeable future throughout all or a significant portion of its range.” 16 U.S.C. § 1532(20). An endangered species is one that is "in danger of extinction throughout all or a significant portion of its range....” Id. § 1532(6).
. The ESA defines critical habitat as: (i) the specific areas within the geographical area occupied by the species, at the time it is listed in accordance with the provisions of section 4 of this Act [15 U.S.C. § 1533], on which are found those physical or biological features (I) essential to the conservation of the species and (II) which may require special management considerations or protection; and (ii) specific areas outside the geographical area occupied by the species at the time it is listed in accordance with the provisions of section 4 of this Act [15 U.S.C. § 1533], upon a determination by the Secretary that such areas are essential for the conservation of the species. 16 U.S.C. § 1532(5)(A).
.Once a species is listed as threatened or endangered, the Secretary is directed to develop and implement "recovery plans” for the conservation and survival of the species. 16 *130 U.S.C. § 1533(f)(1). A recovery plan must contain: "(i) a description of such site-specific management actions as may be necessary to achieve the plan's goal for the conservation and survival of the species; (ii) objective, measurable criteria which, when met, would result in a determination, in accordance with the provisions of this section, that the species be removed from the list; and (iii) estimates of the time required and the cost to carry out those measures needed to achieve the plan's goal and to achieve intermediate steps toward that goal.” Id.
. The decision to create a recovery plan was spurred, at least in part, by a settlement agreement that the FWS entered into with the CIC plaintiffs in an unrelated lawsuit in 2003, whereby the FWS agreed to complete rule-making to revise the critical habitat designation of the northern spotted owl by July 30, 2008. See CIC Opp’n Br. at 7-8 (explaining that the 2008 Critical Habitat Designation fulfilled the Secretary of the Interior’s obligations under the 2003 settlement agreement).
. See, e.g., 73 Fed.Reg. 47328 (“The [Managed Owl Conservation Areas] network identified in the 2008 Recovery Plan for the Northern Spotted Owl, and the [Managed Owl Conservation Areas] identified for the eastside provinces under Option 1 of the 2007 Draft Recovery Plan for the Northern Spotted Owl, serve as the basis for this revised critical habitat designation.”).
. The cases cited by the CIC plaintiffs do not persuade the Court to the contrary. In support of their argument that voluntary remand is impermissible, the CIC plaintiffs rely principally on
Home Builders Association of Northern California v. U.S. Fish & Wildlife Service,
. While the CIC plaintiffs warn that "[t]he court must be especially vigilant not to allow the 'pretext of correction,’ to mask the desire of a new administration ... to reopen a closed proceeding in order to substitute its own policies for those of its predecessors,” CIC Opp’n Br. at 17-18, the Court finds this argument unpersuasive in light of the fact that the prior administration’s investigation revealed that Deputy Assistant Secretary MacDonald had potentially jeopardized the northern spotted owls’ recovery plan.
. As an alternative argument, the federal defendants and the Seattle Audubon plaintiffintervenors ask the Court to construe the federal defendants’ proposed order as a consent decree, arguing that vacatur of a critical habitat designation without a determination of the merits is appropriate pursuant to a consent decree.
See
Seattle Audubon Reply Br. at 14;
see also
Seattle Audubon’s Post-Argument Br. at 3 (explaining that "without even reaching the merits, this Court has the power to approve settlement agreements that are fair, adequate, reasonable, and appropriate if there has been valid consent by the concerned parties” (citing
Citizens for a Better Env’t v. Gorsuch,
. Although the federal defendants and the Seattle Audubon plaintiff-intervenors assert that the Court could decide the issue on the papers already before it, the Court finds this argument unpersuasive in light of the comprehensive review that the federal defendants had to undertake to determine whether to seek voluntary remand. See Notice, Docket No. 22 at 2 ("As a result of [the IG's Report], Federal Defendants will be reviewing the decision and administrative record for this action to determine whether to continue this litigation, amend their litigation position, or pursue further administrative action with respect to this final recovery plan.”); Notice, Docket No. 35 at 2 ("[T]he Service and Department of the Interior undertook a comprehensive review of the [IG's Report] and the Service’s files for the recovery plan and revised critical habitat designation and briefed the appropriate decision-makers. The government has concluded its review and has decided that it is appropriate to seek a remand of the recovery plan and revised critical habitat designation.”).
. The federal defendants do not move the Court to vacate the final recovery plan pending its revision on remand. See Fed. Defs.’ Mot. at 12-13; see also Fed. Defs.’ Reply Br. at 2 ("Federal Defendants have sought remand without vacatur of the recovery plan principally because there is no prior recovery plan to reinstate....").
